Power Quality Improvement of Incoming Supply (TNEB)
![Page 2: sujesh](https://reader035.fdocuments.fr/reader035/viewer/2022062523/58a2c37a1a28ab217a8b5235/html5/thumbnails/2.jpg)
Steps planned to Improve Power Quality:
1. Install HT AVR to ensure Voltage variation within ±1%.
2. Install UPS to reduce losses due to Power Brown outs & Black
outs (M/c Breakdown, Tool Breakdown etc.).
3. Upgrade the Voltage from 11KV to 33KV.
Steps Planned to Improve Power Quality
![Page 3: sujesh](https://reader035.fdocuments.fr/reader035/viewer/2022062523/58a2c37a1a28ab217a8b5235/html5/thumbnails/3.jpg)
• Failure of Motor windings in Heat Treatment Machines due to Low voltage (VHF, SQF etc.,). • Imported CNC,PLC M/c’s fails to run without coolant pump due to voltage fluctuation.
• lights are flickering and capacitors burst due to low voltage.
• Frequent tripping of Circuit breakers due to low voltage during full load.
• Frequent tripping of Air conditioner and compressors due to voltage fluctuation.
Problems occurred before installing AVR
![Page 4: sujesh](https://reader035.fdocuments.fr/reader035/viewer/2022062523/58a2c37a1a28ab217a8b5235/html5/thumbnails/4.jpg)
4
AVR Installation
BeforeAfter
Incoming supply (TNEB)VCB
2
Bus bar
Tr-1 Tr-2 Tr-3 Tr-4
Load LoadLoadLoad
Tr-1 Tr-2 Tr-3 Tr-4
Load LoadLoadLoad
Bus barVCB 2
VCB 1
Incoming supply (TNEB)
6.3 MVA AVR
Additionally Inserted
![Page 5: sujesh](https://reader035.fdocuments.fr/reader035/viewer/2022062523/58a2c37a1a28ab217a8b5235/html5/thumbnails/5.jpg)
5
AVR system installed
![Page 6: sujesh](https://reader035.fdocuments.fr/reader035/viewer/2022062523/58a2c37a1a28ab217a8b5235/html5/thumbnails/6.jpg)
Voltage stabilization process in LT side
Input voltage to AVR : 9000V to 12000VOutput voltage from AVR : 11000V ± 1% (10890V to 11110V)
Stabilization process : HT voltage LT voltage
conventional : 9000V to 12000V 340V to 470V
Recommended : 11000V±1% 415V±6% (i.e.390V
to 440V)
By AVR : 11000V±1% 410V to 420V
![Page 7: sujesh](https://reader035.fdocuments.fr/reader035/viewer/2022062523/58a2c37a1a28ab217a8b5235/html5/thumbnails/7.jpg)
7
voltage bandwidth for motors
D
GOOD
ALLOWED
DANGEROUS
410V
420V
390V
440V
340V
470V
Voltage Bandwidth
![Page 8: sujesh](https://reader035.fdocuments.fr/reader035/viewer/2022062523/58a2c37a1a28ab217a8b5235/html5/thumbnails/8.jpg)
Voltage in LT before & after installation of AVRVoltage in LT side
050
100150200250300350400450500
Time
Volta
ge
Before After Required
![Page 9: sujesh](https://reader035.fdocuments.fr/reader035/viewer/2022062523/58a2c37a1a28ab217a8b5235/html5/thumbnails/9.jpg)
9
After installation of AVRAvoided M/c brownouts, blackouts due to voltage
variation.
Avoided failure of Motor winding and CNC M/c down time due
to voltage fluctuation.
Avoided failure of lights and fans due to low voltage.
Avoided tripping of Air conditioner and compressors due to under voltage.
![Page 10: sujesh](https://reader035.fdocuments.fr/reader035/viewer/2022062523/58a2c37a1a28ab217a8b5235/html5/thumbnails/10.jpg)
10
Up gradation of voltage from 11 KV to 33 KV
6.3 MVA AVR
33 KV TNEB SUPPLY
RMG 33 KV VCB
6.3 MVA,33KV / 11KV TRANSFORMER
11 KV VCB
VCB
VCB VCB VCB
To Power House To
DI building To E & D
![Page 11: sujesh](https://reader035.fdocuments.fr/reader035/viewer/2022062523/58a2c37a1a28ab217a8b5235/html5/thumbnails/11.jpg)
11
Increasing the Capacity of UPS
Bus bar
Tr-1 Tr-2 Tr-3 Tr-4
Load LoadLoad
160 KVA
Existing
160 KVA 550 KVA 160 KVA
Load
Existing CapacityRotary = 870 KVAUPCR = 160 KVA
Planned CapacityRotary = 2360KVAUPCR = 320 KVA