CB techniques.pptx
-
Upload
rahul-more -
Category
Documents
-
view
228 -
download
0
Transcript of CB techniques.pptx
-
8/10/2019 CB techniques.pptx
1/55
1
Capital Budgeting TechniquesThis is only a summary. Please read the text for details. Removalof errors and omissions, if any, in this ppt is your responsibility.
-
8/10/2019 CB techniques.pptx
2/55
2
Agenda
NPV Rule & and Stand-Alone Projects
IRR
MIRR
Payback Rule
Book rate of Return
Profitability Index
Numerical
-
8/10/2019 CB techniques.pptx
3/55
3
Techniques Used
Profitability
Index, 12%
Payback, 57%
IRR, 76%
NPV, 75%
Book rate of
return, 20%
0% 20% 40% 60% 80% 100%
Survey Data on CFO Use of Investment Evaluation Techniques
Source - Graham and Harvey, The Theory and Practice of Finance: Evidence from the
Field, Journal of Financial Economics 61 (2001), pp. 187-243.
-
8/10/2019 CB techniques.pptx
4/55
4
Techniques Used
Two approaches:Discounting: takes time value of money into consideration
Non-discounting: simple and still of value
-
8/10/2019 CB techniques.pptx
5/55
5
NPV Rule
Why use NPV rule to evaluate projects
Accepting positive NPV projects increases valueof the firm
NPV uses cash flows (CF)
NPV uses not just CF but allthe CFs of theproject
NPV discounts the cash flows appropriately(opportunity cost of capital)
-
8/10/2019 CB techniques.pptx
6/55
6
NPV Rule
Net Present Value (NPV) =
Total PV of future CFs + Initial Investment
Estimating NPV
Estimate future cash flows - how much? and when?
Estimate rate
Estimate initial costs
Minimum Acceptance Criteria: Accept if NPV > 0
Ranking Criteria: Choose the highest NPV
-
8/10/2019 CB techniques.pptx
7/55
7
NPV Rule
Consider the following two options:
1. Invest the $100 in a riskless project and pay out $107,1 year from now as dividends
2. Pay out the $100 today
The opportunity cost is 6%
Consider the options from the firms angle and theshareholders anglerefer to your text for greaterdetails
-
8/10/2019 CB techniques.pptx
8/55
8
NPV Rule & Stand-Alone Projects
Consider a take-it-or-leave-it investment decision
involving a single, stand-alone project for FFF Co
The project costs $250 million and is expected to
generate cash flows of $35 million per year, starting at
the end of the first year and lasting forever
What is the NPV of the project?
-
8/10/2019 CB techniques.pptx
9/55
9
NPV Rule & Stand-Alone Projects -
Sensitivity
At 10% cost of capital (opportunity cost, discountrate) the NPV is 100 million
At 14%, the NPV is equal to 0, thus the projectsIRR is 14%
For FFF, if their cost of capital is more than 14%,the NPV would be negative
-
8/10/2019 CB techniques.pptx
10/55
10
NPV Rule & Stand-Alone Projects
In general, the difference between the actual cost ofcapital (r) and the IRR is the maximum amount ofestimation error in the cost of capital estimate that can
exist without altering the original decision
(150.00)
(100.00)
(50.00)
-
50.00
100.00
150.00
200.00
250.00
300.00
350.00
400.00
6% 8.50% 11.00% 13.50% 16.00% 18.50% 21.00% 23.50%
14%
-
8/10/2019 CB techniques.pptx
11/55
11
NPV Rule
Why is NPV widely used
Uses cash flows (not accounting numbers)
Uses ALL cash flows of the project
Discounts ALL cash flows appropriately
Reinvestment assumption: the NPV rule assumes
that all cash flows can be reinvested at thediscount rate
-
8/10/2019 CB techniques.pptx
12/55
12
NPV Rule
Sometimes alternative investment rules may givethe same answer as the NPV rule, but at othertimes they may disagree.
When the rules conflict, the NPV decision rule shouldgenerally be followed.
-
8/10/2019 CB techniques.pptx
13/55
13
NPV Rule
Consider the following example
XYZ company has the following cash flows for aproject
Plot the NPV profile
What is the IRR
If the cost of capital is 12%, would you accept it
Year CF
0 (5,550,000)
1 5,000,0002 4,000,000
3 (3,000,000)
-
8/10/2019 CB techniques.pptx
14/55
14
Internal Rate of Return (IRR)
IRR is the discount that sets NPV to zero or It is the discount rate that will equate the present
value of the outflows with the present value of theinflows
The IRR is the projects intrinsic rate of return Minimum Acceptance Criteria
Accept if the IRR exceeds the required return
Ranking Criteria Select alternative with the highest IRR
Reinvestment assumption All future cash flows assumed reinvested at the IRR
-
8/10/2019 CB techniques.pptx
15/55
15
Internal Rate of Return (IRR)
Disadvantages
Does not distinguish between investing and borrowing
IRR may not exist
There may be multiple IRR Mutually exclusive projects (scale and timing of CF)
Advantages
Easy to understand and communicate
-
8/10/2019 CB techniques.pptx
16/55
16
Internal Rate of Return (IRR)
Situations where the IRR rule and NPV rule may bein conflict
Delayed Investments (Are we borrowing or lending)
Nonexistent IRR
Multiple IRRs Mutually exclusive projects (timing and scale)
Implicit in the IRR calculation is that that discountrates are stable during the term of the project -This implies that all funds are reinvested at theIRR (which may not be the case)
-
8/10/2019 CB techniques.pptx
17/55
17
Internal Rate of Return (IRR)
Consider the following example
You can purchase a turbo powered machine toolgadget for $6,500. The investment will generate$3,500 and $5,500 in cash flows for two years,respectively. What is the IRR on this investment?
-
8/10/2019 CB techniques.pptx
18/55
18
Internal Rate of Return (IRR)
Delayed Investments Assume you have just retired as the CEO of a
successful company - A major publisher has offeredyou a book deal
The publisher will pay you $1.0 million upfront if youagree to write a book about your experiences
You estimate that it will take three years to write thebook
Assume that the time you spend writing will cause you
to give up speaking engagements amounting to$500,000 per year
You estimate your opportunity cost to be 10% Should you accept the deal?
-
8/10/2019 CB techniques.pptx
19/55
19
Internal Rate of Return (IRR)
Nonexistent IRR
Assume now that you are offered $500,000 per year ifyou agree to go on a speaking tour for the next threeyears
If you lecture, you will not be able to write the book(however, as of now there is no book deal)
Compute the IRR and NPV
-
8/10/2019 CB techniques.pptx
20/55
20
Internal Rate of Return (IRR)
Multiple IRRs Now assume the lecture deal is still in
discussion with a tentative offer and you decideto negotiate with the book publisher
You inform the publisher that they need toincrease the offer before you will accept it
The publisher then agrees to make royaltypayments of $20,000 per year forever, starting a
year after the book is published in three years Should you accept or reject the new offer?
-
8/10/2019 CB techniques.pptx
21/55
21
Internal Rate of Return (IRR)
When do you have multiple IRRs?
Generally when the cash flows change directionyou have multiple IRRs
-
8/10/2019 CB techniques.pptx
22/55
22
Internal Rate of Return (IRR)
Mutually exclusive projects
IRR sometimes ignores the magnitude and timingof the projects cash flows
The following two projects illustrate that problem
0 1 2 3
$10,000 $1,000 $1,000
-$10,000
Project A
0 1 2 3
$1,000 $1,000 $12,000
-$10,000
Project B
Assume costof capital is
8%
-
8/10/2019 CB techniques.pptx
23/55
23
Internal Rate of Return (IRR)
In such a case the crossover rate is important and thediscount rate to be usedStepsCompute IRR (A)Compute IRR (B)
NPV (A)NPV (B)Compute the incremental CFensure the first one isnegative to the extent possible
Compute the crossover rate/IRR of the incremental CFCompute the NPV of the incremental project CF at the costof capitalChoose A or B
-
8/10/2019 CB techniques.pptx
24/55
24
Internal Rate of Return (IRR)
Shortcomings of the Incremental IRR RuleThe incremental IRR may not exist
Multiple incremental IRRs could exist
You must ensure that the incremental cash flows are initiallynegative and then become positive
The incremental IRR rule assumes that the riskiness of the
two projects is the same
-
8/10/2019 CB techniques.pptx
25/55
25
Internal Rate of Return (IRR)
Scale (example 5.2 pg 174-175)
Two options to a project: small budget or longbudget
CF (0) CF (1) NPV at 25% IRR
Small Budget -10m 40m 22m 300%
Large Budget -25m 65m 27m 160%
You want to go by the NPV rule and choose the large
budget project but your manager says convince mewhy is the IRR rule may not be appropriate given thatthat small budget project has a higher IRR. What doyou do, given that the discount rate is 25%?
-
8/10/2019 CB techniques.pptx
26/55
26
Internal Rate of Return (IRR)
Scale
If a projects size is doubled, its NPV will double
This is not the case with IRR In such cases, the IRR rule cannot be used to
compare projects of different scales
-
8/10/2019 CB techniques.pptx
27/55
27
Internal Rate of Return (IRR)
Friends
BusinessYour
LaundromatInitial Investment $1,000 $1,000
Cash FlowYear 1 $1,100 $400
Annual Growth Rate -10% -20%Cost of Capital 12% 12%
Consider the following example
-
8/10/2019 CB techniques.pptx
28/55
28
Internal Rate of Return (IRR)
What if the laundromatproject is 20 times largerassumeyou can scale it up easily but not the friends business
The NPV would be 20 times larger but the IRR
remains the same at 20%
Now what would be your decision?
-
8/10/2019 CB techniques.pptx
29/55
29
IRR using interpolation
Consider the following cash flows. The hurdle rateis 25%. Compute the IRR and based on the IRRwhat is your decision?
0 -27001 1100
2 1600
3 8504 1100
5 900
-
8/10/2019 CB techniques.pptx
30/55
30
Internal Rate of Return (IRR)
Percentage Return Versus Impact on Value
Would you prefer a 200% return on $2 or a 10%return on $2 million?
The former investment makes only $4, while thelatter opportunity makes $200,000
The IRR is a measure of the average return, butNPV is a measure of the total dollar impact on value
-
8/10/2019 CB techniques.pptx
31/55
31
Modified Internal Rate of Return (MIRR)
Let PV = PV of the cash outflows(discounted appropriately)
Let TV = FV of all cash inflows(compounded appropriately)The compounding and discounting is at the cost ofcapital
Then MIRR is obtained by solving the followingequation
PV = TV/(1+MIRR)N
Advantagecash flows are reinvested at the cost ofcapitalThe issue with multiple rates would not exist
-
8/10/2019 CB techniques.pptx
32/55
32
Modified Internal Rate of Return (MIRR)
Consider the following example
ABC Ltd. is evaluating a project that has an initial
investment of 1200 and the following cash flow
stream
The cost of capital (opportunity cost) is 12.0% -
Should ABC Ltd. accept the project using the MIRR
rule
1 2 3 4 5
200 100 -300 500 700
-
8/10/2019 CB techniques.pptx
33/55
33
Modified Internal Rate of Return (MIRR)
Consider the XYZ Co. example from before
Compute the MIRR
Does the decision change?
-
8/10/2019 CB techniques.pptx
34/55
34
Payback Rule
How long does it take the project to pay back itsinitial investment
Payback Period = number of years to recover
initial costs Minimum Acceptance Criteria:
set by management
Ranking Criteria:
set by management
-
8/10/2019 CB techniques.pptx
35/55
35
Payback Rule
Disadvantages Ignores the time value of money
Ignores cash flows after the payback period
Biased against long-term projects
Requires an arbitrary acceptance criteriaA project accepted based on the payback
criteria may not have a positive NPV
Advantages Easy to understand
Biased toward liquidity
-
8/10/2019 CB techniques.pptx
36/55
36
Payback Rule
Consider the following example
Suppose that FFF company requires all projects tohave a payback period of 5 years or lesswouldthey undertake the project we discussed?
-
8/10/2019 CB techniques.pptx
37/55
37
Payback Rule
Consider the following problem Projects A, B, and C each have an expected
life of 5 years
Given the initial cost and annual cash flowinformation below, what is the payback periodfor each project?
A B CCost $75 $110 $150
Cash Flow $20 $25 $30
-
8/10/2019 CB techniques.pptx
38/55
38
Payback Rule
Consider the following example
Infoline Online has the following cash flows for a periodof four years. What is the payback period
Year CF
0 (5,450,000)
1 1,508,000
2 1,773,1003 1,897,910
4 2,753,941
-
8/10/2019 CB techniques.pptx
39/55
39
Payback Rule
To incorporate the Time value of money there is amodification of the payback rule calledthediscounted payback rule.
How long does it take the project to pay back its
initial investment taking the time value of moneyinto account
By the time you have discounted the cash flows, you might as wellcalculate the NPV!
-
8/10/2019 CB techniques.pptx
40/55
40
Payback Rule
Use the Infoline example from before andassuming a discount rate of 12% compute thediscounted payback
-
8/10/2019 CB techniques.pptx
41/55
41
Profitability Index
If PI > 0 accept,
-
8/10/2019 CB techniques.pptx
42/55
42
Profitability Index
NET BCR (PI) =(PVB-I)/I=BCR-1
Decision Rules:
BCR NBCR(PI) Rule
>1 >0 Accept
=1 =0 Indifferent
-
8/10/2019 CB techniques.pptx
43/55
43
Profitability Index
When resources are limited, the profitability index(PI) provides a tool for selecting among variousproject combinations and alternatives
A set of limited resources and projects can yieldvarious combinations
The highest weighted average PI can indicate whichprojects to select
-
8/10/2019 CB techniques.pptx
44/55
44
Profitability Index
-
8/10/2019 CB techniques.pptx
45/55
45
Profitability Index
In some situations the profitability Index does not give anaccurate answer
Suppose in Example 6.4 that NetIt has an additional small
project with a NPV of only $100,000 that requires 3 engineerswhat happens
-
8/10/2019 CB techniques.pptx
46/55
46
Profitability Index
Consider the following example
You only have RS.300,000 to invest, Which do weselect?
Proj NPV Invest PIA 276 200 1.38
B 151.25 125 1.21
C 213.5 175 1.22
D 211.5 150 1.41
-
8/10/2019 CB techniques.pptx
47/55
47
Profitability Index
Compute Weighted average PI, and choose the highest WAPI
Optionsonly A, BC, BD
-
8/10/2019 CB techniques.pptx
48/55
48
Book Rate of Return
Also known as Average Accounting Return Rule
Average net income (project earning) divided by averagebook value over project life (or average book value of theinvestment)
Another simple non-cash flow approach Ranking Criteria and Minimum Acceptance Criteria set by
management Disadvantages
Ignores the time value of money Uses an arbitrary benchmark cutoff rate Based on book values, not cash flowsand market
values Advantages
The accounting information is usually available Easy to calculate
-
8/10/2019 CB techniques.pptx
49/55
49
Book Rate of Return
Consider the following example
A manufacturer is considering building a new production plant
in a new town. It will require an initial capital investment of
$12 million and the plant will be depreciated on a straight-
line basis over the next four years of its use. The new
project will generate incremental net income of $1,100,000,
$1,350,000, $1,200,000 and $2,100,000 over each of the
next four years for the company. What is the average
accounting return (AAR)for this project?
-
8/10/2019 CB techniques.pptx
50/55
50
Numerical 1
The firm for which you work must choose between the
following two mutually exclusive projects - The appropriatediscount rate for the projects is 10 percent
The firm chooses to undertake A. At a luncheon for theshareholders, the managers of a pension fund that owns asubstantial amount of the firms stock asked you why the firm
chose project A instead of project B when B is more profitable.How would you justify your firms action? Are there any
circumstances under which the pension fund managers
argument could be correct?
C0 C1 C2 PI NPV
Project A -1000 1000 500 0.32 322.31
Project B -500 500 400 0.57 285.12
-
8/10/2019 CB techniques.pptx
51/55
51
Numerical 2
Orchid Biotech Company is evaluating several development projects for
experimental drugs. Although the cash flows are difficult to forecast, thecompany has come up with the estimates of the initial capital requirementsand NPVs for the projects as shown below. Given a wide variety of staffingneeds, the company has also estimated the number of research scientistsrequirements for each development project (all cost values are given in
millions of dollar)
Project
Initial
Capital
#
Scientists NPV
I 10.00 2 10.10
II 15.00 3 19.00
III 15.00 4 22.00
!V 20.00 3 25.00
V 30.00 10 60.20
Suppose that orchid has a totalcapital budget of $60 million.How should it prioritize theseprojects?
Suppose that orchid currentlyhas 12 research scientists anddoes not anticipate to be ableto hire any more in the future.How should Orchid prioritizethese projects?
-
8/10/2019 CB techniques.pptx
52/55
52
Consider the following 2 mutually exclusive projects
Numerical 3
A B0 (300,000) (40,000)
1 20,000 19,000
2 50,000 12,000
3 50,000 18,000
4 390,000 10,500
Assuming that your opportunity cost is 15%, which projects would you choosea. Using the payback criterion? Why?b. Discounted payback criterion? Why?c. NPV criterion? Why?
d. Using the IRR criterion? Why?e. Using the Profitability criterion? Why?f. Based on your answers in (a)(e) above, which project will you finally
choose? Why?
-
8/10/2019 CB techniques.pptx
53/55
53
Numerical 5
Your firm is considering two mutually exclusiveprojects A and B. Project A involves an initial outlayof Rs.100m and will generate an expected cashinflow of Rs.25 m per year for 6 years. Project B
involves an initial outlay of Rs.50 m and willgenerate an expected cash inflow of Rs.13 m peryear for 6 years. Both projects have a similar riskand the firms cost of capital is 12%
a) Calculate the NPV and IRR of each projectb) Calculate the NPV and IRR of the incremental
(differential) project
-
8/10/2019 CB techniques.pptx
54/55
54
Summary
Discounted CF techniques NPV IRR MIRR
PIPayback Criteria Payback Discounted Payback
Accounting Criterion
AAR/Book Rate of Return
-
8/10/2019 CB techniques.pptx
55/55
Thank You!