GestioneRischi HSE Inglese

download GestioneRischi HSE Inglese

of 52

Transcript of GestioneRischi HSE Inglese

  • 7/29/2019 GestioneRischi HSE Inglese

    1/52

  • 7/29/2019 GestioneRischi HSE Inglese

    2/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 2 of52

    INDEX

    EXECUTIVE SUMMARY 4

    ACRONYMS, ABBREVIATIONS 4

    1. SCOPE AND APPLICATION 12

    2. RISK AND CATEGORIES OF RISK 13

    2.1 EVENT RISK 13

    2.2 RISKS TO PEOPLE (HEALTH AND SAFETY) 13

    2.3 RISKS TO CRITICAL EQUIPMENT AND FACILITIES 13

    2.4 ENVIRONMENTAL RISK 14

    2.5 ASSET RISK 14

    2.6 REPUTATION RISK 14

    3. RISK MANAGEMENT PROCESS 15

    3 1 IDENTIFICATIONOF HAZARDS AND EFFECTS 16

  • 7/29/2019 GestioneRischi HSE Inglese

    3/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 3 of52

    6.3 RISK REGISTERS 27

    7. RESPONSIBILITY / ACCOUNTABILITY / OWNERSHIP 28

    APPENDIXA. MEASUREMENT OF RISK TO PEOPLE 33

    B1. EVENT RISK SCREENING MATRIX 39

    B2. PERSONNEL (TASK)RISKASSESSMENT MATRIX 40

    B3. RISK TO PEOPLE (OPERATIONS )ASSESSMENT MATRIX 41

    B4. SOCIETAL RISK MATRIX 42

    B5. ENVIRONMENTAL RISK MATRIX 43

    B6. ASSET RISK MATRIX 44

    B7. REPUTATION RISK MATRIX 45

    B8. SOCIAL RESPONSIBILITY 46

    APPENDIX C.ALARP AND COSTS-BENEFITSANALYSIS 47

    APPENDIX D RISK REGISTER PROFORMAS 50

  • 7/29/2019 GestioneRischi HSE Inglese

    4/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 4 of52

    EXECUTIVE SUMMARY

    Risk Management is a basic requirement for the development of a Health, Safety, Environment,

    Quality and Radiation Protection Integrated Management System (HSE IMS).

    Eni E&P Division HSE Directives (Ref. 8) outline what must be done for Risk Management,

    whereas Application Requirements address how to implement those directives to achieve a correct

    management of HSE risks within the business and operations.

    The purpose of this document is to establish a framework for the Risk Management processes and

    the establishment of risk management criteria, according to Eni E&P Division HSE Directives and

    Application Requirements, in order to ensure that the HSE risks are managed to a consistent and

    acceptable level across all operations.

    ACRONYMS, ABBREVIATIONS

    ALARP As Low As Reasonably Practicable

  • 7/29/2019 GestioneRischi HSE Inglese

    5/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 5 of52

    GLOSSARY

    Acceptable Risk / Acceptability

    See Tolerable Risk (ISO 17776:2000).

    Accident

    Undesired event giving rise to death, ill health, injury, damage or other loss (OHSAS 18002:2000).

    An alternative simpler definition: unplanned event giving rise to undesired outcome (death, ill

    health).

    ACGIH

    The American Conference of Governmental Industrial Hygienists (see http://www.acgih.org/ )

    ALARP (As Low As Reasonably Practicable)

    The point at which the effort to introduce further reduction measures become unreasonably

    disproportionate to the additional risk reduction that will be obtained The concept of ALARP may

  • 7/29/2019 GestioneRischi HSE Inglese

    6/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 6 of52

    Hazard

    Anything with the potential to cause harm, including ill health or injury, damage to property, plant,

    products or the environment; production losses or increased liabilities. (OGP report 6.36/210, 1994

    Guidelines for the development and application of health, safety and environmental management

    systems).

    Hazardous event

    A hazardous event is synonymous with a hazard.

    HSE Integrated Management System (HSE IMS)

    Part of the overall management system that enables the management of the HSE risks associated

    with the business of the organisation. This includes the organisational structure, planning activities,

    responsibilities, practices, procedures, processes and resources for developing, implementing,

    achieving, reviewing and maintaining the organisations HSE Policy.

    To the purposes of this document, all references to HSE IMS are contained in Ref. 8.

  • 7/29/2019 GestioneRischi HSE Inglese

    7/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 7 of52

    LC% hmn - Lethal Concentration for Humans

    A concentration by which a given percentage of the exposed population will be fatally injured,

    following a certain period of exposure.

    LFL - Lower Flammability LimitThe lowest concentration of the substance (vapour or gas) in air that is known to produce a flash of

    fire when an ignition source is present.

    NORSOK

    Norwegian Technology Centre standards (see

    http://committees.api.org/standards/isotc67/links_other.html)

    Occupational illness

    An occupational illness is any abnormal condition or disorder of an employee, other than one

    resulting from an occupational injury, caused by exposure to environmental factors associated with

    employment. (Record-keeping Guidelines for Occupational Injuries and Illnesses, Occupational

    S f t d H lth A t OSHA USA 1986) Thi i l d b th t d h i ill

  • 7/29/2019 GestioneRischi HSE Inglese

    8/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 8 of52

    OGP

    International Association of Oil & Gas Producers (seehttp://www.ogp.org.uk/)

    OLF

    Oljeindustriens Landsforening (see http://www.olf.no/ )

    OHSAS

    Occupational Health & Safety Advisory Services(seehttp://ohsas.org/)

    OREDA

    Offshore Reliability DAta (see http://www.sintef.org/ )

    Qualitative Risk Assessment

    Generic term used for techniques which allow the risk associated with a particular activity to be

    estimated in relative terms such as high or low (ISO 17776:2000).

  • 7/29/2019 GestioneRischi HSE Inglese

    9/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 9 of52

    Risk Evaluation

    Judgement, on the basis of risk analysis, of whether a risk is tolerable (ISO 17776:2000).

    Risk Register

    Document proving a brief, but complete, overview of the identified hazards, the relevant screening

    criteria and the measures necessary to manage them.

    Screening Criteria

    Targets or standards used to judge the tolerability of an identified hazard or effect (ISO

    17776:2000). For the purpose of this document, they have been developed by Eni E&P division

    and are intended for use where not provided by regulators.

    Societal Risk

    The risks to society arising from operations; the term society in this context include communities,

    residential areas and, in general, the public domain which is not connected with those operations

    (the Canvey Study HSE, 1978).

  • 7/29/2019 GestioneRischi HSE Inglese

    10/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 10 of52

    INTRODUCTION

    Management of HSE risks is an integral part of the management of the business and requires the

    total concerted effort of the organisation, focused on the objective of protecting people, theenvironment, assets, the business and earnings from potential losses. The Eni E&P Division HSE

    Integrated Management System has been developed to provide the overall framework for

    management of HSE risks within the business and operations.

    This document forms an integral part of the HSE IMS and sets out the Eni E&P Division Risk

    Management criteria. It is intended to ensure that HSE risks associated with operations are

    managed to a consistent and acceptable level across all operations.

    In addition to the requirements set in the HSE IMS Directives and Application Requirements,

    reference is also made to ISO 17776 Petroleum and natural gas industries Offshore production

    installations Guidelines on tools and techniques for hazard identification and risk assessment

    (R f 1) Th i k t d fi d i thi ISO t d d t th ith th l t HSE

  • 7/29/2019 GestioneRischi HSE Inglese

    11/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 11 of52

    Assets and Operations damage to the Companys assets and/or impacts on projects and/or

    production losses.

    Reputation damage to the business or to the License to Operate or to the overall value of

    the Company deriving from HSE risks; it includes, inter alia, the image.

    The risk management criteria must be applied as part of a broader risk management process within

    the organisation.

    It is important to remember that most activities which carry some degree of risk, entail risk

    to more than one of the above areas. It is vital that all possible effects of a hazard are

    considered together. For example an activity entailing risk to company profits must not be

    considered in isolation to its effect on the HSE. It is difficult to determine a hierarchy of importance

    in the risk effect areas mentioned above, but by common consent the effect of a hazard on

    persons, including HSE effects, carries most weight and the effect on assets and profits least

    weight.

  • 7/29/2019 GestioneRischi HSE Inglese

    12/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 12 of52

    1. SCOPE AND APPLICATION

    The primary scope of this document is to provide a guidance for definition of risk tolerability criteria

    which is applicable to all Eni E&P Division locations and operations and shall be kept into

    consideration for all risk identification and assessment activities as required by the HSE IMS.

    The application of risk tolerability criteria as a management tool requires specific skills and

    expertise. Specialist advice should be sought where necessary.

    Where specific regulatory requirements exist in a particular location, the most stringent

    requirements apply.

    The document is also aimed at giving guidance on the practical application of risk management

    criteria, which shall be used only once all legislative prescriptions have been properly

    applied. Chapter 2 contains an overview of risk categories.

    Chapter 3 deals with the general concept of risk, providing an overview of the risk management

    process.

    f C

  • 7/29/2019 GestioneRischi HSE Inglese

    13/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 13 of52

    2. RISK AND CATEGORIES OF RISK

    2.1 EVENT RISK

    Risk is a function of the likelihood of an event and the severity of its consequences. The risk from a

    particular event, the Event Risk is the HSE risk associated with a specific, discrete scenario (such

    as helicopter crash, transport accident, oil spill, etc.) in terms of effects on people, environment,

    assets and reputation and is usually assessed qualitatively.

    2.2 RISKS TO PEOPLE (HEALTH AND SAFETY)

    Hazardous activities may result in injury, fatality or diseases both to those personnel engaged in

    work associated with the activity or to community. Risks to people may be divided into:

    ) f f f

  • 7/29/2019 GestioneRischi HSE Inglese

    14/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 14 of52

    2.4ENVIRONMENTAL RISK

    The Environmental Risk is the risk to the environment from different activities that fall under the

    responsibility of the Company. As a consequence, environmental risk management should take

    account of the exposure of the environmental resources to a variety of activities which constitute,

    as a whole, the sustainable development of the Company itself.

    2.5ASSET RISK

    The Asset Risk considers the probability of damage to Companys physical assets, impacts on

    projects (failure to meet project objectives) and operations in terms of production loss, deferred

    production and costs of replacement of damaged structures and equipment due to any incidents.

    2.6REPUTATION RISK

    Reputation risk is the risk to the reputation of a Company as perceived by society at large, or

  • 7/29/2019 GestioneRischi HSE Inglese

    15/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 15 of52

    3. RISK MANAGEMENT PROCESS

    The Risk Management Process (see Figure 1), as outlined in Eni E&P Division HSE Directives

    (Ref. 8), is a continuous, iterative process, which typically consists of four major tasks:

    1. Identification and definition of hazards and their potential effects.

    2. Evaluation of the risk arising from identified hazards in terms of evaluation of the likelihood /

    probability / frequency of occurrence of accident sequences and evaluation of severity of the

    consequences.

    3. Assessment of tolerability of risk to people, environment, assets and reputation by

    comparing risk level with the relevant tolerability criteria.

    4. Identification of risk reduction measures needed to reduce the likelihood / probability /

    frequency (prevention) and/or the consequence of an accident (control and mitigation).

    Identification of

    Hazards andEffects

  • 7/29/2019 GestioneRischi HSE Inglese

    16/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 16 of52

    3.1 IDENTIFICATION OF HAZARDS AND EFFECTS

    The identification of potential HSE hazards and effects covers all phases of the Companys

    processes and related activities at the appropriate level of accuracy, taking also into account all

    phases in the life of any installation, including temporary conditions dictated by maintenance

    activities.

    For each activity, the most significant hazards are identified and the likely effects are then

    assessed to determine whether each hazard is significant or not in relation to health, environment,

    assets and Company reputation.

    3.2 RISK EVALUATION (REF.HSEIMSB-1.3)

    Risk evaluation requires consideration of both the severity of the consequences of a potential

    hazard and the likelihood of their realisation.

    Each risk is assessed by consideration of the following factors:

    how often the hazard is likely to occur;

    the likelihood of the hazard resulting in an accident;

  • 7/29/2019 GestioneRischi HSE Inglese

    17/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 17 of52

    3.4 IDENTIFICATION OF RISK REDUCTION MEASURES (REF HSEIMSB-1.5)

    Risk reduction measures may prevent incidents or reduce the probability of their occurrence,

    control incidents (limiting the extent and duration of a hazardous event) or mitigate adverse effects

    (reducing the severity of consequences).

    4. RISK IDENTIFICATION AND EVALUATION

    A systematic approach to the identification of hazards and the evaluation of risk is a key element of

    effective HSE management, providing information to support decision-making on risk-reduction

    measures.

    For new installations or activities hazards shall be identified as early as possible, in order that

    sufficient time can be given to the most appropriate way to manage them. It is always easier to

    make modifications early in the design stage of a project, when changes can be made with minimal

    effect on cost and schedule.

    Hazard analysis and risk assessment shall also be applied to existing facilities, but in some cases

  • 7/29/2019 GestioneRischi HSE Inglese

    18/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 18 of52

    Experience from previous analyses, safety inspections and audits

    This is particularly useful where the activity under consideration is similar to activities

    undertaken previously in other locations. The approach is not suitable when dealing with

    innovative systems or where local conditions invalidate previous experiences.

    Use of checklists and accident statistics

    Checklists are normally drawn up from standards and operational experience and ensure that

    known hazards have all been identified and assessed. They are easy to apply and can be

    used at any phase in the project life cycle.

    Examples of Hazard checklists are provided in ISO 17776 (Ref.1).

    Codes and standards

    Codes and standards reflect collective knowledge and experience, accumulated on the basis

    of Company, national or international operations. These documents incorporate the lessons

    learned from previous design, from hazard and risk assessment and from accident and

    incident investigation. The compliance with prescriptive standards ensures the reduction of

  • 7/29/2019 GestioneRischi HSE Inglese

    19/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 19 of52

    simple narrative form, using multiple branch event trees and utilising more or less complex

    computerised modelling techniques.

    Since the majority of models provides only an approximation of what might happen, models should

    only be used when they are validated in a particular application and their predictive capability is

    generally accepted.

    Successful application requires use by personnel with adequate training and experience.

    As far as possible, consequence analysis should also assess the contribution to failure from human

    and organisational factors, together with the contribution from such failures to dependent failures

    (escalation).

    The following analysis methods may be used for the escalation analysis:

    Event Tree Analysis (ETA)

    Simulation/ probabilistic analysis

    More details about these techniques can be found in ISO 17776.

  • 7/29/2019 GestioneRischi HSE Inglese

    20/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 20 of52

    4.4 MEASUREMENT OF RISK

    In order to interpret risk to people, reputation etc. some means of measurement of risk is required.

    Since risk is in its simplest terms consequences times frequency, obvious types of measure may

    be:

    Fatalities / occupational illness per year ( risk to people)

    Spills per transfer operation (risk to the environment)

    Financial losses per year (asset losses)

    Apart from financial loss which is relatively easy to measure in risk terms, all other areas presentproblems. Environmental risk is particularly difficult to define except in terms of specific items such

    as spills as detailed above. Some of the problems with the measurement of environmental risk are

    described below:

    Some environmental discharges are continuous but have indeterminate effects

    Some environmental hazards are short term in duration but have long term effects changing

  • 7/29/2019 GestioneRischi HSE Inglese

    21/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 21 of52

    5. RISK TOLERABILITY CRITERIA

    Measurement of risk is the preliminary phase of assessing its acceptability (tolerability). It is

    necessary to compare risk figures with acceptability/tolerability thresholds in order to determine

    whether the risk is fully acceptable, completely intolerable or somewhere in between.

    5.1 EVENT RISK SCREENING MATRIX

    A preliminary measure in the global assessment of risk is the Event Risk Screening Matrix reported

    in Appendix B1. This provides definition of consequences and a range of qualitative criteria to

    estimate probability or frequency for risks to people, the environment, etc. The meaning of the

    terms in the matrix, such as continuous improvement, etc is explained below in section 5.2.

    This matrix is mandatory in the identification of high level HSE Risks during risk screening

    (Major Hazard Analysis, Environmental Impact Assessment etc.). This matrix provides the

    basis to identify significant risks or areas of risk and prioritise further assessment and

    management efforts.

    Risk screening matrices are suitable to be linked with other means of assessing tolerability,

  • 7/29/2019 GestioneRischi HSE Inglese

    22/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 22 of52

    The horizontal axis represents the measure of likelihood / probability / frequency of the occurrence

    of a hazardous event. Such a scale is defined in general terms from 0 to E on the basis of

    historical evidence or experience that such consequences have materialised within E&P industry or

    the Company.

    The risk matrices included in Appendices, are separated in three regions that identify the limit of

    risk tolerability; such regions are:

    1. Continuous

    improvement

    The level of risk is broadly acceptable and generic control

    measures are required aimed at avoiding deterioration.

    2. Risk reduction

    measure

    The level of risk can be tolerable only once a structured review of

    risk-reduction measures has been carried out (where necessary,

    the relevant guidance from the local Authorities should be adopted

    for application of ALARP). ALARP is a concept that applies well

    only to personnel risk. For environmental risk the concept of BPEO

  • 7/29/2019 GestioneRischi HSE Inglese

    23/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 23 of52

    significant risks or areas of risk (for example, transportation risk) and prioritise further assessment

    and management efforts.

    Should the qualitative risk figure be intolerable, either a quantitative risk analysis (QRA) or

    the adoption of fit-for-purpose and more effective risk-reduction measures shall be

    required.

    5.2.2. Personnel Risk (Tasks)

    When considering Occupational Health and Safety Risk Assessment related to specific tasks, a

    qualitative approach is preferred, since it is usually based on past experience.

    The Personnel (Task) Risk Assessment Matrix is based on the document Task Risk Assessment

    Guide - A step change in safety (Ref 2) and is reported in Appendix B2

    The occupational health risk (occupational illness or injury) is usually based on exposure to

    hazardous agents (physical, chemical, etc.); this is covered by specific Minimum Health

    Standards (Ref. 9).

  • 7/29/2019 GestioneRischi HSE Inglese

    24/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 24 of52

    As far as consequences are concerned, a list of options is shown; they are intended not to be used

    contemporarily; for example, in sensitive areas, the option based onamount of spilled oil is not

    suitable, and is preferable to adopt options related to protection of fauna and flora.

    5.2.5. Asset Risk

    The asset risk matrix is reported in Appendix B6. Even in this case, different options are shown to

    describe consequences, based on times and costs for repair.

    As far as probability / frequency is concerned, both quantitative and qualitative criteria are shown,

    where the latter is based on reliability of technical / operational protection systems, such as

    temporary refuges, control systems etc. (see also 2.3). The reliability is expressed in terms of

    minimum number of failures needed for the hazard to be realized (higher the number of failures,

    higher the number of barriers against the hazardous event).

    5.2.6. Reputation Risk

  • 7/29/2019 GestioneRischi HSE Inglese

    25/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 25 of52

    1) Identify hazardous events, considering techniques such as Event Trees (see 4.2 and

    4.3);

    2) Consider the accidental loads (e.g. radiation from fires) and, hence, the damage/harm

    deriving from the hazardous event to: an employee, a man of the public (risk to people), a

    plant section (asset risk) etc;

    3) Sum up frequencies of all hazardous events of the same nature (all gas releases, all fires,

    all explosions etc.) with same consequences (harm to an employee, a man of the public, a

    group of people, an area with a given occupancy see Ref. 7 - etc.);

    4) Enter the suitable risk matrix and verify tolerability;

    5) If unacceptable, assess what controls are viable;

    6) Determine if the risk, which is residual after controls, will be manageable;

    7) If still unacceptable, consider further mitigating factors (reduction of % of manning, chance

    of sheltered escape, favourable wind directions, extra controls etc.) to re-conduct the event

    in the acceptable area;

  • 7/29/2019 GestioneRischi HSE Inglese

    26/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 26 of52

    6.2 IDENTIFICATION,DEVELOPMENT AND IMPLEMENTATION OF CONTROLS

    Risk reduction measures include preventative measures (reduction of likelihood / probability /

    frequency) and mitigating measures (reduction of severity of consequences). Mitigation measures

    include steps to prevent escalation of developing abnormal situations and to lessen adverse effects

    on Health, Safety and the Environment.

    Risk reduction measures also include recovery preparedness measures, which address emergency

    procedures as well as restoration and Company procedures to recover.

    In identifying control measures, consideration should be given to:

    The activity

    The people involved

    What tools, equipment and materials are to be used

    The working environment

    The remedial measures needed to control each of the intolerable risks should be based on good

    safe working practice in order to reduce the residual risks to a level which is practicable.

  • 7/29/2019 GestioneRischi HSE Inglese

    27/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 27 of52

    Evaluation of risk-reducing measures should always be based on sound engineering principles and

    common sense. The following aspects should also be observed: local conditions and

    circumstances, the state of scientific and technical knowledge relating to the particular situation,

    and the estimated costs and benefits. See Appendix C for further information on Costs-Benefits

    analyses.

    It must be clear in any case that no level of risk of fatality for anyone person is acceptable.

    6.3 RISK REGISTERS

    From the risk identification process a list of significant risks should be identified and transferred to

    Risk Registers for that particular project / operating unit. The Risk Registers should demonstrate

    that:

    (probability of the hazard) x (costs if it realizes) = expected cost from the risk

  • 7/29/2019 GestioneRischi HSE Inglese

    28/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 28 of52

  • 7/29/2019 GestioneRischi HSE Inglese

    29/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 29 of52

    Risk Screening Matrix (which includes risks related to the Company HQ) for executive management

    perusal.

    The Company will submit to the BU and E&P Division HSE Function the Risk Screening Matrix with

    the relevant Action Plan aimed at implementing suitable risk reduction measures and demonstrating

    the sustainability of residual risks.

    The BUs will consolidate the Risk Matrixes in agreement with the E&P Division HSE Function and

    will communicate a summary to the Eni Corporate HSE Function (Ref. 0).

  • 7/29/2019 GestioneRischi HSE Inglese

    30/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 30 of52

    REFERENCE DOCUMENTS

    Ref.0 Eni DIHSE: Modello di Sistema di Gestione per la tutela della salute, della sicurezza,

    dellambiente e dellincolumit pubblica doc. 1.1/3 19/12/03

    Ref.1 EN ISO 17776: 2000 "Petroleum and natural gas industries - Offshore productioninstallations - Guidelines on tools and techniques for hazard identification and risk

    assessment ".

    Ref.2 "Task Risk Assessment Guide A Step Change in Safety" UKOOA, IMCA, IADC, IAGC

    OPITO, (August 2000)

    Ref.3 E&P Forum QRA Data Sheet Directory 15/10/96

    Ref.4 IEC 61508 "Functional safety of electrical / electronic / programmable electronic safety

    related system (all parts)

    IEC 61511 "Functional safety instrumented systems for the process industry sector (all

    parts)

    Ref.5 UKOOA 95

  • 7/29/2019 GestioneRischi HSE Inglese

    31/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 31 of52

    MHS 8 Human Factors Engineering in New Projects

    BACKGROUND REFERENCES:

    Ref. 10 UK HSE - (1989) "Quantified Risk Assessment an Input to Decision Making" ISBN 0

    11 885499 2

    Ref. 11 UK Health and Safety Executive R2P2

    Ref. 12 NORSOK Standard Z-013 Rev.2 - (2002) "Risk and emergency preparedness analysis"

  • 7/29/2019 GestioneRischi HSE Inglese

    32/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 32 of52

    APPENDICES

  • 7/29/2019 GestioneRischi HSE Inglese

    33/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 33 of52

    APPENDIX A

    MEASUREMENT OF RISK TO PEOPLE

  • 7/29/2019 GestioneRischi HSE Inglese

    34/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 34 of52

    Risk

    Risk to people (usually, personnel or, generally speaking, workers) can be measured in terms ofrisk of exposure (Ref. 9) , risk of injury or risk of fatality. Normally in quantitative risk assessments

    the fatality risk is considered, while for the other risks a qualitative approach is adopted.

    Risk can be measured in a generalised way such as high, medium and low where these terms

    refer to comparative indications of risk for the industry or activity under review. Alternatively it can

    be measured in specific terms where an attempt is made to calculate the average probability ofinjury or death in a specific time period either to an individual or to a group of people.

    General Measurement of Risk

  • 7/29/2019 GestioneRischi HSE Inglese

    35/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 35 of52

    Specific Measurement of Risk

    Risk to Individuals

    The method of measurement, which has become increasingly used in recent years, is individual risk

    (IR). This is the risk of fatality to any person exposed to a hazard normally averaged over a year.

    Individual risk can be specific to a particular individual, averaged over those individuals in a high

    risk group, or averaged across all persons in a potentially high risk location (e.g. where high H2S

    levels are expected in the reservoir). In measuring individual risk the changes in exposure of

    persons, for example by moving away from or closer to the hazard over a period of time is taken

    into account. Individual risk may also be assigned to specific locations.

    Calculation of Individual Risk

    Consider a particular location at risk from a hazardous event nearby. The individual risk from the

    event following realisation of the hazard is calculated as follows.

  • 7/29/2019 GestioneRischi HSE Inglese

    36/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 36 of52

    IR = z(n/N)p1p3

    where p1 = fatality probability

    z = event frequency

    n = the average number of persons present at the affected location

    N = the total workforce on site (all assumed to work for similar number of hours per week)

    and p3 = proportion of time for which the person is present on site

    Should other information (such as % of success of escape or evacuation; % of favourable winds

    etc.) become available, the overall IR figure can be progressively refined to keep account of these

    parameters.

    In summary, it is possible to calculate a coarse IR and a refined IR, with due regards to reliability

    of available data.

  • 7/29/2019 GestioneRischi HSE Inglese

    37/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 37 of52

    Risk to Groups

    Individual risk to specific persons may be low in particular situations but due to the large number of

    persons exposed, the possibility of fatality may be significant. In these situations it may be

    appropriate to determine the Potential Loss of Life (PLL). This is a measure of how many persons

    would become fatalities from a particular site or event, normally expressed over a period of time.

    Calculation of PLL

    Consider a particular location at risk from a hazardous event nearby. The potential loss of life (PLL)

    from the event following realisation of the hazard is calculated as follows. The event frequency is z.

    PLL = zp1n

    where p1 = fatality probability

  • 7/29/2019 GestioneRischi HSE Inglese

    38/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 38 of52

    APPENDIX B

    RISK MATRICES

  • 7/29/2019 GestioneRischi HSE Inglese

    39/52

    HSE Risk ManagementEni S.p.A.

    E&PDivision1.3.0.03 Page 39 of51

    B1.EVENT RISKSCREENING MATRIX

    Consequence Increasing Annual Frequency0 A B C D E

    Practically non-credible

    occurrence

    Rareoccurrence

    Unlikelyoccurrence

    Credibleoccurrence

    Probableoccurrence

    Likely/Frequentoccurrence

    Severity

    People

    Environ.

    Assets

    Reputation

    Could happen

    in E&P

    industry

    Reported for

    E&P industry

    Has occurred

    at least once

    in Company

    Has occurred

    several times

    in Company

    Happens

    several

    times/y in

    Company

    Happens

    several

    times/y in

    one location

    1 Slight healtheffect / injurySlighteffect

    Slightdamage

    Slightimpact

    Cont inuous Improvement

    2 Minor healtheffect / injury

    Minoreffect

    Minordamage

    Minor

    impactRisk Reduction Measures

    3 Major healtheffect / injury

    Local

    effect

    Localdamage

    Local

    impact

    4 PTD(*) or 1fatality

    Majoreffect

    Majordamage

    Nationalimpact

    Intolerable Risk

    5 Multiplefatalities

    Extensiveeffect

    Extensivedamage

    Internationalimpact

    (*) Permanent Total Disability

  • 7/29/2019 GestioneRischi HSE Inglese

    40/52

    HSE Risk ManagementEni S.p.A.

    E&PDivision1.3.0.03 Page 40 of52

    B2. PERSONNEL (TASK)RISK ASSESSMENT MATRIX

    0 A B C D E

    Not

    Applicable

    Not

    Applicable

    Could occur,

    when

    additional

    factors are

    present;

    otherwise

    unlikely.

    Not certain to

    happen but

    an additional

    factor may

    result in an

    accident/

    exposure.

    Almost

    inevitable

    than an

    accident/

    exposure

    would result

    Almost

    inevitable

    that more

    than one

    accident/

    exposure

    would resultSeverity

    Personnel (Task) Risk

    N/A N/AHas occurredat least once

    in Company

    Has occurredseveral times

    in Company

    Happensseveral times

    a year inCompany

    Happensseveral

    times/y inone location

    1 (NOT APPLICABLE) Cont inuous Improvement

    2Minor health effect / injury:

    offsite medical treatment or LTA;up to 10 days off.

    Agents have reversible effects to health.

    3

    Major health effect / injury:more than 1 LTA; up to 30 days off.

    Agents have irreversible effects to health:noise, manual handling, toxics, etc.

    Risk Reduct ion

    Measure

    4PTD (*) or 1 fatality:

    agents are capable

    of serious disability or death

    5Multiple fatalities

    from an accident or occupational illness (e.g. chemicalasphyxiation or cancer or epidemic diseases)

    Intolerable Risk

    (*) Permanent Total Disability

    HSE Ri k M t

  • 7/29/2019 GestioneRischi HSE Inglese

    41/52

    HSE Risk ManagementEni S.p.A.

    E&PDivision1.3.0.03 Page 41 of52

    B3.RISK TO PEOPLE (OPERATIONS)ASSESSMENT MATRIX

    0 A B C D E1

    occ/y (1)

    Severity Risk for People

    (E&P Operations) Could happenin E&P

    industry

    Reported for

    E&P industry

    Has occurred

    at least once in

    Company

    Has occurred

    several times

    in Company

    Happens

    several times/y

    in Company

    Happens

    several times/

    in one location

    1 Slight health effect / injury Cont inuous Improvement

    2 Minor health effect / injury Risk Reduction Measures

    3 Major health effect / injury

    Compulsoryreduction

    measures for

    3rd parties

    onshore

    4Permanent Total Disability or 1 fatality

    (small exposed population)

    Intolerable for

    3rd

    parties

    onshore

    5Multiple fatalities

    (exposed groups)Intolerable Risk

    (1) frequency expressed in occurrencies per year

    HSE Risk Management

  • 7/29/2019 GestioneRischi HSE Inglese

    42/52

    HSE Risk ManagementEni S.p.A.

    E&PDivision1.3.0.03 Page 42 of52

    B4.SOCIETAL RISKMATRIX

    Societal Risk 0 A B C D E

    Severity

    Radiation

    (kW/m2)

    (assuming

    unobstructedescape to

    repair)

    Flash Fire Overpres-sure

    (mbar)

    Toxicity

    (ppm)

    (based on 30

    min eventduration)

  • 7/29/2019 GestioneRischi HSE Inglese

    43/52

    Eni S.p.A.E&PDivision

    1.3.0.03 Page 43 of52

    B5. ENVIRONMENTAL RISK MANAGEMENT

    0 A B C D E

    Severity

    Environmental Risk 1occ/urrencies

    per year

    1Slight effect

    a) No stakeholder impact b) temporary impact on the area -c) Involved area < 0.1 sq mile (0.26 km

    2)

    d) Onshore spill (1)< 1 m3

    e) No sensitive impact on ground. Cont inuous improvement

    2

    Minor effecta) Some local stakeholder concern b) 1 year for natural

    recovery c) Impact on small no. of not compromised species.

    d) Involved area < 1 sq mile (2.6 km2)

    e) Onshore spill (1)< 10 m3

    f) Impact on localised ground. Risk reduct ion m easures

    3

    Local effecta) Regional stakeholder concern b) 1-2 years for natural

    recovery c)1 week for clean-up d) Threatening to somespecies - e) Impact on protected natural areas.

    f) Involved area < 10 sq miles (26 km2) g) Onshore spill (1) 5 years for natural recovery d) > 5 months

    for clean-up e) Reduction of biodiversity f) Impact on specialconservation areas - g) Involved area > 100 sq miles (260 km

    2)

    h) Onshore spill (1)> 1000 m3.

    Intolerable r isk

    (1) to be reduced of a factor 10 for offshore spill and a factor 100 for sensitive areas

    HSE Risk ManagementEni S p A

  • 7/29/2019 GestioneRischi HSE Inglese

    44/52

    HSE Risk ManagementEni S.p.A.

    E&PDivision1.3.0.03 Page 44 of52

    B6.ASSET RISK MATRIX0 A B C D E

    1 occ/y

    Severity

    Risks to Assets/ProjectObjectives

    costs in USD figures below shall not be combined

    for deriving the value of a humanlife!

    Always

    outcome of 2 or

    more

    concurrent

    failures (*)

    Usually

    outcome of 2

    concurrent

    failures (*)

    (Very Low

    Probability)

    Likely outcome

    of 2 concurrent

    failures (*)

    (Low

    Probability)

    Could be

    outcome of 2

    concurrent

    failures (*)

    (High

    Probability)

    Could be

    outcome of a

    single failure

    Is outcome of

    a single failure

    1 Slight damageNo disruption to operations/business. Cont inuous improvement

    2Minor damage

    Possible short disruption of operations/business:repair cost < 200000; production downtime < 1 day.

    Risk reduct ion m easures

    3Local damage

    The unit has been repaired/replaced to resume operations:

    repair cost < 2500000; production downtime < 1 week.

    4Major damage

    Long time/Major change to resume operations/business:

    repair cost < 25000000; production downtime < 3 months.

    Major inquiry for the damage cost.

    5

    Extensive damageTotal loss of operations/business.

    Revamping necessary to resume the process:

    repair cost > 25000000; production downtime > 3months.Extensive inquiry for the damage cost.

    Intolerable risk

    (*) failures of Critical Systems protecting people (escapeways to temporary refuges, control systems, emergency systems etc.)

  • 7/29/2019 GestioneRischi HSE Inglese

    45/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 45 of52

    B7.REPUTATION RISK MATRIX

    0 A B C D E

    Could

    happen in

    E&P

    industry

    Reported

    for E&P

    industry

    Has

    occurred

    at least

    once in

    Company

    Has

    occurred

    several

    times in

    Company

    Happens

    several

    times/y in

    Company

    Happens

    several

    times/y in

    one

    locationSeverity

    Reputation Risk

    Non-

    credible

    occurrence

    Rare

    occurrence

    Unlikely

    occurrence

    Credible

    Occurrence

    Probable

    occurrence

    Likely/

    Frequent

    Occurrence

    1Slight impact

    Minor and short lived impact in the loca lity

    Continuous

    improvement

    2Minor impact

    Some loss of reputation in the area, which should berecovered

  • 7/29/2019 GestioneRischi HSE Inglese

    46/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 46 of52

    B8. SOCIAL RESPONSIBILITY

    This aspect covers a range of subject areas including inter alia: business ethics, communities,

    workforce/labour, human rights, land and indigenous rights and security forces. Consequences of

    poor management, breaches of legislation or standards or incidents in this respect will essentially

    result in loss to people, assets or reputation of one form or another.

    Where it is necessary to make an assessment of risk the risks/scenario in question should be

    compared against the appropriate matrix and criteria.

  • 7/29/2019 GestioneRischi HSE Inglese

    47/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 47 of52

    APPENDIX C

    ALARP AND COSTS-BENEFITS ANALYSIS

  • 7/29/2019 GestioneRischi HSE Inglese

    48/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 48 of52

    ALARP

    Where risks are very low whether to personnel, the environment, assets or reputation then the

    situation may be considered acceptable. On the other hand where risks are high, good operating

    practices and often the law, requires that they be reduced. Where risk exists in the region in

    between, normally called the ALARP region especially where the risks are safety risks, a more

    structured approach is required. In the ALARP region a reduction in risk is justified unless it is

    grossly disproportionate to the benefits gained. In practice many risks fall in this region and so what

    is often known as an ALARP case should be made for each of these. Sometimes this is possible by

    discussion alone. For example, where hazardous activity is not known to have any safer alternative

    and where personnel exposure cannot be further reduced, an ALARP case may be presented in

    such terms without recourse to more detailed analysis. However where a range of protective

    measures exists each entailing some cost, unless the cost can be accepted, further analysis is

    required.

    This analysis is usually based on a cost-benefits analysis described below.

  • 7/29/2019 GestioneRischi HSE Inglese

    49/52

    HSE Risk ManagementEni S.p.A.E&PDivision

    1.3.0.03 Page 49 of52

    profits. For risks to personnel the easiest approach is to place a monetary value on technical and

    operational efforts made to save human life.

    It is implicit to this approach that low-cost measures are implemented in any case.

    Costs-benefits analyses are very difficult to perform where the principal risks are to the environment

    or to reputation due to the difficulties in estimating the benefits obtained from improvements in

    these areas.

    Limitations of Costs-Benefits Analyses

    ALARP type arguments cannot and must not be made as a means of avoiding basic levels of

    protection to personnel. It is a requirement of many laws and codes and standards that some

    means are available to allow personnel who may be exposed to a reasonably foreseeable hazard,

    of saving their life. Examples are lifejackets, lifeboats and liferafts on boats and offshore

    installations, lifejackets and breathing masks on airplanes, and fire alarm systems, and escape

    stairs in buildings.

    HSE Risk ManagementEni S.p.A.E&P Di i i

  • 7/29/2019 GestioneRischi HSE Inglese

    50/52

    E&PDivision1.3.0.03 Page 50 of52

    APPENDIX D

    RISK REGISTERPROFORMAS

    A - High Level Risk Register (Management Summ ary)

    Risk/Issue Controls in place

    LikelihdCategory

    (0-E)

    ConseqCategory

    (1-5)

    RiskCategory

    (H M L)

    Metrics Risk Reducing Measures

    Biodiversity & Environmental Sensitivity

    All activities and developments will impactand interact with the surroundingenvironment in some way. Keyconsiderations:

    Landuse/Footprint

    Ecology

    Habitats

    Physical impact

    Knowledge of hydrology/ hydro-geology/geology

    Emerging issuesmonitoring/briefing

    Effective environmental

    management system

    Proper project design

    Environment training

    Environmental/strategicimpact assessments

    Habitat management

    Site clean-up /rehabilitation

    Contractor controls

    B 3 L Numbers of peoplereceiving environ.training

    Landuse Mapping

    No. of EIAs for allactivities

    Environmentalcertification

    Ensure awareness of biodiversityissue with Senior management

    Ensure EIAs are conducted to a

    high standard for all activities

    Baseline land use GIS for keyoperations

    Rig sites/process facilities footprintdesign

    Implement HSE IMS and seekenvironmental certification

    Develop basic environmentalawareness training programme

    Consider footprint reduction targetsfor new projects

    Consider ENI R&D projects

    Facilities Safety

    Major accident in impacting people(workforce and/or community), environment,production etc.

    Corporate Audits

    Safety training/competence

    C 4 M No. of equipmentfailures causingdowntime

    Ensure project HSE reviews arepart of project managementprocess

    HSE Risk ManagementEni S.p.A.E&P Division

  • 7/29/2019 GestioneRischi HSE Inglese

    51/52

    E&PDivision1.3.0.03 Page 51 of52

    Risk/Issue Controls in place

    LikelihdCategory

    (0-E)

    ConseqCategory

    (1-5)

    RiskCategory

    (H M L)

    Metrics Risk Reducing Measures

    Project design

    planning

    construction

    commissioning

    decommissioning

    Plant integrity

    Plant age

    Maintenance

    Leaks and releases

    Pipelines

    Contractors

    Project management/design standards

    Maintenance standards

    Containment integrity

    Technology

    Operating procedures

    Audits/inspections

    Preventative/ predictivemaintenance

    Identification of safetycritical equipment

    Contractor controls

    No. inspections

    % outstandingmaintenance

    Develop criteria in the HSE IMSfor project design for newfacilities, major modification andexisting operations (HSEQ Plan).

    HSE Risk ManagementEni S.p.A.E&P Division

  • 7/29/2019 GestioneRischi HSE Inglese

    52/52

    E&PDivision1.3.0.03 Page 52 of52

    B - G.U./Subsid iary/Si te Risk Register

    Risk/Issue Controls in place

    LikelihdCategory

    (0-E)

    ConseqCategory

    (1-5)

    RiskCategory

    (H M L)Metrics Risk Reduction Measures

    Activity Exploration Project X

    Biodiversity & Environmental Sensitivity

    The X area contains many untouchedareas some with National Park status and awide range of fragile flora and fauna. Thereis little baseline information, as well asactual damage to the environment. In thisrespect there is also the potential forsignificant reputation issues.

    (A) Seismic activities have thepotential to impact significantly throughphysical disturbance and presence ofpersonnel

    (B) In the event of a good prospectand field development there existssignificant potential for permanent localimpact (water extraction, footprint, noise)

    EIA and baseline studiesfor seismic

    Proper project design

    Habitat management

    Site clean-up /rehabilitation

    C

    C

    2

    3

    L

    M Numbers of people

    receivingenvironmenttraining

    Ensure awareness of biodiversityissue with Senior Management

    Identify management objectives

    Include the issue in certificationcontrols

    Develop basic environmentalawareness training programmefor this development

    Establish links and relationshipswith nature conservation groups

    Activity Production FacilityY

    Facility Integrity

    There are several key issues with facility Y:

    Plant integrity

    Plant age

    Maintenance

    Leaks and releases

    There is an increasing risk of facility integrityissues and loss of containment with

    potential for extended loss of production andsafety of workers and public.

    Safety training

    Operating procedures

    Audits/inspections

    Maintenance

    C 4 H Near miss reporting

    No. of Equipmentfailures causingproduction losses

    Planned/completedinspections ratio

    Maintenancetargets

    Full condition survey underway

    Detailed plant reliability analysisto be performed

    Enhance maintenanceprogrammes to apredictive/preventative approach

    Identification of safety criticalequipment