Lags in precedence networks

Transcript of Lec 12 lags

Page 1: Lec 12 lags

Lags in precedence networks

Page 2: Lec 12 lags
Page 3: Lec 12 lags
Page 4: Lec 12 lags
Page 5: Lec 12 lags
Page 6: Lec 12 lags
Page 7: Lec 12 lags

Lag Time

• When an activity is completed, and there is a delay or wait period before the second activity starts, this is called lag and the delay is known as the Lag Time.

• A lag specifies an offset or delay between an activity and its successor

• Lags can be used to constrain the start and finish of an activity

• Can be a positive or a negative value

Page 8: Lec 12 lags

Example

• Suppose you have to paint a newly constructed room.

• So the first activity would be applying the primer coating and then you will go for the final painting.

• However, after applying the primer coating, you must give it some time to dry properly. Once the primer coating dries, you can start final painting.

• The time given for coating to dry itself is called the lag time.

Page 9: Lec 12 lags

Lag Time

• FS +1:• For example, the time duration

for the first activity is 3 days, and for the second activity it is 2 days.

• After completing the first activity you wait for one day, and then you start second activity.

• Lag Time is one day• Finish to Start activity with one

day delay or lag.

Page 10: Lec 12 lags
Page 11: Lec 12 lags
Page 12: Lec 12 lags

Example 1

Page 13: Lec 12 lags

Answer

Page 14: Lec 12 lags

Example 2

Page 15: Lec 12 lags

Answer

Page 16: Lec 12 lags

Example 3

Page 17: Lec 12 lags

Answer

Page 18: Lec 12 lags

Example: a successor finishes before the predecessor

Excavate-1 Subbase-7 Lay pipe-4 Backfill-3 Compact-2

1 2 1 1

Page 19: Lec 12 lags

In this example, FF relationships ensure that no successor can finish before its predecessor.

Subbase cannot start till at least 1 day after excavate has started.Subbase cannot finish earlier than 1 day after the finish of excavate.

Excavate Subbase-7 Lay pipe-4 Backfill-3 Compact-2

1 2 1 1

1 1 2 1

Page 20: Lec 12 lags

CPM calculations for precedence networks

CPM calculations for precedence diagrams are similar to, but not the same as the CPM calculations discussed previously.

The following example illustrate the calculations procedure.

A-5 B-7 C-3 Figure6

0 5

0 7

0 7

0 7 74

0 7

Page 21: Lec 12 lags

In the forward pass, Activity A starts the projects. ES=0, EF=0+5=5Activity B is connected to A by 2 relationships: SS and FF. ES(B)= ES (A)+lag(if any) = 0, However the early finish of B is controlled by the max of: EF(B)=ES(B) +Dur = 0+7=7 or EF(B)= EF(A)+lag(if any) = 5 Thus, EF(B)=7

The same method applies for C.ES (C)=ES(B)+lag(if any) = 0, However the early finish of C is controlled by the max of: EF(C)=ES(C) +Dur = 0+3=3 or EF(C)= EF(B)+lag(if any) = 7 Thus, EF(C)=7

Page 22: Lec 12 lags

In the backward pass, Activity C must finish no earlier than day 7. LF(C)=7, LS=7-3=4

Activity B must finish no later than the LF(C). LF(B)= LF(C)-lag(if any) = 7, However the latest start of B is controlled by the min of: LS(B)=LF(B) - Dur = 7-7=0 or LS(B)= LS(C)-lag(if any) = 4 Thus, LS(B)=0

Activity A must finish no later than the LF(B).LF (A)=LF(B)-lag(if any) = 7, However the latest start of A is controlled by the min of: LS(A)=LF(A) - Dur = 7-5=2 or LS(B)= LS(B)-lag(if any) = 0 Thus, LS(A)=0

Page 23: Lec 12 lags

A-5 B-7 C-3 Figure6

0 5

0 7

0 7

0 7 74

0 7

In figure6, activity A must start at 0 otherwise activity B, which is critical, will be delayed. Activity A has 2 days of restricted float(start-restricted float).

Activity C has 4 days of float at its start. However, no matter when it starts, it must finish on day 7.C has 4 days restricted float (finish-start float).

Page 24: Lec 12 lags

Unlike the arrow and node diagrams, precedence networks may show the start or finish of an activity to be critical while the rest of the activity is not.

A-10 B-3 C-5 Figure7

0 10

0 10

2 10

2 10 105

5 102 3

In figure7, both A and C are completely critical. Activity B has a critical start and a critical finish but is not critical.

Activity B must start on day 2 and must finish on day 10. note that B has a duration of 3 days, but must fill an 8-day interval. Thus B has 5days double-restricted float(start-finish-restricted float)

Page 25: Lec 12 lags

Example:

Activity Duration (weeks)

Immediate predecessors

Type of relation

Lag

A 2 ----

B 6 A

C 11 A SS 1

D 7 B SS, 2

FF 0

E 4 B

C FF 5

F 8 ----

G 3 D,E

F FF 4

Page 26: Lec 12 lags

Start

C-11

A-2 B-6 D-7

F-8

E-4 G-3

8

1

4

0 2

0 7

1 12

1 12

4 11

10 17

17 20

17 20

0 8

2

16

2 8

7 13

8 17

13 17

Page 27: Lec 12 lags

Forward pass, Activity A: starts the projects. ES=0, EF=0+2=2Activity B: ES(B)= EF (A)= 2, EF(B)=2+6=7Activity C: ES(C) = ES(A)+lag=1+0=1 , EF(C)= 1+11=12Activity D: ES(D) = ES(B)+lag=2+2=4 , EF(D)= max{4+7=11 or 8}=11Activity E: ES(E)=8, EF(E)= MAX{8+4=12 or 12+5=17}=17Activity F: ES(F)=0, EF(F)= 0+8=8Activity G: ES(G)=max{EF(E)=17,EF(B)=11}=17 , EF(G)=max{ES(G)+Dur=17+3=20 or EF(F)+Lag=8+4=12}=20

Page 28: Lec 12 lags

Backward pass, Activity G: LF(G)=20, LS(G)=20-3=17Activity F: LF(F)=LF(G)-Lag=20-4=16,LS(F)=16-8=8Activity E: LF(E) =17, LS(E)= 17-4=13Activity D: LF(D) = 17, LS(D)=17-7=10Activity B: LF(B)=min{LF(D)=17 or LS(E)=13}=13, LS(B)=min{LF(B)-Dur=13-6=7 or LS(D)-Lag= 10-2=8}=7Activity C: LF(C)=LF(E)-Lag= 17-5=12, LS(C)= 12-11=1Activity A: LF(A)=LS(B)=7, LS(A)=min{LS(C) -Lag =1-1=0 or LS(A)-Dur=7-2=5}=0

Page 29: Lec 12 lags

Critical Path

• Start of A-C- end of E-G • Duration : lag 1+ 11+lag 5 +3= 20