DAILY INSPECTION REPORT
Transcript of DAILY INSPECTION REPORT
Govt. of India Funded Reconstruction of 70 School Buildings and 1 Library Facility in Earthquake Affected Districts of Nepal
DAILY INSPECTION REPORT
REPORT NO: KAV_40_4675 PMC ENGINEER MdMohsinNAME OF PROJECT: 40-Laxmi Narayan Uchha Madhyamik
VidyalayaDATE: 18/10/2021
LOCATION KAVREPALANCHOK \ Acharyagaun
SCHOOL ID: 40
EMIS CODE: 240840002 STRUCTURALDETAIL:
RCC Framed Structure
CONCRETE: Nominal Mix M25 GRADE OFSTEEL:
FE-500
CONTRACTINGAGENCY:
M/S Khani Bright J/V
Project START DATE: 18-02-2020 Project END DATE: 14/4/2021
Weather
Sunny Cloudy Windy Rainy
Ambient Temperature °C
Min 16 Max 26
CONRACTOR's MANPOWERCATEGORY NO. CATEGORY NO.PROJECT MANAGER 0 LABOURENGINEER 1 Skilled 3Foreman 1 Unskilled 3Technician 0Operator 0
PLANT & EQUIPMENTTYPE: QTY: STATUS:Water pump 2 NormalDrilling machine 2 NormalGrinding machine 2 NormalDC generator 2 Normal
LATEST SITE PROGRESS PHOTOS
Painting work going on Painting work going on
Page 1 of 4
Govt. of India Funded Reconstruction of 70 School Buildings and 1 Library Facility in Earthquake Affected Districts of Nepal
DAILY INSPECTION REPORT
NON COMPLIANCES & SUGGESTIONSS.No. Description Status1 Instructions to Contractor for site clearence New
MATERIAL RECEIVED AT SITES.No ITEM UNIT QTY ACCEPTED/REJECTED
1 Sand 8 cum Accepted
2 Cement 220 nos Accepted
Sand Cement
PaintTESTS CONDUCTED AT SITE
Page 2 of 4
Govt. of India Funded Reconstruction of 70 School Buildings and 1 Library Facility in Earthquake Affected Districts of Nepal
DAILY INSPECTION REPORT
S.No LOCATION ACTIVITY RESULTS COMPLIANCE(Y/N)
Block: 24(3S-13C)
CONSTRUCTION ACTIVITESS.No.
Activity in progress StatusYes/No/NA
Description AcceptedYes/No
1 Dismantling yes Completed yes2 Earthwork yes Completed yes3 PCC work yes Completed yes4 RCC work yes Completed yes5 Brick work yes Completed yes6 Stone work yes Completed yes7 Metal work
Truss/Railingyes Completed yes
8 Door & Window works yes Going on yes9 Flooring work yes Going on yes10 Roofing yes Completed yes11 Plaster work yes Completed yes12 Painting yes Going on yes13 Cement Board Wall n/a14 False Ceiling n/a15 Electrical Work n/a16 Sanitary Work n/a17 Others n/a
Front Elevation Back Elevation
Block: 24(3S-13C)
GENERAL CHECKLISTS.No. Action/Measure Status Yes/No/NA Details/Remarks1 Site Office is fully established as per contract yes Esy2 Construction site is barricaded yes Barricated3 Hoarding Board for Project Information is installed yes Installed4 Contract Documents, Specification are available yes Available5 Complete set of working drawings is available at
siteyes Available
6 Adequate Manpower at site construction progress no Not available
Page 3 of 4
Govt. of India Funded Reconstruction of 70 School Buildings and 1 Library Facility in Earthquake Affected Districts of Nepal
DAILY INSPECTION REPORT
7 Quality Control Laboratory is established & wellequipped
no
8 Calibration certificates for Testing Equipments areavailable
no
9 Special test on Materials to be performed outsideSite
yes Performed
10 Inspection Register is maintained yes Maintained11 Cement store is cheked and found OK. yes Checked and found ok.12 Cement Register is maintained. yes Maintained13 Construction Materials are stored properly. yes Stored properly14 Construction Equipments are in good working
conditionyes Good
15 Timely compliance of Non conformities / Defects &PMC Instructions
yes
16 Material sampling & testing done as per requiredfrequency
yes Done
17 Material Test reports are maintained at site yes Maintained18 Cube samples for concrete taken for daily
concrete work & testedyes Taken
19 Safety measures pertaining to construction worksfollowed as per relevant safety codes & nationalregulations
no
20 Personal Protective Equipments are being usedwithin the construction area -Helmets,Gloves,Boot,Safety glasses/faceshields,earplugs/ear muffs,First Aid tools,etc.
no
Page 4 of 4