Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... ·...

46
T T h h e e T T w w e e n n t t i i e e t t h h S S p p e e n n c c e e r r B B u u c c h h a a n n a a n n L L e e c c t t u u r r e e F F r r i i d d a a y y , , N N o o v v e e m m b b e e r r 3 3 0 0 t t h h, , 2 2 0 0 1 1 2 2 C C o o l l l l e e g g e e S S t t a a t t i i o o n n H H i i l l t t o o n n C C o o l l l l e e g g e e S S t t a a t t i i o o n n , , T T e e x x a a s s , , U U S S A A http://ceprofs.tamu.edu/briaud/buchanan.htm S S e e i i s s m m i i c c M M e e a a s s u u r r e e m m e e n n t t s s a a n n d d G G e e o o t t e e c c h h n n i i c c a a l l E E n n g g i i n n e e e e r r i i n n g g T T h h e e 2 2 0 0 1 1 1 1 K K a a r r l l T T e e r r z z a a g g h h i i L L e e c c t t u u r r e e B B y y D D r r . . K K e e n n n n e e t t h h S S t t o o k k o o e e A A c c t t i i v v e e R R i i s s k k M M a a n n a a g g e e m m e e n n t t i i n n G G e e o o t t e e c c h h n n i i c c a a l l E E n n g g i i n n e e e e r r i i n n g g T T h h e e 2 2 0 0 1 1 2 2 S S p p e e n n c c e e r r J J . . B B u u c c h h a a n n a a n n L L e e c c t t u u r r e e B B y y D D r r . . A A l l l l e e n n M M a a r r r r

Transcript of Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... ·...

Page 1: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

TThhee TTwweennttiieetthh SSppeenncceerr BBuucchhaannaann LLeeccttuurree

FFrriiddaayy,, NNoovveemmbbeerr 3300tthh,, 22001122

CCoolllleeggee SSttaattiioonn HHiillttoonn

CCoolllleeggee SSttaattiioonn,, TTeexxaass,, UUSSAA

hhttttpp::////cceepprrooffss..ttaammuu..eedduu//bbrriiaauudd//bbuucchhaannaann..hhttmm

SSeeiissmmiicc MMeeaassuurreemmeennttss

aanndd GGeeootteecchhnniiccaall

EEnnggiinneeeerriinngg

TThhee 22001111 KKaarrll TTeerrzzaagghhii LLeeccttuurree BByy DDrr.. KKeennnneetthh SSttookkooee

AAccttiivvee RRiisskk

MMaannaaggeemmeenntt iinn

GGeeootteecchhnniiccaall

EEnnggiinneeeerriinngg

TThhee 22001122 SSppeenncceerr JJ.. BBuucchhaannaann

LLeeccttuurree BByy DDrr.. AAlllleenn MMaarrrr

Page 2: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Table of Contents

Spencer J. Buchanan 1

Donors 3

Spencer J. Buchanan Lecture Series 6

Agenda 7

Biography

Dr. Allen Marr, 2012 Spencer J. Buchanan Lecturer

Dr. Kenneth Stokoe, 2011 Karl Terzaghi Lecturer

8

9

“Active Risk Management in Geotechnical Engineering” Dr. Allen Marr

11

“Seismic Measurements and Geotechnical Engineering” Dr. Kenneth Stokoe

20

Pledge Information 45

Page 3: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

SPENCER J. BUCHANAN

Spencer J. Buchanan, Sr. was born in 1904 in Yoakum, Texas. He graduated from Texas A&M University with a degree in Civil Engineering in 1926, and earned graduate

and professional degrees from the Massachusetts Institute of Technology and Texas A&M University.

He held the rank of Brigadier General in the U.S. Army Reserve, (Ret.), and

organized the 420th Engineer Brigade in Bryan-College Station, which was the only such unit in the Southwest when it was created. During World War II, he served the U.S. Army Corps of Engineers as an airfield engineer in both the U.S. and throughout the islands of the

Pacific Combat Theater. Later, he served as a pavement consultant to the U.S. Air Force and during the Korean War he served in this capacity at numerous forward airfields in the combat zone. He held numerous military decorations including the Silver Star. He was

founder and Chief of the Soil Mechanics Division of the U.S. Army Waterways Experiment Station in 1932, and also served as Chief of the Soil Mechanics Branch of the Mississippi

River Commission, both being Vicksburg, Mississippi.

Professor Buchanan also founded the Soil Mechanics Division of the Department of Civil Engineering at Texas A&M University in 1946. He held the title of Distinguished Professor of Soil Mechanics and Foundation Engineering in that department. He retired

from that position in 1969 and was named professor Emeritus. In 1982, he received the College of Engineering Alumni Honor Award from Texas A&M University.

1

Page 4: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

He was the founder and president of Spencer J. Buchanan & Associates, Inc., Consulting Engineers, and Soil Mechanics Incorporated in Bryan, Texas. These firms were

involved in numerous major international projects, including twenty-five RAF-USAF airfields in England. They also conducted Air Force funded evaluation of all U.S. Air

Training Command airfields in this country. His firm also did foundation investigations for downtown expressway systems in Milwaukee, Wisconsin, St. Paul, Minnesota; Lake Charles, Louisiana; Dayton, Ohio, and on Interstate Highways across Louisiana. Mr.

Buchanan did consulting work for the Exxon Corporation, Dow Chemical Company, Conoco, Monsanto, and others.

Professor Buchanan was active in the Bryan Rotary Club, Sigma Alpha Epsilon

Fraternity, Tau Beta Pi, Phi Kappa Phi, Chi Epsilon, served as faculty advisor to the Student

Chapter of the American Society of Civil Engineers, and was a Fellow of the Society of American Military Engineers. In 1979 he received the award for Outstanding Service from the American Society of Civil Engineers.

Professor Buchanan was a participant in every International Conference on Soil Mechanics and Foundation Engineering since 1936. He served as a general chairman of the International Research and Engineering Conferences on Expansive Clay Soils at Texas

A&M University, which were held in 1965 and 1969.

Spencer J. Buchanan, Sr., was considered a world leader in geotechnical engineering, a Distinguished Texas A&M Professor, and one of the founders of the Bryan Boy’s Club. He died on February 4, 1982, at the age of 78, in a Houston hospital after an

illness, which lasted several months.

2

Page 5: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

The Spencer J. Buchanan ’26 Chair in Civil Engineering

The College of Engineering and the Department of Civil Engineering gratefully recognize the

generosity of the following individuals, corporations, foundations, and organizations for their part in helping to establish the Spencer J. Buchanan ’26 Professorship in Civil Engineering. Created in 1992 to honor a world leader in soil mechanics and foundation engineering, as well as a

distinguished Texas A&M University professor, the Buchanan Professorship supports a wide range of enriched educational activities in civil and geotechnical engineering. In 2002, this professorship became the Spencer J. Buchanan ’26 Chair in Civil Engineering.

Donors

Founding Donor

Mr. C. Darrow Hooper ‘53

Benefactors ($5,000+)

Flatt Partners, Limited

Mr. & Mrs. Spencer J. Buchanan, Jr. '53

ETTL Engineers and Consultants, Inc.

East Texas Testing Laboratory, Inc.

Patrons ($1,000-$4,999)

Aviles Engineering Corporation

Dr. Rudolph Bonaparte

Dr. Mark W. Buchanan

The Dow Chemical Foundation

Dr. Wayne A. Dunlap ‘52

Br. Gen. John C.B. Elliott

Dr. Dionel E. Aviles ‘53

ExxonMobil Foundation

Mr. Douglas E. Flatt ‘53

Mr. Perry G. Hector ‘54

Mr. Robert S. Patton ‘61

Dr. Jose M. Roesset

Spencer J. Buchanan Associates, Inc.

Dr. Kenneth H. Stokoe

Fellows ($500-$999)

Mr. Joe L. Cooper ‘56

Mr. Alton T. Tyler ‘44

Harvey J. Haas, Col USAF (Ret) ‘59

Mr. Conrad S. Hinshaw ‘39

Mr. & Mrs. Peter C. Forster ‘63

Mr. George D. Cozart ’74

Mr. Donald R. Ray ‘68

Dr. Lyle A. Wolfskill ’53

Mr. Donald W. Klinzing

R.R. & Shirley Bryan

O’Malley & Clay, Inc.

3

Page 6: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Members ($100-$499)

Adams Consulting Engineers, Inc.

Lt. Col. Demetrios A. Armenakis ‘58

Mr. Eli F. Baker ‘47

Mr. & Mrs. B.E. Beecroft ‘51

Dean Fred J. Benson ‘36

John R. Birdwell ‘53

Mr. & Mrs. Willy F. Bohlmann, Jr. ‘50

G.R. Birdwell Construction, L.P.

Mr. Craig C. Brown ‘75

Mr. Donald N. Brown ‘43

Ronald C. Catchings, LTC USA (Ret) ‘65

Mr. Ralph W. Clement ‘57

Coastal Bend Engineering Associates

Mr. & Mrs. James T. Collins

Mr. John W. Cooper, III ‘46

Mr. George W. Cox ‘35

Mr. and Mrs. Harry M. Coyle

Mr. Murray A. Crutcher, Jr. ‘74

Enterprise Engineers, Inc.

Mr. Donald D. Dunlap ‘58

Edmond L. Faust, Jr. Col (Ret) ‘47

Mr. David T. Finley ‘82

Mr. Charles B. Foster, Jr. ‘38

Mr. Benjamin D. Franklin ‘57

Mr. Thomas E. Frazier ‘77

Mr. William F. Gibson ‘59

Mr. Cosmo F. Guido ‘44

Joe G. Hanover, Gen (Ret) ‘40

Mr. & Mrs. John L. Hermon ‘63

Dr. W. Ronald Hudson ‘54

W.R. Hudson Engineering

Mr. Homer A. Hunter ‘25

Ms. Iyllis Lee Hutchin

Mr. Walter J. Hutchin ‘47

Dr. YanFeng Li ‘04

Brig. Gen. Hubert O. Johnson, Jr. ‘41

Lt. Col. William T. Johnson, Jr. ‘50

Mr. Homer C. Keeter, Jr. ‘47

Mr. Richard W. Kistner ‘65

Charles M. Kitchell, Jr., Col USA (Ret) ‘51

Frank Lane Lynch, Col USA (Ret) ‘60

Major General Charles I McGinnis ‘49

Mr. Jes D. McIver ‘51

Mr. Charles B. McKerall, Jr. ‘50

Dr. James D. Murff ‘70

Mr. & Mrs. Jack R. Nickel ‘68

Roy E. Olson

Dr. Nicholas Paraska ‘47

Mr. & Mrs. Daniel E. Pickett ‘63

Pickett-Jacobs Consultants, Inc.

Mr. Richard C. Pierce ‘51

Mr. & Mrs. Robert J. Province ‘60

Mr. David B. Richardson ‘76

LTC David E. Roberts ‘61

Mr. Walter E. Ruff ‘46

Mr. Weldon Jerrell Sartor ‘58

Mr. Charles S. Skillman, Jr. ‘57

Mr. Louis L. Stuart, Jr. ‘52

Mr. Ronald G. Tolson, Jr. ‘60

Mr. & Mrs. Hershel G. Truelove ‘52

Mr. Donald R. Wells ‘70

Mr. Andrew L. Williams, Jr. ‘50

Dr. James T.P. Yao

Dodd Geotechnical Engineering

William and Mary Holland

Mary Kay Jackson ‘83

Andrew & Bobbie Layman

Mr. & Mrs. W.A. Leaterhman, Jr.

Morrison-Knudsen Co.,Inc.

Soil Drilling Services

Mr. & Mrs. Thurman Wathen

Associates ($25-$99)

Mr. & Mrs. Charles A. Arnold ‘55

Colonel Carl F. Braunig, Jr. ‘45

Mr. & Mrs. Norman J. Brown ‘ 49

John Buxton, LTC USA (Ret) ‘55

Mr. & Mrs. Joseph R. Compton

Mr. Robert J. Creel ‘53

Mr. & Mrs. Robert E. Crosser ‘49

Caldwell Jewelers

Lawrence & Margaret Cecil

Mr. & Mrs. Howard T. Chang ‘42

Mrs. Lucille Hearon Chipley

Caroline R. Crompton

O. Dexter Dabbs

Guy & Mary Bell Davis

4

Page 7: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Mr. & Mrs. Stanley A. Duitscher ‘55

Mr. George H. Ewing ‘46

Mr. & Mrs. Neil E. Fisher ‘75

Lt. Col. John E. Goin ‘68

Dr. Anand V Govindasamy '09

Col. Howard J. Guba ‘63

Halliburton Foundation, Incorporated

Mr. Scott W. Holman III ‘80

Lt. Col. & Mrs. Lee R. Howard ‘52

Mr. & Mrs. William V. Jacobs ‘73

Mr. Ronald S. Jary ‘65

Mr. & Mrs. Shoudong Jiang ‘01

Stanley R. Kelley, COL USA (Ret) ‘47

Mr. Elmer E. Kilgore ‘54

Mr. Kenneth W. Kindle ‘57

Lt. Col. Walter A. Klein ‘60

Mr. Kenneth W. Korb ‘67

Mr. Larry K. Laengrich ‘86

Mr. Monroe A. Landry ‘50

Lt. Col. Linwood E. Lufkin ‘63

Mr. Frank H. Newman, Jr. '31

Northrop Grumman Foundation

Mr. Charles W. Pressley, Jr. ‘47

Brig. Gen. Allen D. Rooke, Jr. ‘46

Mr. Paul D. Rushing ‘60

S.K. Engineering

Mr. Milbourn L. Smith ‘60

Mr. & Mrs. Robert F. Stiles ‘79

Mr. Edward Varela ‘88

Ms. Constance H. Wakefield

Mr. Kenneth C. Walker ‘78

Mr. Robert R. Werner ‘57

Mr. & Mrs. William M. Wolf, Jr. ‘65

Mr. William K. Zickler ‘83

Mr. Ronald P. Zunker ‘62

Mr. & Mrs. John S. Yankey III ‘66

Mr. & Mrs. John Paul Abbott

Bayshore Surveying Instrument Co.

Mrs. E.D. Brewster

Mr. & Mrs. Stewart E. Brown

Robert P. Broussard

Robert & Stephanie Donaho

Mr. Charles A. Drabek

Mr. & Mrs. Nelson D. Durst

First City National Bank of Bryan

Mr. & Mrs. Albert R. Frankson

Maj. Gen Guy & Margaret Goddard

Mr. & Mrs. Dick B. Granger

James & Doris Hannigan

Mrs. Jack Howell

Col. Robert & Carolyn Hughes

Richard & Earlene G. Jones

H.T. Youens, Sr.

Mr. Tom B. King

Dr. & Mrs. George W. Kunze

Lawrence & Margaret Laurion

Mr. & Mrs. Charles A Lawler

Mrs. John M. Lawrence, Jr.

Jack & Lucille Newby

Lockwood, Andrews, & Newman, Inc.

Robert & Marilyn Lytton

W.T. McDonald

James & Maria McPhail

Mr. & Mrs. Clifford A. Miller

Minann, Inc.

Mr. & Mrs. J. Louis Odle

Leo Odom

Mr. & Mrs. Bookman Peters

Mr. & Mrs. D.T. Rainey

Maj. Gen. & Mrs. Andy Rollins and J. Jack Rollins

Mr. & Mrs. J.D. Rollins, Jr.

Mr. & Mrs. John M. Rollins

Schrickel, Rollins & Associates, Inc.

William & Mildred H. Shull

Southwestern Laboratories

Mr. & Mrs. Homer C. Spear

Mr. & Mrs. Robert L. Thiele, Jr.

W. J. & Mary Lea Turnbull

Mr. & Mrs. John R. Tushek

Troy & Marion Wakefield

Mr. & Mrs. Allister M. Waldrop

Every effort was made to ensure the accuracy of this list. If you feel there is an error, please contact

the Engineering Development Office at 979-845-5113. A pledge card is enclosed on the last page

for potential contributions.

5

Page 8: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Spencer J. Buchanan Lecture Series

1993 Ralph B. Peck “The Coming of Age of Soil Mechanics: 1920 - 1970”

1994 G. Geoffrey Meyerhof “Evolution of Safety Factors and Geotechnical Limit State Design”

1995 James K. Mitchell “The Role of Soil Mechanics in Environmental Geotechnics”

1996 Delwyn G. Fredlund “The Emergence of Unsaturated Soil Mechanics”

1997 T. William Lambe “The Selection of Soil Strength for a Stability Analysis”

1998 John B. Burland “The Enigma of the Leaning Tower of Pisa”

1999 J. Michael Duncan “Factors of Safety and Reliability in Geotechnical Engineering”

2000 Harry G. Poulos “Foundation Settlement Analysis – Practice Versus Research”

2001 Robert D. Holtz “Geosynthetics for Soil Reinforcement”

2002 Arnold Aronowitz “World Trade Center: Construction, Destruction, and Reconstruction”

2003 Eduardo Alonso “Exploring the Limits of Unsaturated Soil Mechanics: the Behavior of

Coarse Granular Soils and Rockfill”

2004 Raymond J. Krizek “Slurries in Geotechnical Engineering”

2005 Tom D. O’Rourke “Soil-Structure Interaction Under Extreme Loading Conditions”

2006 Cylde N. Baker “In Situ Testing, Soil-Structure Interaction, and Cost Effective Foundation

Design”

2007 Ricardo Dobry “Pile response to Liquefaction and Lateral Spreading: Field Observations

and Current Research”

2008

Kenneth Stokoe

"The Increasing Role of Seismic Measurements in Geotechnical

Engineering"

2009 Jose M. Roesset “Some Applications of Soil Dynamics”

2010 Kenji Ishihara “Forensic Diagnosis for Site-Specific Ground Conditions in Deep

Excavations of Subway Constructions”

2011 Rudolph Bonaparte “Cold War Legacy – Design, Construction, and Performance of a Land-

Based Radioactive Waste Disposal Facility”

2012 W. Allen Marr “Active Risk Management in Geotechnical Engineering”

The texts of the lectures and a DVD’s of the presentations are available by contacting:

Dr. Jean-Louis Briaud

Spencer J. Buchanan ’26 Chair Professor

Zachry Department of Civil Engineering

Texas A&M University

College Station, TX 77843-3136, USA

Tel: 979-845-3795

Fax: 979-845-6554

E-mail: [email protected]

http://ceprofs.tamu.edu/briaud/buchanan.htm

6

Page 9: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

AGENDA

The Twentieth Spencer J. Buchanan Lecture

Friday, November 30, 2012

College Station Hilton

2:00 p.m. Introduction by Jean-Louis Briaud

2:15 p.m. John Niedzwecki - The Zachry Department of Civil Engineering

2:20 p.m. Phil King - The ASCE Geo Institute

2:25 p.m. Introduction of Kenneth Stokoe by Jean-Louis Briaud

2:30 p.m. “Seismic Measurements and Geotechnical Engineering”

The 2011 Terzaghi Lecture by Kenneth H. Stokoe, II

3:30 p.m. Introduction of W. Allen Marr by Jean-Louis Briaud

3:35 p.m. “Active Risk Management in Geotechnical Engineering”

The 2012 Buchanan Lecture by W. Allen Marr

4:35 p.m. Discussion

4:50 p.m. Closure with Philip Buchanan

5:00 p.m. Photos followed by a reception at the home of Jean-Louis and

Janet Briaud.

7

Page 10: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

W. Allen Marr, Ph.D., PE, NAE, F.ASCE

Dr. Allen Marr, President and CEO of Geocomp, has over 40 years of

specialized expertise in design and construction of large earthwork facilities, value engineering for earthworks and earth retention systems, risk

management for underground construction, and instrumentation and real-

time monitoring systems. He has spent his entire professional career focused on incorporating the benefits of applied research in geo-engineering into

civil engineering practice.

Dr. Marr holds a Bachelor of Science degree in Civil Engineering from the

University of California at Davis as well as a MS and PhD in Civil Engineering from the Massachusetts Institute of Technology. He is an

elected member of the National Academy of Engineering (NAE) which

recognizes outstanding engineers for their dedication to their discipline as well as for their development of an engineering invention or process that has

greatly improved humanity.

Some of his significant contributions in the field of engineering include the development of techniques for

monitoring the stability, movement and pressure in earthworks projects by using sensors, wireless communications,

automated analysis and visualization of data. In developing sensing, monitoring, measurement and analysis technologies, Dr. Marr has enabled full-scale construction projects to be built more safely and efficiently, at lower

cost.

Dr. Marr has developed the concepts of “Active Risk Management”; “Key Risk Indicators” and “Risk Monitoring”

to better manage risks associated with heavy civil construction. Active Risk Management assesses risk throughout the design and construction life of a project and indicates where and what mitigation measures should

be employed to optimally manage risk. And, as the developer of an integrated iSite™ system which monitors

sensors located anywhere in the world via a Web browser, Dr. Marr has created a system that is increasingly used to monitor the safety of facilities during construction and provides early warnings of adverse performance.

His many contributions have been widely published and he serves on a number of professional society committees and boards. Dr. Marr has consulted on such significant projects as Boston’s Central Artery Tunnel; Dulles Airport

Expansion; the new World Trade Center construction and the Woodrow Wilson Bridge in Washington, D.C., as

well as projects in Canada, the Netherlands, Qatar, Japan, Venezuela and South Korea.

8

Page 11: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Kenneth H. Stokoe, II, Ph.D. Jennie C. and Milton T. Graves Chair

The University of Texas at Austin

Dr. Kenneth H. Stokoe, II is the holder of the Jennie C. and

Milton T. Graves Chair in Engineering in the Civil,

Architectural and Environmental Engineering Department

at the University of Texas at Austin. He has been working in

the areas of field seismic measurements, dynamic laboratory

measurements, and dynamic soil-structure interaction for

more than 40 years. He has been instrumental in developing

several small-strain field methods for in-situ shear wave

velocity measurements. He has also developed two types of

resonant column systems that are used to evaluate dynamic

soil and rock properties in the laboratory. Over the last Ten

years, Dr. Stokoe has led the development of large-scale mobile field equipment for dynamic loading of

geotechnical systems, foundations and structures, an activity that has been funded by the National Science

Foundation in the NEES (Network for Earthquake Engineering Simulation) program. The equipment has

already led to the development of new testing methods to evaluate soil nonlinearity and liquefaction

directly in the field. Dr. Stokoe has received several honors and awards, including election to the National

Academy of Engineering, the Harold Mooney Award from the Society of Exploration Geophysicists, the

C.A. Hogentogler Award from the American Society for Testing and Materials, and the H. Bolton Seed

Medal and the Karl Terzaghi Distinguished Lecturer from the American Society of Civil Engineers.

9

Page 12: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

AAccttiivvee RRiisskk MMaannaaggeemmeenntt iinn

GGeeootteecchhnniiccaall EEnnggiinneeeerriinngg

TThhee 22001122 SSppeenncceerr JJ.. BBuucchhaannaann LLeeccttuurree BByy DDrr.. AAlllleenn MMaarrrr

10

Page 13: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

1  

  

Active Risk Management in Geotechnical Engineering

W. Allen Marr1, PE, PhD, NAE, F.ASCE

1President and CEO, Geocomp Corporation, 125 Nagog Park, Acton, MA 01720 [email protected]

ABSTRACT: Active risk management, (ARMTM), is a systematic process of identifying, analyzing, planning, monitoring and responding to project risk over the life of the project. It involves processes, tools, and techniques that help the project team minimize the probability and consequences of adverse events (threats) and maximize the probability and consequences of positive events (opportunities) throughout the life of the project. It is especially useful in projects with significant geotechnical risks. It provides the project team with more complete information on the risks they face in a format understandable to non-specialists – cost and schedule impacts. It identifies the uncertainties and potential events that create the most risk to the project and develops ways to minimize these uncertainties as they affect final project cost and schedule. The concept of Active Risk Management applied to civil engineering projects has been developed by the author on a variety of projects over 35 years. This paper lays out the steps of Active Risk Management and discusses how they are applied in geotechnical engineering. It illustrates the use of the method with a practical example that shows the value of obtaining additional geotechnical information to reduce risk.

INTRODUCTION

Every construction project faces risks that threaten successful completion of the project as measured by cost, schedule and quality. The construction industry is seeking better ways to manage these risks. Since the 1970’s, the author and his colleagues have worked with clients in the infrastructure market to identify and quantify risks for specific projects, then develop risk management strategies that provide the most benefit to the project in terms of cost, schedule and quality. This work has led to the concept of Active Risk Management which recognizes that risk management efforts must extend throughout the life of a project and must be based on information that is current and comprehensive. This document represents the synthesis of our experience with risk management into a logical and consistent approach that has saved clients large sums of money by actively managing risk throughout the project.

11

lcouillard
Typewritten Text
lcouillard
Typewritten Text
lcouillard
Typewritten Text
GeoRisk 2011 © ASCE 2011 894
lcouillard
Typewritten Text
894
lcouillard
Typewritten Text
Please click here for the full version of this document - redistribution is subject to ASCE license or copyright. http://www.ascelibrary.org
Page 14: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

2  

Project risk is an uncertain event or condition that potentially impacts the project objectives for cost, schedule, and quality. Impacts may be both positive and negative. A risk has a cause and, if it occurs, a consequence. Risk is the combination of the likelihood of the uncertain event times its consequence. A likely event with moderate consequences may expose the project to more risk than an unlikely event with high consequences. Risk management is a systematic process of identifying, analyzing, planning, monitoring and responding to risk. It involves processes, tools, and techniques that help the project team minimize the probability and consequences of adverse events and maximize the probability and consequences of positive events. Many organizations practice some form of risk management on construction projects. Generally these activities focus on risk assessment and risk allocation by individual members of the project team. These activities are organized to manage that member’s risk by transferring, avoiding, mitigating or accepting specific risk elements. This is not managing overall project risk. It may in fact increase total project costs because risks do not get allocated to the team member best positioned to manage that risk at an efficient cost. ACTIVE RISK MANAGEMENT The author has developed the concept of Active Risk Management™ (ARM™) to describe an organized risk management strategy that transcends the entire project. Active risk management is a systematic process of identifying, analyzing, planning, monitoring and responding to project risk over the life of the project. It involves processes, tools, and techniques that help the project team minimize the probability and consequences of adverse events (threats) and maximize the probability and consequences of positive events (opportunities) throughout the life of the project. Active Risk Management provides the project team with more complete information on the risks they face in an understandable quantitative format – cost and schedule at risk – and does so in near real‐time. This not only helps team members make informed decisions, but also monitor the progress of risk management efforts over the duration of the project. Active Risk Management provides quantitative information on the impacts of each risk component to cost, schedule and quality so that the most significant risks can be managed with the most effective approach. It applies methods of uncertainty analysis with project management tools to consider all potential risks and find those with the highest potential impact on the project objectives. The physical processes of construction inherently involve substantial uncertainty that creates risk to the owner, contractor and engineer. These risks are in addition to the conventional risks (those from injury, contract, regulatory, legal, financial, weather and others) associated with the project. No amount of planning and engineering can predict with 100‐percent certainty how the various elements of the project will actually perform during construction. Among the unknowns are: the geologic profile; the engineering properties of each component of the geologic profile; the groundwater conditions; the in situ stresses; the effects of environmental conditions, construction activities, and time on the underground conditions; limitations of analysis and design methodologies; unknown obstructions; location,

12

Page 15: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

3  

condition and performance during construction of existing utilities and other structures; and interactions between the ground and structures. There may also be uncertainty in the forces from extreme events that the project will experience. On top of these are the uncertainties that derive from accidents, mistakes, poor judgment, and improper actions of the work force and other construction issues during the performance of the work. These types of risk are referred to as “operational risks”. Operational risks are often ignored in the contractual, financial, and legal discussions of risk management; yet they may jeopardize the entire project. One approach to managing risks is to develop a conservative design based on what the project team considers a worst‐case scenario, and hope for the best. But unexpected factors, such as excessive ground movements or unexpected groundwater flow can damage completed work or adjacent facilities. These, in turn, can cause project delays, add substantial costs, degrade quality, or risk the health and safety of workers and the public. A more cost‐effective way to manage risks is to design for the most likely scenario based on an investigation of the underground conditions and potential hazards. The design process includes a risk assessment to determine which sources of uncertainty dominate the operational risks, which risks can be reduced with design modifications, and which risks can be avoided with observation and remedial work during construction, i.e. monitoring how the site actually performs as construction begins, then making adjustments to the design and/or construction methodology as required by the observed performance. The risk assessment is continually reviewed and updated as new information becomes available. This approach is the essence of Active Risk ManagementTM. The ARMTM method has similarities to Dr. Peck’s Observational Method (Peck, 1969) from a geotechnical engineer’s perspective, but looks more broadly at all potential risks to the project; makes quantitative estimates of the relative magnitudes of each risk element and its impact on cost, schedule and quality; and monitors Key Risk Indicators. Active Risk Management uses historical data, expert judgment with tools from decision theory, and probability theory to make numerical assessments of each component of risk for construction. Measurements of actual conditions as they unfold and opinions from subject matter experts are integrated with formal analyses to produce a balanced quantitative assessment of each source of operational risk in terms of potential impact on cost and schedule. This approach has helped owners and contractors make informed decisions regarding design and construction of major facilities – decisions that have saved hundreds of millions of dollars by avoiding overly conservative approaches and focusing resources on the most beneficial actions. Effective risk management consists of several steps that can be visualized as a continuous circle of improvement shown in Figure 1. Effective risk management requires the process of risk mitigation to be completed and repeated throughout the project duration as new information becomes available. Past risk management practice on many projects has typically been to prepare a risk assessment during the planning phase of a project, make some decisions on risk allocation, then do little formal work on risk management for the remainder of the project. This practice does not provide the substantial benefits of a complete risk management program. Effective risk management of project construction starts in the planning phase, and

13

Page 16: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

4  

continues until after the facility is placed into service or risks are reduced to an acceptable level. Numerous sources of risk exist on a complex project. It becomes easy to overlook or forget a significant source of risk that later threatens the project objectives. Using established methods and tools, qualitative risk analysis assesses the probability and the consequences of each identified risk to determine its overall importance. Risks to project cost and schedule involve two principal elements: uncertainties in quantities and unit costs for known elements and

unknown conditions and events that are not covered in the baseline cost and schedule elements. During the planning phase of a project, quantities and unit prices may have considerable uncertainty. These uncertainties can be estimated by asking the sources of the information to expand their estimates to lowest possible value, highest conceivable value and the most likely value for each cost, quantity, and schedule item. These types of variability have traditionally been handled by the estimators making individual conclusions about what amount to put into a price estimate and then adding a contingency to the project total cost. The problem with the contingency approach is that different estimators use different means to decide how much contingency to add to each cost item and then another contingency gets added to the total bid cost. No one knows what the final project price really represents relative to all the uncertainties that were or were not considered in the individual price elements. APPLICATION ILLUSTRATION Explicit consideration of the best estimates of the uncertainties in each element of the project costs can be used to obtain a range of probable cost for the project. This range can then be used to decide how much risk to accept in preparing the final bid price. This is illustrated with an example. A large earthworks project is estimated by conventional means to cost $495 million. The bid management team discusses uncertainties and risks and decides to add a 6% contingency to the base estimate for external risks making their total cost estimate $525 million. A risk assessment breaks this global estimate of risks into an estimate of uncertainty in cost and schedule for each component of the project and for each potential risk event. Table 1 gives a summarized risk registry for the primary unknowns. A detailed review by item of the base cost and schedule with the project estimators results in a range for base cost and schedule. Table 1 summarizes the estimates for lowest possible value, the highest conceivable value and the most likely value (called mode) for costs, schedule and likelihoods. The values come from the subjective assessments by the project team members most familiar with the project. A review with the project team indicates 5 events with significant potential impact to the project cost and schedule that were not covered in the base cost and schedule estimate. Estimates

Fig. 1: Circle of Risk Management

14

Page 17: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

5  

are made for the range of potential cost and schedule impacts to the project and for the likelihood that each of these events may occur. Note that uncertainty in the likelihood estimate is also included. These data are used as input to a numerical simulation run in a spreadsheet that develops a probability distribution for each uncertain element and numerically integrates the individual event distributions into one overall distribution on cost and another on schedule. These risk costs are added to the base cost uncertainties to obtain the overall uncertainty for project cost. Such estimates are shown by the six curves in Figure 2.

Table 1: Simplified Risk Registry  

Risk Event ID Consequence (ranges are lowest, mode

and highest estimates)

Likelihood and Sources of Data

Base Base 475/500/550 millions 46/48/54 months

100% review of base estimates

Earthwork issues A 5/6/7.5 millions 3/4/6 months

12-16-22% from project manager

Delays in shoring delivery

B 7/8/9 millions 4/5/6 months

10/20/25% from suppliers

Unexpected site conditions

C 30/54/90 millions 4/6/8 months

7-10-15% from geotechnical consultants

Bad weather D 1/1.5/2.5 millions 1/1.3/2 months

9-12-15% from weather records

Approval Delays E 0.2/0.25/0.3 millions 3/4/6 months

25-30-35% past experience

Additional Testing and Monitoring

F 1/1.2/1.5 millions No schedule impact

Likelihood for A reduced to 4/5.3/7.3%; Likelihood for C

reduced to 0.7/1.0/1.5% The seventh curve, ID F, is actually an opportunity. An additional testing program to reduce uncertainty in soil properties and a performance monitoring program to give early warnings to invoke contingency measures costs money but reduces uncertainty which lowers risk. The reduced uncertainty lowers risk costs by much more than the cost of the additional work. Accounting for risk costs from event uncertainties in the example increases the best estimate of the base cost from $495M to $507 million. There is a 10% chance that the base cost could exceed $530M. The range of probable cost for the project with all uncertainties and identified risks accounted for is $492 to 554M (C10 and C90 exceedance values). Prudent decision makers would consider this range of probable cost in preparing budgets for the project and bids for the construction. It is useful to note that an estimate using mean values for unit prices and quantities and adding a 6% contingency to account for uncertainty in costs and quantities, but not including the unknown risks, would yield a cost of $525M. Figure 2 shows that there is a 15% chance that this cost will be exceeded if risk events A-E are not considered and a 33% chance if risk events A-E are included. Most contractors would be very

15

Page 18: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

6  

uncomfortable bidding a project with a price that had a 33% chance of being exceeded.    Figure 3 shows the risk curves for schedule. The best estimate of likely time to complete the job is 48 months. Adding in the effects of potential external events shows that the chance of completing the project in 48 months is about 10%. There is a 10% chance that the project will take more than 56.6 months to complete. This additional time has a significant impact on the cost of the project.  

 Fig. 2: Estimated Cost with Risk

 Fig. 3: Estimated Schedule with Risk

This example shows the effects of uncertainties on project costs and schedule estimates during the planning phase of a project. As the project progresses, new information alters the uncertainties. Pricing and quantities become more certain. As time passes, a risk event happens or doesn’t happen which alters its probability to 0 or 1. Uncertainties in cost and schedule can also be reduced by collecting additional information that reduces uncertainty in risk events. Curve 7 shows the potential benefits of performing more testing on the earthen materials to reduce uncertainty in how they can be excavated and compacted, and of adding an instrumentation program to determine as early as possible how the work is performing and whether remedial actions may be required to prevent undesirable performance, such as a slope stability failure or a foundation failure, that increase cost or schedule. Another useful outcome of the risk assessment is a ranking of the sources of risk by their relative impacts on estimated cost and schedule. Figures 4 and 5 show results for this example. The highest cost risk is caused by uncertainty in site conditions. Based on the cost and likelihood estimates of the team this uncertainty has an expected cost impact of $6.5M on the project and a schedule delay of 0.6 months. ID F in Table 1 illustrates opportunity. By performing further site investigations to lower geotechnical uncertainty and adding a performance instrumentation-monitoring system, there is an expected cost increase of $1.2M but the value of the expected reduction in risk is $7M for a net potential gain of almost $6M and a schedule reduction of 1 month. The effect on the risk curves for cost and schedule are shown by the difference between curves 6 and 7 in Figures 2 and 3. For geotechnical engineers, results like these provide a great way to communicate the value of additional site investigations and performance monitoring programs to clients.

16

Page 19: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

7  

Fig. 4: Tornado Chart for Costs

 Fig. 5: Tornado Chart for Schedule

The Risk Management approach illustrated in this example occurs at the beginning of the project. It provides very useful information to help bid the project and develop strategies to manage the project to minimize risks during the execution. It provides a rational and consistent methodology to quantify all uncertainties in the project cost and schedule elements. To be most effective however, this risk assessment methodology should continue throughout the project with a monitoring and updating program to expose emerging risks and manage their consequences. This addition is what makes the Active Risk Management concept unique. The “F” event given in the example shows the potential benefit of continuing risk management through the project. TEN STEP APPROACH TO ACTIVE RISK MANAGEMENT The ARMTM approach to risk management involves close teamwork among the Owner, the Engineer, the Contractor (if contract has been awarded) and a team of subject matter experts. The Owner provides information on the project scope and objectives and supplies other resources necessary to conduct the risk assessment. The Engineer provides information on possible risk

0 2 4 6 8

C

B

A

D

E

Expected Value Cost Impact ($ Million)

Risk ID

Cost (Without F)

Cost (With F)

0 0.5 1 1.5

E

B

A

C

D

Expected Value Schedule  Impact (Months)

Risk ID

Schedule (Without F)

Schedule (With F)

Fig. 6: Work Tasks for Active Risk Management Process

17

Page 20: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

8  

events, their likelihood of occurrence and their consequences. Perspective Contractors, or construction specialists, also provide information on possible risk events ‐ especially those tied to construction means and methods, their likelihood of occurrence, and their consequences. The Risk Team facilitator provides the framework for a systematic examination of risk by the team; facilitates the definition of risk events, their likelihood of occurrence, and their consequences; tests the information for completeness and consistency with scientific requirements; develops and applies a mathematical model of risk; and interprets and reports the results to the project team. The Risk Assessment Team is comprised of professionals experienced in all aspects of planning, design, and construction of the facility. Independent consultants or subject matter experts whose expertise closely aligns with unique aspects of the project and who understand the essential elements of risk analysis may be added to the team. Figure 6 illustrates the sequence of tasks we use to complete an active risk assessment program. The process runs in a linear sequence in which the specific work in each task depends on the results of previous tasks. Each task is self evident.  CONCLUSIONS Active Risk Management provides the project team with complete information on the risks they face in an understandable format – cost and schedule at risk. It identifies the uncertainties and potential events that create the most risk to the project and develops ways to minimize these uncertainties on final project cost and schedule. This not only helps team members to make informed decisions, but also to monitor the progress of risk management efforts over the duration of the project. Active Risk Management provides clients with a continual assessment of their risk profile and how it is changing as the project progresses. Active Risk Management identifies specific actions that can be used to alter events and reduce consequences; thereby preventing unexpected and costly events. Active Risk Management seeks to contain and control the many costs that result from unexpected and uncontrolled events. The result can be savings that are many times the cost of the risk management effort. The author’s experience shows that the project’s best interests are served when key participants take a proactive approach to minimizing the occurrence of significant unexpected events and controlling the significant consequences of undesirable performance. Using Active Risk Management concepts on significant projects around the world has shown that this methodology is best applied by whoever has the most at risk in a project’s successful outcome. Depending on the project and its risk profile, this may be the Owner, the General Contractor, the Construction Manager, the Insurer or the Financer. REFERENCES Marr, W.A. (2006) “Geotechnical Engineering and Judgment in the Information Age,”

Keynote lecture. ASCE GSP GeoCongress-2006, Atlanta, GA. Peck, R.B. (1969) “Advantages and Limitations of the Observational Method In

Applied Soil Mechanics,” Geotechnique, June, pp. 173-187.

18

Page 21: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

SSeeiissmmiicc MMeeaassuurreemmeennttss aanndd

GGeeootteecchhnniiccaall EEnnggiinneeeerriinngg

TThhee 22001111 KKaarrll TTeerrzzaagghhii LLeeccttuurree BByy DDrr.. KKeennnneetthh SSttookkooee

19

Page 22: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Prof. Kenneth H. Stokoe, II Jennie C. and Milton T.

Graves Chair Civil, Architectural and

Environmental Engrg. Dept. University of Texas at Austin

47th Terzaghi Lecture

Texas A& M University College Station, Texas

November 30, 2012

Seismic Measurements and Geotechnical Engineering

Focus Characterizing the linear and nonlinear stiffnesses of soil and rock in the field

Outline 1. Present a Brief Background 2. Discuss State of Practice 3. Show Applications 4. Discuss Next-Generation Test

Methods and Future Directions 5. Concluding Remarks

1. Brief Background: Seismic Measurements

• Imaging with seismic (stress) waves • Subset of geophysical measurements • Emphasize field measurements

- traditional and advanced methods - perform at existing field conditions - link field conditions to lab tests

• Laboratory testing - permits parametric studies

• Overview surface-wave measurements - robust nonintrusive tests 20

Page 23: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

1a. Traditional Roles: Field and Laboratory Seismic (Stress Wave) Measurements

1. Soil Profile 3. Lab: Linear and Nonlinear G and D

Sand (SP)

Clay (CH)

Silt (ML)

Sand (SW)

Clay (CL)

G, MPa

Gmax

120

0

Dmin D, %

16

0 0.001 0.1

Shear Strain, ��, %

0.001 0.1

Gmax = �vs2

2. Field: Linear Vs and Vp

60

40

20

0

Dep

th, m

450 300 150 0 Vs, m/s

1000 0 VP, m/s

2000

1b. Field: Seismic Measurements Objective: measure time, t, for a known stress wave to propagate a known distance, d ... then velocity = d/t

Source Point 1 Point 2

* d

Key characteristic: small-strain (linear) measurements Key points: (1) “good” seismic source, (2) receivers properly oriented, and (3) proper analysis procedure

Field Measurements with Compression (P) and Shear (S) Waves

Gmax = VS2

�t g

Mmax = Vp2

�t g

Small-Strain Modulus

Distortion

Vp

VS

Wave Velocity

Particle Motion

Wave Type

P

S

21

Page 24: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Small-Strain Seismic Measurements

0 0 0.05 0.10 0.15

Shear Strain, ������

Shear Stress, � (kPa)

Gmax

�� ����Initial

Loading Curve

Small-Strain Wave Propagation: Gmax = (�t / g) VS

2

h

v

1. Crosshole Test

2. Downhole Test

* *

Traditional “Geotechnical” Field Seismic Methods (1970s)

Direct P and S Waves

Advanced Field Methods (1980s & 90s) 1. Seismic Cone Penetrometer (SCPT)

3. Surface Wave (SASW) Test

2. P-S Suspension Logger

*

* Direct S Waves

*

Measure Rayleigh

(R) Waves

Direct P and S Waves

22

Page 25: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

1c. Laboratory: Combined Resonant Column and Torsional Shear (RCTS) Device

Soil

Fixed Base

Accelerometer

Top Cap Drive Coil

Magnet

Torsional Excitation

Confining Chamber

Laboratory Parametric Studies b. Log Dmin – log o a. Log Vs – log o

0.1

1

10

10 2

10 3

10 4

10 5

10 100 1000 Confining Pressure, o, kPa

Mat

eria

l Dam

ping

Rat

io, D

min

, %

Confining Pressure, o, psf

1

Silty Sand (Small Strain, � < 0.001% )

Confining Pressure, o, psf

Shea

r Wav

e Ve

loci

ty, V

S, ft

/sec

Shear Wave Velocity, V

S , m/sec

Confining Pressure, o, kPa

1

10 2

10 3

10 4

10 2

10 3

10 4

10 5

10 100 1000

100

1000

Laboratory Parametric Studies b. D – log �� a. G – log ��

Shearing Strain, �, %

150

100

50

0

Shear Modulus, G

, MPa

0.0001 0.001 0.01 0.1 1

3500

3000

2500

2000

1500

1000

500

0

Shea

r Mod

ulus

, G, k

sf

cell���1

Shearing Strain, �, %

Mat

eria

l Dam

ping

Rat

io, D

, %

10

8

6

4

2

0 0.0001 0.001 0.01 0.1 1

Gmax = (�t / g) VS2

Dmin

23

Page 26: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Small-Strain Vp and Vs Measurements: Piezoelectric Transducers

P Wave

Confining chamber not shown.

Note:

S Wave

-0.01

-50

0

50

Ampl

itude

, Vol

ts

15 10 5 0 Time, sec x 10-4

0.01 0

�t

Input Input

Output Output

Base Pedestal

Top Cap

Soil

Bender

Disc

P S

15 10 5 0 Time, sec x 10-4

�t

50

0

-50 0.0025

-0.0025

Amplitude, Volts

0

Integration of Seismic Measurements into Geotechnical Engineering

a. Field Testing b. Laboratory Testing

Time Line 1960 1980 2000 2020

Traditional

Advanced

Utilization

1960 Time Line

1980 2000 2020

Traditional

Advanced

Utilization

1d. Overview of SASW*: Generalized Field Arrangement and Sampling

* SASW = Spectral Analysis of Surface Waves

Vertical Seismic Source

R2

R1 Layer 1

Layer 2

Layer 3

Dynamic Signal Analyzer

X Receiver #1 Receiver #2

24

Page 27: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Multiple Source-Receiver Positions

Source R #2 R #1

X 2X

8X

Source

Test Sequence. R #3

X

R #2 R #3 R #1

4X 4X

1.

2.

3. . . .

C L

32X

Source R #2 R #3 R #1

16X 16X

(Not to Scale)

Liquidator Used as SASW Source

f ≥ 1 Hz

Composite Field Dispersion Curve Generated from All Receiver Spacings

Wavelength (m)1 10 100 1000

Phase Velocity (m/sec)

0

500

1000

1500

2000

Wavelength (ft)1 10 100 1000 10000

Phas

e Ve

loci

ty (f

t/sec

)

0

1000

2000

3000

4000

5000

6000

7000S = 5 ft

S = 20 ft S = 40 ft S = 75 ft S = 150 ft S = 300 ft S = 600 ft (Location 1) S = 600 ft (Location 2) S = 800 ft S = 1200 ft S = 1600 ft

S = 10 ft (Location 1) S = 10 ft (Location 2)

max (2818 ft, 860m)

Wavelength, (ft)

Wavelength, (m)

Phase Velocity (m/sec) Ph

ase

Velo

city

(fps

)

25

Page 28: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Best-Match Theoretical Dispersion Curve (Final Step in Forward Modeling)

Wavelength (ft)1 10 100 1000 10000

Phas

e Ve

loci

ty (f

t/sec

)

0

1000

2000

3000

4000

5000

6000

7000Global Experimental Dispersion CurveTheoretical Dispersion Curve

Shear Wave Velocity (ft/sec)0 2000 4000 6000 8000

Depth (ft)

0

500

1000

1500

2000

Final Step

max (2818 ft, 860m)

max / 2 (1409 ft, 430m)

Composite Field Dispersion Curve

2. State of Practice: Field Seismic Testing

Seismic method or combination of methods depends upon: • critical level of facilities • geologic profile - materials (soft soil, alluvium, etc) - spatial variability - depth of critical layer(s) • overall profiling depth • area of investigation • sampling volume

Field Seismic Testing

Depth of Profiling (d) • shallow, d < 250 ft (75 m ) • intermediate, 250 ft ≤ d ≤ 750 ft • deep, d > 750 ft (225 m)

Shallow Seismic Investigations • state of practice ranges (very good poor) • many seismic methods used • number of practitioners is growing

26

Page 29: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Comparison of Field Seismic Methods: Shallow (d < 75 m) Field Investigations

1. Waste Handling Building (WHB) Area at Yucca Mountain, Nevada

• three seismic methods (blind comparisons) • plan dimensions of area: 300 m by 400 m • alluvium over faulted tuffs • compare statistical analysis of profiles

General Location of Yucca Mountain Site, Nevada

Nevada Test Site

Reno

SH 95

IH 80

SH 95

Yucca Mountain Site Las Vegas

~N

Seismic Testing at

Yucca Mountain

Site

South Ramp

WHB Area

Future Emplacement

Area

~N

Tunnels

North Portal

27

Page 30: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Locations of 12 Common (Boreholes) Sites and Nearby SASW Test Arrays at WHB Area

RF#18 RF#25

RF#14 RF#17

RF#16 RF#26

RF#28

RF#15

RF#24

RF#22

RF#23

RF#13

SASW-20

~N North Portal

Comparison of Downhole, P-S Logger and SASW VS Profiles at RF #15 in WHB Area

Shear Wave Velocity (m/sec)0 1000 2000 3000

0

20

40

60

80

100

120

Shear Wave Velocity (ft/sec)0 2000 4000 6000 8000 10000

Dep

th (f

t)

0

100

200

300

400

SASWDownhole

Shear Wave Velocity (m/sec)0 1000 2000 3000

Depth (m

)

0

20

40

60

80

100

120

Shear Wave Velocity (ft/sec)0 2000 4000 6000 8000 10000

0

100

200

300

400

DownholeP-S Logger

Downhole SASW

Different Seismic Methods Sample Different Amounts of Material

28

Page 31: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Different Seismic Methods Sample Different Amounts of Material

50 ft 100 ft

100 ft

50 ft

SASW Receivers

To Scale

1. SASW

SASW Sampling at

50-ft Spacing

SASW Sampling at

100-ft Spacing

Different Seismic Methods Sample Different Amounts of Material

50 ft 100 ft

100 ft

10 ft

50 ft

SASW Receivers

To Scale

Downhole

1. SASW 2. Downhole

SASW Sampling at

50-ft Spacing

SASW Sampling at

100-ft Spacing

Different Seismic Methods Sample Different Amounts of Material

50 ft 100 ft

100 ft

10 ft

50 ft

SASW Receivers

To Scale

Downhole P-S Logger

1. SASW 2. Downhole 3. P-S Logger

SASW Sampling at

50-ft Spacing

SASW Sampling at

100-ft Spacing

29

Page 32: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

0 5 10 15

0

20

40

60

80

No. of Profiles0 5 10 15

Depth (m

)

0.0 0.5 1.0

c.o.v.0.0 0.5 1.0

Shear Wave Velocity (m/sec)0 500 1000 1500 2000

Depth (m

)

0

20

40

60

80

Shear Wave Velocity (ft/sec)0 2000 4000 6000 8000

Dep

th (f

t)

0

50

100

150

200

250

300

Statistical Analysis of 12 VS Profiles at Common Sites, WHB Area

�mean

c.o.v. =

V s Profiles Median (N > 3) 16 th and 84 th Percentiles

Faulted Tuffs

SASW

0 10 20 30 40

0

20

40

60

80

No. of Profiles0 10 20 30 40

Depth (m

)

0.0 0.5 1.0

c.o.v.0.0 0.5 1.0

Shear Wave Velocity (m/sec)0 500 1000 1500 2000

Depth (m

)

0

20

40

60

80

Shear Wave Velocity (ft/sec)0 2000 4000 6000 8000

Dep

th (f

t)

0

50

100

150

200

250

300

“Apples-to-Oranges” Comparison WHB Area, Yucca Mountain

Median of SASW Median of Downhole

“Red-Apples-to-Red-Apples” Comparison WHB Area, Yucca Mountain

N � 3

0

20

40

60

80

No. of Profiles 0 5 10 15

Depth (m

)

0 5 10 15 0.0 0.5 1.0

c.o.v. 0.0 0.5 1.0

Shear Wave Velocity (m/sec) 0 500 1000 1500 2000

Depth (m

)

0

20

40

60

80

Shear Wave Velocity (ft/sec) 0 2000 4000 6000 8000

Dep

th (f

t)

0

50

100

150

200

250

300

�mean

c.o.v =

Median of SASW Median of Downhole

30

Page 33: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

“Red-Apples-to-Red-Apples” Comparison WHB Area, Yucca Mountain

N � 3

0 5 10 15

0

20

40

60

80

No. of Profiles 0 5 10 15

Depth (m

)

0.0 0.5 1.0

c.o.v. 0.0 0.5 1.0

Shear Wave Velocity (m/sec) 0 500 1000 1500 2000

Depth (m

)

0

20

40

60

80

Shear Wave Velocity (ft/sec) 0 2000 4000 6000 8000

Dep

th (f

t)

0

50

100

150

200

250

300

Median of Downhole Median of P-S Logger

�mean

c.o.v =

Parts 1 and 2: Conclusions 1. Many seismic methods are available; accurate

results if properly performed by knowledgeable practitioners.

2. Good agreement is found between median Vs profiles for common-site-and-depth comparisons (“red apples to red apples”).

3. Differences between median Vs profiles are mainly due to sampling volumes and geology.

4. For exploration areas with common parent material (covering small to large areas), c.o.v.s: • range from 0.10 to 0.20, with 0.15

representing a reasonable average value, and • increase near the surface (top 3 to 6m).

3. Applications: Traditional and Advanced Field Seismic Methods

• Site Characterization - layering, variability, soft zones, etc. • Evaluate Stiffness Properties - static and dynamic analyses - material type, “quality”, cementation, etc. • Monitoring Processes - compaction, consolidation, grouting, etc. • Liquefaction Evaluations • Form Link Between Field and Lab • Integrity Testing of Foundations

31

Page 34: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

3a. Embankment Dam Investigation: “Quality” of Alluvium in and beneath Dam

Embankment Core

Natural Alluvium

Bedrock

Reservoir ~200 ft (60 m)

1 2

1 2.5

Pervious Upstream Shell

Pervious and Semi-Pervious

Downstream Shell

Dam Site

Seismic Source

Drill Rig

SASW Test Locations - Downstream Face and Downstream Area

Downstream Area

Toe Road

Fence

Downstream Face

Bedrock

75 ft 25 ft

Downstream Shell; Compacted

Alluvium

Natural Alluvium

SASW Profiling Location and Depth

Note: All Testing Arrays Parallel to Crest

32

Page 35: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

0

5

10

150 5 10 15 20 25

No. of Profiles0 5 10 15 20 25

Depth (m

)

0.0 0.5 1.0

c.o.v.0.0 0.5 1.0

Zone of Disturbance (deleted VS values)

Shear Wave Velocity (ft/sec)0 500 1000 1500 2000 2500

Dep

th (f

t)

0

10

20

30

40

50

Shear Wave Velocity (m/sec)0 200 400 600

Depth (m

)

0

5

10

15

Individual VS Profiles Mean+/-

�mean

c.o.v. =

Avg. c.o.v. = 0.08

Statistical Analysis of Natural Alluvium

Comparison of Mean VS Profiles - Natural Alluvium and Compacted Alluvium in

Downstream Shell

Results: 1. Natural alluvium is stiff (VS �� 300 m/s); hence,

dense. 2. Compacted alluvium in

dam is dense and similar to natural alluvium.

3. Natural alluvium is not cemented.

4. No loose zone of alluvium under toe of dam.

5. Average COV < 0.15

Shear Wave Velocity (m/sec)0 200 400 600 800

(Inclined) Depth (m

)

0

5

10

15

Shear Wave Velocity (ft/sec)0 500 1000 1500 2000 2500 3000

(Incl

ined

) Dep

th (f

t)

0

10

20

30

40

50

Natural Alluvium(toe road and open area)Alluvium in Dam and Below

Mean VS:

Natural Alluvium

Beneath Dam(Inclined

Depth = 26 ft)

Dam Material

(CompactedAlluvium)

Inclined Depth

Dam Toe

Liquefaction Resistance from VS (Andrus and Stokoe, 2000)

0.0

0.2

0.4

0.6

0 100 200 300

6 to 34 %

No Liquefaction

Cyclic Stress or

Resistance Ratio, CSR

or CRR

Liquefaction

> 35 %

Mw = 7.5

Stress-Corrected VS, VS1, m/s

Fines Content < 5 % 20

Fines Content

(%)

>35 <5

Overburden-Stress

Correction for VS:

Vs1 = Vs(Pa/'vo)0.25

Pa = 2117 psf

'vo = depth * �t

33

Page 36: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Overburden - Stress Corrected VS1 Profile (Natural Alluvium - Downstream Area)

Shear Wave Velocity VS1 (m/sec)0 200 400 600 800

Depth (m)

0

5

10

15

Shear Wave Velocity VS1 (ft/sec)0 500 1000 1500 2000 2500 3000

Dept

h (ft

)

0

10

20

30

40

50

60

Mean VS1 Profile+/- (for 14 Prfiles)

Natural Alluvium:(Groups 1A, 1B and 4)

VS1* = Limiting Upper Value

Stress Corrected Vs, Vs1 (m/s)

Stress Corrected Vs, Vs1 (fps) Overburden-Stress Correction for VS: Vs1 = Vs(Pa/'

vo)0.32 Pa = 2117 psf 'vo = depth * �t

Average VS1 Assumed �t ~ 130 pcf Avg. Vs1 = 1250 fps (380 m/s)

Note: 1. VS1* equals limiting value for triggering of liquefaction in sand with fines < 5%, Mw = 7.5, and level ground conditions (Youd, Idriss et al., 2001)

3b. Vs Profiling on Big Island, Hawaii: Map of Geologic Units and SASW Test Locations

Geologic Units:

Basalt Ash/Tephra Artificial Fill Alluvium Sand Dunes Glacial Deposits Landslide Deposits

19 SASW test sites are on basalt and assumed VS > 2500 fps.

Sites of SASW Tests (Wong et al., 2008)

~N

Mahakuna Earthquake M = 6.0 15 Oct ‘06

Kiholo Bay Earthquake M = 6.7 15 Oct ‘06

Note:

Test Locations and Vs Profiles SASW Test Locations 22 VS Profiles

Legend:

~N

National Strong-Motion Network Stations

20 ml

Shear Wave Velocity (ft/sec)0 1000 2000 3000 4000

Dep

th (f

t)

0

50

100

150

200

250

300

Shear Wave Velocity (m/sec)0 500 1000

Depth (m

)

0

20

40

60

80

Averageat 35 ft

Mahakuna Earthquake M = 6.0 15 Oct ‘06

Kiholo Bay Earthquake M = 6.7 15 Oct ‘06

34

Page 37: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

0

20

40

60

80

0 5 10 15 20 25

No. of Profiles0 5 10 15 20 25

Depth (m

)

0.0 0.5 1.0

c.o.v.0.0 0.5 1.0

Shear Wave Velocity (m/sec)0 500 1000

Shear Wave Velocity (ft/sec)0 1000 2000 3000 4000

Dep

th (f

t)

0

50

100

150

200

250

300

Vs ProfilesMedian (N > 3)16th and 84th Percentiles

c.o.v. =

mean

Statistical Analysis of 20 Vs Profiles

Results: 1. Vs profiling to depths of 100 to 318 ft. 2. Surprise by low Vs values since 19 sites assumed to be NEHRP Site Class B (Vs,30 = 2500 to 5000 fps).

Depth (m

)

�mean

c.o.v. =

Avg. c.o.v. =

0.21

Template of Vs – Depth Relationships Used to Categorize Geotechnical Materials

Shear Wave Velocity (m/sec)0 500 1000

Depth (m

)

0

10

20

30

40

50

60

Shear Wave Velocity (ft/sec)0 1000 2000 3000 4000

Dep

th (f

t)

0

50

100

150

200

Average Water Table

at 35 ft

Unweathered Basalt Lower Boundary Vs ≥ 2200 fps at depths ≤ 100 ft

’o: effective isotropic confining pressure, Pa: atmospheric pressure in same units as ’o. Ko: earth pressure coef. = 0.5.

Legend:

Notes:

Dense Sand (SP) (V S = 837 ( ' o /P a )

0.26 ) C u = 2.5; D 50 = 0.5 mm; D r = 95%; e = 0.48; � sat = 132 pcf and

Dense Gravel (GW) (V S = 1025 ( ' o /P a )

0.33 ) C u = 35; D 50 = 5 mm; D r = 95%; e = 0.25; � sat = 145 pcf and

Menq (2003): Vs ≥ 2500 fps at depths > 100 ft

Vs,30 = 1153 fps

Vs,30 = 885 fps

Unweathered Basalt

Dense Sand

Dense Gravel

Analysis of 20 Vs Profiles: Identifying Unweathered Basalt

0

20

40

60

80

0 5 10 15 20 25

No. of Profiles0 5 10 15 20 25

Depth (m

)

0.0 0.5 1.0

c.o.v.0.0 0.5 1.0

Shear Wave Velocity (m/sec)0 500 1000

Shear Wave Velocity (ft/sec)0 1000 2000 3000 4000

Dep

th (f

t)

0

50

100

150

200

250

300

Vs ProfilesMedian (N > 3)16th and 84th Percentiles

c.o.v. =

mean

�mean

c.o.v. =

Avg. c.o.v. =

0.21

35

Page 38: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

0

20

40

60

80

0 5 10 15 20 25

No. of Profiles0 5 10 15 20 25

Depth (m

)

0.0 0.5 1.0

c.o.v.0.0 0.5 1.0

Shear Wave Velocity (m/sec)0 500 1000

Shear Wave Velocity (ft/sec)0 1000 2000 3000 4000

Dep

th (f

t)

0

50

100

150

200

250

300

Avg.c.o.v. = 0.11

c.o.v. =

mean

Statistical Analysis of Unweathered Basalt

No. of Locations: 14

�mean

c.o.v. =

Avg. c.o.v. =

0.11

0

20

40

60

80

0 5 10 15 20 25

No. of Profiles0 5 10 15 20 25

Depth (m

)

0.0 0.5 1.0

c.o.v.0.0 0.5 1.0

Shear Wave Velocity (m/sec)0 500 1000

Shear Wave Velocity (ft/sec)0 1000 2000 3000 4000

Dep

th (f

t)

0

50

100

150

200

250

300

Average Water Table

at 35 ft

Statistical Analysis of Weathered Basalt

No. of Locations: 16

Vs Profiles Median 16th and 84th Percentiles Dense Sand Dense Gravel

�mean

c.o.v. =

Avg. c.o.v. =

0.10

0

20

40

60

80

0 5 10 15 20 25

No. of Profiles0 5 10 15 20 25

Depth (m

)

0.0 0.5 1.0

c.o.v.0.0 0.5 1.0

Shear Wave Velocity (m/sec)0 500 1000

Shear Wave Velocity (ft/sec)0 1000 2000 3000 4000

Dep

th (f

t)

0

50

100

150

200

250

300

Average Water Table

at 35 ft

Statistical Analysis of Stiff Soil

Vs Profiles Median 16th and 84th Percentiles Dense Sand Dense Gravel

No. of Locations: 16

�mean

c.o.v. =

Avg. c.o.v. =

0.09

36

Page 39: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Sites of SASW Tests (Wong et al., 2008)

Geologic Units:

Basalt Ash/Tephra Artificial Fill Alluvium Sand Dunes Glacial Deposits Landslide Deposits

Note: 19 SASW test locations are on basalt.

~N

Mahakuna Earthquake M = 6.0 15 Oct ‘06

Kiholo Bay Earthquake M = 6.7 15 Oct ‘06

Map of Geologic Units and SASW Test Locations

Example Interpreted Geotechnical Profiles

Shear Wave Velocity (m/sec)0 500 1000

Depth (m

)

0

10

20

30

40

50

60

Shear Wave Velocity (ft/sec)0 1000 2000 3000 4000

Dep

th (f

t)

0

50

100

150

200

Shear Wave Velocity (m/sec)0 500 1000

Depth (m

)

0

10

20

30

40

50

60

Shear Wave Velocity (ft/sec)0 1000 2000 3000 4000

Dep

th (f

t)

0

50

100

150

200

Pohoa Fire Station NEHRP Site Class : C Vs,30 = 1497 fps

Mac Farms NEHRP Site Class : D Vs,30 = 1086 fps

Stiff Soil Weathered

Basalt

Basalt

Stiff Soil

Basalt

3c. Advanced Seismic Testing: Deep (d > 225m) Field Investigations

1. Yucca Mountain, Nevada • SASW method • Plan dimensions of area: 3 km x 10 km • Profiling to 450 m

2. Hanford, Washington • Downhole method with T-Rex • 3 boreholes within about 700 m • Profiling to 420 m 37

Page 40: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Recording Surface Waves up to 1000 m Long at Yucca Mountain

Liquidator

0 2 4 6 8 10

0

100

200

300

400

500

600

No. of Profiles0 2 4 6 8 10

Depth (m

)

0.0 0.5 1.0

c.o.v.0.0 0.5 1.0

Shear Wave Velocity (m/sec)0 1000 2000 3000

Shear Wave Velocity (ft/sec)0 2000 4000 6000 8000 10000

Dep

th (f

t)

0

500

1000

1500

2000

SASW Vs ProfilesMedian16th and 84th Percentile

Statistical Analysis of Softer VS Profiles Associated with One Area (Lin, 2007)

�mean

c.o.v. = N ≥ 3

3d. Link Between Field and Lab: Predicting Ground Motions During an Earthquake

0.2%

0.02%

7 MPa

56 MPa

G

G

BEDROCK

SOIL LAYER 1

SOIL LAYER 2

ROCK LAYER 2

ROCK LAYER 1

Soft”

Stiff”

Shear Waves from Earthquake 38

Page 41: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Estimating the Field G – log �� Relationship

Note: G� field = Gmax field Gmax lab G� lab

Shea

r Mod

ulus

, G, 1

03 k

sf

Typical Soil

Shearing Strain, �, %�

Field

Lab Curve

100 10-1 10-5 10-4 10-3 10-2

2.0

1.5

0.5

0

1.0

Estimated Field Curve

EQ

Estimating the Field G – log �� Relationship

Note: G� field = Gmax field Gmax lab G� lab

Shea

r Mod

ulus

, G, 1

03 k

sf

Shearing Strain, �, %

Shea

r Mod

ulus

, G, 1

03 k

sf

Typical Soil Typical Rock

Shearing Strain, �, %�

Field

Lab Curve

100 10-1 10-5 10-4 10-3 10-2

2.0

1.5

0.5

0

1.0

Estimated Field Curve

0

Lab Curve

500

400

100

300

200

600

Field

Estimated Field Curve

100 10-1 10-5 10-4 10-3 10-2

EQ

EQ

Relationship Between Field and Laboratory VS Values

Typical Soil Typical Rock 5

4

3

2

1

0 3000 2500 2000 1500 1000 500 0

Field Shear Wave Velocity, Vs, field, m/s

Shea

r Wav

e Ve

loci

ty R

atio

, Vs,

lab/V

s, fi

eld

No. of Specimens = 47 (Cored Samples)

Trend Line

Range

1000 Field Shear Wave Velocity, Vs, field, m/s

Shea

r Wav

e Ve

loci

ty R

atio

, Vs,

lab/V

s, fi

eld

1.2

1.0

0.8

0.6

0.4

0.2

0.0 800 600 400 200 0

Trend Line Range

No. of Specimens = 63 (Push-Tube Samples)

39

Page 42: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

4. Next Generation Test Methods: Parametric Studies in the Field

• Vary Stress State – log Vs – log o’ and log Vp – log o’

• Vary Strain Amplitude – G – log ��and G/Gmax – log ��

• Vary Strain Amplitude and N – �u - log ��at given numbers of cycles

(liquefaction testing)

4a. Next Generation Testing: Nonlinear Shear Modulus Measurements

Surface Footing (Park, 2010)

Static Load

Dynamic Horiz. Load

Footing

Embedded Sensor Array

Svh

Dynamic Vertical Load

Shv

Drilled Shaft

Embedded Sensor Array

Deep Foundation (Kurtulus, 2006)

Linear and Nonlinear Steady-State Dynamic Tests: Yucca Mountain (Park, 2010)

3-ft diameter footing

Thumper

(b) G - log γ 10000

9000

8000

7000

6000

5000

4000

3000

2000

1000

0

Shea

r M

odul

us, k

sf

10-5 10-4 10-3 10-2 10-1

Shearing Strain, %

450

400

350

300

250

200

150

100

50

0

Shear Modulus, M

Pa

Steady-State Testing Using Thumper

Lower Muck YardStatic Load Level: ~4,000 lbs(Average in-situ vertical stressis estimated as ~5 psi) Excitation Frequency: 130 Hz

Uncemented Gravel (Menq, 2003) (Cu = 50, v = 5 psi, Ko= 0.5)

(a) Test –Set-up

40

Page 43: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

4b. Next Generation Testing: In-Situ Liquefaction Measurements (Cox, 2006)

GWL

Liquefiable Layer

Sensors (nodes)

2 ft

#1 #2

#3 #4

2 ft

4 ft

#5

Stiff, Less Permeable Surface Layer(s)

Trapezoidal Array

~3 to 5 m

Trapezoidal 2D Array

0.6 m

0.6 m

1.2 m

Hydraulic Ram

T-Rex

Highest Amplitude

10 Hz – 200 cycles • Nonlinear shear strain

time history • Major nonlinear

development coincides with sharp pressure increase at node #3

• Pore pressure ratios and shear moduli resulting from more than 100 cycles of loading are not included in the results

~ 30000 lbs

~ 0.075 %

~ 23 %

Lab

���te

n = 10; ru = 2% n = 20; ru = 5%

n = 50; ru = 12%

n = 100; ru = 23%

Combined Modulus Degradation

and Nonlinearity

Results for Site C • Dobry’s Pore

Pressure Model (Vucetic and Dobry, 1986)

– Developed from cyclic laboratory tests on liquefiable soils from the Wildlife Site

– Assumed cyclic threshold shear strain of 0.02%

Series 2

Max ru = 23%

���tc

41

Page 44: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

Liquefaction Resistance from VS (Andrus and Stokoe, 2000)

0.0

0.2

0.4

0.6

0 100 200 300

6 to 34 %

No Liquefaction

Cyclic Stress or

Resistance Ratio, CSR

or CRR

Liquefaction

> 35 %

Mw = 7.5

Stress-Corrected VS, VS1, m/s

Fines Content < 5 % 20

Fines Content

(%)

>35 <5 Overburden-Stress

Correction for VS:

Vs1 = Vs(Pa/'vo)0.25

Pa = 2117 psf

'vo = depth * �t

Average VS1:

Avg. Vs1 = 110 m/s

(361 fps)

4. Next-Generation Test Methods and Future Directions (continued)

• Field Measurements – develop full-waveform analyses – develop techniques to identify soil types – perform suites of geophysical tests – combine R and Love wave measurements – investigate M – log �� , D – log � , etc.

• Laboratory Measurements – develop capabilities to measure at � > 1% – develop nonlinear models of test specimens – develop capabilities to measure Vp, M, and Dp

– improve automation • Education

Concluding Remarks

� Seismic (stress wave) measurements play an important role in geotechnical engineering.

� This role will continue to grow in solving static and dynamic problems.

�� The growth will involve four areas: 1. education, 2. integration, 3. automation,

and 4. innovation. 42

Page 45: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

THANK YOU

43

Page 46: Acttiivvee RRiisskk Mannaagge emmen ntt iin Ge ...ceprofs.civil.tamu.edu/briaud/Buchanan Web... · L eeccturre Byy rDD r.. AA llleenn MMaarrr . Table of Contents . Spencer J. Buchanan

44