COMIT EUROPEN DES ASSURANCES
SECRETARIAT GENERAL 3bis, rue de la Chausse d'Antin F 75009 Paris
Tl. : +33 1 44 83 11 73 Fax : +33 1 44 83 11 85 Web : cea.assur.org
DELEGATION A BRUXELLES
Square de Mees, 29 B 1000 Bruxelles Tl. : +32 2 547 58 11 Fax : +32 2 547 58 19
Web : cea.assur.org
PROPERTY INSURANCE COMMITTEE Prevention Specifications
Planning and Installation for Automatic Fire Detection and Fire Alarm Systems
CEA 4040: July 2003 (en)
Copyright by CEA 3 bis, rue de la Chausse dAntin 75009 PARIS
2
Contents
FOREWORD..................................................................................................................................................................5
0 - INTRODUCTION.....................................................................................................................................................5
1 - SCOPE .......................................................................................................................................................................5
2 - REFERENCES AND DEFINITIONS .....................................................................................................................6
3 - GENERAL...............................................................................................................................................................11 3.1 USAGE OF THE GUIDELINES ...................................................................................................................................11 3.2 FORMAT OF THE GUIDELINES.................................................................................................................................12 3.3 NATIONAL INSURANCE DOCUMENTS .....................................................................................................................14 3.4 OTHER SYSTEMS....................................................................................................................................................14 3.5 SAFETY REQUIREMENTS ........................................................................................................................................14 3.6 FALSE ALARMS......................................................................................................................................................14 3.7 NEW DEVELOPMENTS ............................................................................................................................................14 3.8 WARRANTIES AND GUARANTEES...........................................................................................................................14 3.9 DOCUMENTATION .................................................................................................................................................15 3.10 RESPONSIBILITY..................................................................................................................................................15 3.11 QUALIFICATIONS.................................................................................................................................................15
4 - ASSESSMENT OF NEEDS....................................................................................................................................16 4.1 PURPOSE ...............................................................................................................................................................16 4.2 CONSULTATION.....................................................................................................................................................16 4.3 PARTS OF THE BUILDING NEEDING COVER .............................................................................................................16 4.4 FIRE BRIGADE ATTENDANCE..................................................................................................................................18 4.5 FIRE ALARM RESPONSE STRATEGY ........................................................................................................................18 4.6 DOCUMENTATION .................................................................................................................................................20 4.7 RESPONSIBILITY....................................................................................................................................................20 4.8 QUALIFICATIONS...................................................................................................................................................20
5 PLANNING AND DESIGN...................................................................................................................................21 5.1 DEVICES CONNECTED TO THE SYSTEM...................................................................................................................22 5.2 SYSTEM DESIGN ....................................................................................................................................................22 5.3 ZONES ...................................................................................................................................................................26 5.4 SELECTION OF DETECTORS AND MANUAL CALL POINTS .........................................................................................29 5.5 SITING AND SPACING OF AUTOMATIC DETECTORS AND MANUAL CALL POINTS ......................................................32 5.6 ALARM SYSTEMS AND DEVICES .............................................................................................................................58 5.7 CONTROL AND INDICATION ...................................................................................................................................60 5.8 POWER SUPPLIES ..................................................................................................................................................61 5.9 SIGNALS TO A FIRE ALARM RECEIVING STATION....................................................................................................63 5.10 DOCUMENTATION ...............................................................................................................................................63 5.11 RESPONSIBILITY..................................................................................................................................................63 5.12 QUALIFICATIONS.................................................................................................................................................64
6 - INSTALLATION ....................................................................................................................................................64 6.1 GENERAL ..............................................................................................................................................................64 6.2 SITING AND ACCOMMODATION OF EQUIPMENT......................................................................................................64
3
6.3 INSTALLATION OF CABLES AND INTERCONNECTIONS............................................................................................65 6.4 CABLE JOINTS AND TERMINATIONS .......................................................................................................................67 6.5 RADIOACTIVITY ....................................................................................................................................................67 6.6 DOCUMENTATION .................................................................................................................................................67 6.7 RESPONSIBILITY....................................................................................................................................................67 6.8 QUALIFICATIONS (REFER TO 3.11) .....................................................................................................................67
7 - COMMISSIONING AND VERIFICATION........................................................................................................68 7.1 GENERAL ..............................................................................................................................................................68 7.2 COMMISSIONING ...................................................................................................................................................68 7.3 VERIFICATION .......................................................................................................................................................69 7.4 DOCUMENTATION .................................................................................................................................................70 7.5 RESPONSIBILITY....................................................................................................................................................70 7.6 QUALIFICATIONS...................................................................................................................................................70
8 - THIRD PARTY APPROVAL................................................................................................................................70 8.1 GENERAL ..............................................................................................................................................................70 8.2 PROCEDURES...................................................................................................................................