ROYAUME DU MAROC MINISTERE DES TRAVAUX PUBLICS DIRECTION DES ROUTES ET DE LA CIRVULATION ROUTIERE

GUIDE POUR LE CHOIX DE TECHNIQUES DE CONSTRUCTION ET DENTRETIEN DES ROUTES NON REVETUES

AVRIL 1995

SOMMAIREINTRODUCTION................................................................................................................................................. 4 CONCEPTION DES ROUTES NON REVETUES............................................................................................ 5 I- INTRODUCTION .......................................................................................................................................... 5 II- DIMENSIONNEMENT ................................................................................................................................ 5 III - GEOMETRIE.............................................................................................................................................. 6 IV CHOIX DES MATERIAUX......................................................................................................................... 7 MATERIAUX POUR COUCHE DE SURFACE............................................................................................... 8 INTRODUCTION.............................................................................................................................................. 8 A - MATERIAUX GRAVELEUX ET TOUT VENANT ALLUVIONNAIRES COURANTS ........................ 8 I - GENERALITES ......................................................................................................................................... 8 II - SPECIFICATIONS .................................................................................................................................. 9 B/ TUFS ET ENCROUTEMENTS CALCAIRES ........................................................................................... 11 1 - GENERALITES ...................................................................................................................................... 11 II - SPECIFICATIONS ................................................................................................................................ 12 C/GYPSE ET ANHYDRITE ........................................................................................................................... 13 I/DEFINITION-PROPRIETES .................................................................................................................... 13 II/ - SPECIFICATIONS ............................................................................................................................... 13 DISPOSITIONS CONSTRUCTIVES POUR LEXECUTION DES ROUTES NON REVETUES ............ 15 I/ INTRODUCTION ........................................................................................................................................ 15 II/TRAVAUX DE CHAUSSEE ....................................................................................................................... 15 2-1 - Dispositions gnrales ........................................................................................................................ 15 2-2 - Cas des tufs labors........................................................................................................................... 17 2 3/- Cas des tufs tendres tout venant .................................................................................................... 18 2-4 Cas des gypses et anhydrides ................................................................................................................ 19 III/SYSTEME DE DRAINAGE....................................................................................................................... 19 IV/ FOSSES LATERAUX ............................................................................................................................... 21 V/- GUES ET RADIERS SUBMERSIBLES ................................................................................................... 24 VI/ - PONCEAUX (BUSES DALOTS) ........................................................................................................... 24 VII/ - ACCOTEMENTS................................................................................................................................... 25 STABILISATION DES SOLS............................................................................................................................ 26 I/ - LES TECHNIQUES DE STABILISATION .............................................................................................. 26 II/- CAS DES SOLS GONFLANTS TIRS....................................................................................................... 26 III/- ETUDE EN LABORATOIRE .................................................................................................................. 27 IV/ - RECOMMANDATIONS SUR LA MISE EN OEUVRE........................................................................ 27 TECHNIQUE DE LA PIERRE CASSEE ......................................................................................................... 30 I/ - PRESENTATION DE LA TECHNIQUE .................................................................................................. 30 II/ - PROPRIETE DES PIERRES .................................................................................................................... 31 III/ - CYLINDRAGE........................................................................................................................................ 31 IV/ - ARROSAGE ............................................................................................................................................ 32

ENTRETIEN ....................................................................................................................................................... 33 I/ - CHAUSSEE................................................................................................................................................ 33 1-1/ - Nivellement et profilage..................................................................................................................... 34 1-2 - Reflachage .......................................................................................................................................... 36 1-3 - Rechargement ..................................................................................................................................... 37 II/ - DRAINAGE .............................................................................................................................................. 38 2-1 - Nettoyage et rparation des ponceaux : ............................................................................................. 39 2-2 - Nettoyage des fosss............................................................................................................................ 40 2-3 - Contrle de lrosion .......................................................................................................................... 41 ANNEXE LES DEGRADATION ...................................................................................................................... 43 I/ - ORNIERAGE ............................................................................................................................................. 44 II - TOLE ONDULEE ...................................................................................................................................... 45 III - PERTE DE BOMBEMENT...................................................................................................................... 46 IV / NID DE POULE ....................................................................................................................................... 47 V/ - RAVINEMENT ........................................................................................................................................ 48 VI - ARGILE.................................................................................................................................................... 49 VII/ - PERTE DE MATERIAUX..................................................................................................................... 50 REFERENCES BIBLIOGRAPHIQUES .......................................................................................................... 52

INTRODUCTIONLes routes non revtues prsentent comme particularit une absence de revtement qui protge le corps de chausse contre des sollicitations dues au trafic eu au climat. Donc si on adopte la solution, route non revtue , on doit admettre un entretien beaucoup plus frquent que dans le cas des routes revtues. On peut dire que la route non revtue est allergique aux effets climatiques mme trafic nul. De ce fait elle ncessite des dispositions quau moment de lentretien. Ces dispositions concernent les matriaux qui doivent avoir un comportement acceptable et un cot minimal et les procds de construction. Le prsent document regroupe essentiellement les diffrents types de matriaux qui peuvent tre utiliss en couche de roulement ainsi quun ensemble de dispositions constructives relatives lexcution des travaux et lentretien. Il est labor spcialement pour les routes rurales marocaines o souvent le trafic ne dpasse pas 150 vhicules par jour. De ce fait, il ne prtend pas tre applicable dans le cas gnral o le trafic peut tre lourd et agressif comme le cas des routes de desserte dexploitation minire par exemple qui, bien que dpourvues de couche de roulement, exigent quand mme une structure similaire celles des routes fort trafic. Cest pourquoi dans le prsent document on ne parle que dune seule couche appele indiffremment couche damlioration , couche de surface ou