TVA Nuclear Safety Initiatives After Fukushimagrouper.ieee.org/groups/npec/N12-01/NPEC for JDW 2012...
Transcript of TVA Nuclear Safety Initiatives After Fukushimagrouper.ieee.org/groups/npec/N12-01/NPEC for JDW 2012...
Nuclear Power Group1
TVA Nuclear Safety Initiatives After Fukushima
IEEE Nuclear Power Engineering Committee Winter 2012Joe D. Williams
General Manager Design EngineeringTVA Nuclear Power Group
Nuclear Power Group
• The Fukushima Daiichi Event• What Made Fukushima Daiichi
Different?• TVA Lessons Learned from
Fukushima Daiichi– Site Considerations– Regional Events Considerations
• TVA’s Commitment to Safe Nuclear Power
TopicsTopics
2
Nuclear Power Group3
The Fukushima Daiichi EventThe Fukushima Daiichi Event
Nuclear Power Group
• March 11 @ 1446 – 9.0 earthquake strikes
– Epicenter is at sea ~200 km north of Fukushima– Design basis earthquake for the plant was 8.2– Seismic monitors initiate automatic shutdown on 11 reactors
• Fukushima Daiichi, Fukushima Daini, Onagawa and Tokai • All subsystems work as designed but offsite power is lost
– Emergency Diesel Generators start and load as designed– Core cooling systems are started to remove the decay heat
• March 11 @ 1545 – Tsunami hits Fukushima Daiichi
– All Emergency Diesel Generators are flooded and incapacitated
– Station batteries last 1-8 hours– DC is exhausted, core cooling and spent fuel pool cooling
are lost4
Sequence of EventsSequence of Events
Nuclear Power Group5
Tsunami at Fukushima DaiichiTsunami at Fukushima Daiichi
Emergency diesels and electrical boards
Nuclear Power Group
• Wide area loss of grid– Simultaneous trip of multiple units and plants– Nuclear, fossil and hydro plants lost – Instant drop in grid capacity: 52,000 to 31,000
MW• Workforce was impaired or unable to respond• Communication with support organizations
impaired • Access to drawings, procedures and data impaired• Leads to loss of assets and radiation releases
6
Results of Quake and Tsunami Results of Quake and Tsunami
Nuclear Power Group
What Made Fukushima Daiichi Different?What Made Fukushima Daiichi Different?
7
Nuclear Power Group
• Onsite– Beyond design basis event
• Tsunami was 42’ versus 17’ feet expected– Breached the seawall– Flooded ground floor and basement elevations– Flooded the switchyard and relay house– Impaired EDGs, batteries and board rooms
– Some units were in outage• Hot fuel was in the spent fuel pool
– Loss of core and spent fuel cooling• Decision to vent H2 was delayed• Loss of facility and large radiation release
Factors Which Made a DifferenceFactors Which Made a Difference
8
Nuclear Power Group
• Offsite– It was a regional disaster– Multiple plants and units effected– Widespread loss of the grid– Impaired response
• Infrastructure breakdown– Transportation– Communication
• Loss of workers, their families and homes
Factors Which Made a DifferenceFactors Which Made a Difference
9
Nuclear Power Group
• Fukushima Daiichi offsite power provided at 275 kV and 500 kV
– Having only HV and EHV offsite connections slowed restoration times
• Offsite power restoration times per TEPCO– U1 - 13 days– U2 - 15 days– U3 - 11 days– U4 - 18 days– U5 - 11 days– U6 - 11 days
Factors Which Made a DifferenceFactors Which Made a Difference
10
Nuclear Power Group11
TVA Lessons LearnedTVA Lessons Learned
Nuclear Power Group
1. Protect the public and the environment2. Preserve the asset
Characteristics of success– Provide motive power to critical plant components
• For core and spent fuel pool cooling• Keep temperature in the spent fuel pool under 200oF
– Get all reactors to cold shutdown– No fuel damage– No radiation releases– Address vulnerabilities to ‘stacked’ events– Must be able to handle regional events
TVA Lessons Learned - Definition of SuccessTVA Lessons Learned - Definition of Success
12
Nuclear Power Group
• Its all about power– Need to extend battery life
• Add dedicated diesel generators in-plant (no transport)– Add more large portable diesel generators (LPDGs)
• Both onsite and remote– For motive power and battery recharging
• Seismically harden onsite storage shelters– Seismically harden the switchyards
• Avoids potential fires – From tipping of transformers and breakage of bushings
• Facilitates restoration of offsite power
• Diversify means to refill the spent fuel pool– With and without AC power
• Timely H2 venting is critical13
TVA Lessons Learned – OnsiteTVA Lessons Learned – Onsite
Nuclear Power Group
• Station batteries– TVA coping time for SBO is 4 hrs
• Achieved with some load shedding
– Extended coping dictates Battery DGs (BDGs) must be permanently installed in their needed location
– BDGs be sized to power chargers plus one channel of load
– BDGs will backfeed electrical boards through a dedicated welding receptacle
• Portable battery carts– Motive/control power for devices– Easily transported– Procedure controlled – Operators trained
TVA Lessons Learned – Onsite (Batteries)TVA Lessons Learned – Onsite (Batteries)
14
Nuclear Power Group
• TVA planning assumes all installed EDGs will be lost
• Provide multiple connection points for LPDGs
– Connection points must be widely spaced and above flood elev– Use modified ground trucks to backfeed boards
• LPDG placement must consider:– Access, especially for flood– Storage, transport (limits size), connection and refueling– Must consider seismic aftershock durability– Match generation voltage to plant grid
• Eliminates interposing transformer
TVA Lessons Learned – Onsite (LPDGs)TVA Lessons Learned – Onsite (LPDGs)
15
Nuclear Power Group
• Restoration of offsite power is crucial– “Lost but recovered in 5 hrs at Fukushima Daini”
• No significant issues– Only “momentarily lost” at Onagawa
• Closer to the epicenter than either Fukushima plant• No significant issues
– Offsite power at both plants helped contain events• Site elevations also played a role
• Benefits of the grid– Much “stiffer” than diesel generator power– High capacity compared to need– High reliability compared to diesel power– Eliminates logistical problems of fuel resupply– Onsite distribution must be available for any benefit of grid
• Not enough consideration has been given to regional events
16
TVA Lessons Learned – OffsiteTVA Lessons Learned – Offsite
Nuclear Power Group
• Restoring existing lines– Daiichi had 275 and 500 kV
lines– Having only HV and EHV
connections delayed restoration– Offsite power “available” 11-18
days after the quake/tsunami
• Consider new emergency lines
– Mobile transformers may be needed to connect with the plant power system
• Difficult transport if highway infrastructure is damaged
– Local distribution voltage can be erected faster than HV/EHV
• Lesson learned for all plants
17
TVA Lessons Learned – Offsite (Grid)TVA Lessons Learned – Offsite (Grid)
Offsite power restoration at Fukushima Daiichi in
full dress-out
Nuclear Power Group
• April 27, 2011
TVA’s Regional Event – Tornado StormTVA’s Regional Event – Tornado Storm
18
Red is tornado, blue is high wind and yellow is hail.226 tornadoes in 24 hrs; left 330 dead, 230 in AL alone
Nuclear Power Group
TVA’s Regional Event – Tornado StormTVA’s Regional Event – Tornado Storm
19
• Several plants off-line including all 3 units at Browns Ferry
• 350 transmission structures damaged or destroyed including:
– All 500 kV lines in N. AL and N. MS– One of two 161 kV offsite lines to
Browns Ferry• Remaining line had limited
capacity• Plant remains on EDGs for five days• 108 lines out of service• 128 customer connections broken• 850,000 customers without power
Nuclear Power Group
TVA’s Regional Event – Tornado StormTVA’s Regional Event – Tornado Storm
20
• 4,000 workers • 24/7 task• Within 5 days
– 121 of 128 distributors and direct-serve customer connections were restored
• Last 500-kV line was restored June 30th
• $39M in repairs• $95M for replacement
power
Nuclear Power Group
TVA’s Regional Event – Lessons LearnedTVA’s Regional Event – Lessons Learned
• Communication assets need upgrading• Chattanooga Emergency Center needs
hardening• Multi-unit events need to be part of standard
drills• Drills must involve Nuclear and Transmission• Emergency warning sirens need alternate
power source• Reliability of existing rented temporary diesel
generators needs improvement• Evaluating installation of some offsite feeders
underground
21
Nuclear Power Group
Other Regional Events - FloodingOther Regional Events - Flooding
22
Flood levels are categorized as a near impossible flooddue to rainfall/dam failures event (substantially greater than a 10,000-year flood)
Sequoyah and Watts Bar are designed to have the structures and systems capable for cooling the fuel during this event TVA is evaluating options to harden sites Berms and Dikes Making structures water-tight to higher elevations
Nuclear Power Group
• Potential initiator of regional event– Higher frequency event than DBE– Could cause widespread loss of
grid– Could damage critical
transformers– Short duration needing fast
response• TVA actions
– Evaluating transformer susceptibilities
• Developing monitoring and response strategies
– Scripting plant operator responses to grid alert
Regional Events - Geomagnetic StormsRegional Events - Geomagnetic Storms
23
Nuclear Power Group
• Offsite Power is Crucial• Switchyards should be hardened
– Including fire protection– Seismically anchor transformers, breakers etc
• Procure spare mobile power transformers– In case onsite units are destroyed/damaged
• Stock spare HV/EHV bushings– Most vulnerable element
• Need structured offsite power restoration strategies with transmission provider
• Black-start switchyards and relay rooms must also be hardened
Regional Events - SeismicRegional Events - Seismic
24
Nuclear Power Group
• Identify transmission lines to black-start units– Don’t rely on those with river crossings
• Long restoration times– Consider distribution level feed from local utility– Stockpile tower steel, line conductor and
insulators– Evaluate required logistics (storage,
transportation etc)• Joint Nuclear and Transmission activities
– Relocate emergency centers to common structure
Regional Events – The GridRegional Events – The Grid
25
Nuclear Power Group
TVA Commitment to NuclearTVA Commitment to Nuclear• Established 1934• 88,000 square miles
– Parts of seven states• Generation and
transmission– No distribution
• Approx 33,000 MW– 11 fossil plants, 59 units– 29 power dams, 117
units– 20 non-power dams– 1 pumped storage plant
• 4 units– 3 nuclear plants
• 6 operating units
Nuclear Power Group
• Nuclear power is safe and being made safer– This is a learning industry
• It makes sense for the environment– No greenhouse gases– Minimizes dependence on widespread strip
mining• Permanent siting of spent fuel remains a national
policy issue– Interim on-site storage is current policy
Why a Nuclear Future?Why a Nuclear Future?
27
Nuclear Power Group
Nuclear Power’s Increasing RoleNuclear Power’s Increasing Role
28
Nuclear Power Group
A More Balanced Power SupplyA More Balanced Power Supply
29
Nuclear Power Group
• Westinghouse PWR• 1,180 MW• Construction halted
1985– Restarted 2007
• Expected online in 2013
Watts Bar Unit 2Watts Bar Unit 2
30
Nuclear Power Group
• B&W PWR• 1,260 MW• Deferred in 1988• Board approved U1
completion Aug 2011
• Online by ~ 2020
Bellefonte 1Bellefonte 1
31
Nuclear Power Group
• 125-megawatt reactors would be built in groups• Could replace aging coal units and use existing
sites and transmission• “Passive” safety design w/underground
containment• 4 to 5-year fuel cycle• mPower group plans to demonstrate this
technology by 2020 near Oak Ridge, TN
Small Modular ReactorsSmall Modular Reactors
32
Nuclear Power Group
Timeline for New ProjectsTimeline for New Projects
33
Nuclear Power Group
Questions?Questions?
34