Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

download Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

of 115

Transcript of Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    1/115

    BSC6900 UMTS

    V900R017C10

    Installation Guide

    Issue 01

    Date 2015-03-25

    HUAWEI TECHNOLOGIES CO., LTD.

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    2/115

     

    Copyright © Huawei Technologies Co., Ltd. 2015. All rights reserved.

    No part of this document may be reproduced or transmitted in any form or by any means without prior written

    consent of Huawei Technologies Co., Ltd.

     

    Trademarks and Permissions

     and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.

     All other trademarks and trade names mentioned in this document are the property of their respective holders.

     

    Notice

    The purchased products, services and features are stipulated by the contract made between Huawei and the

    customer. All or part of the products, services and features described in this document may not be within the

    purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information,

    and recommendations in this document are provided "AS IS" without warranties, guarantees or representations

    of any kind, either express or implied.

    The information in this document is subject to change without notice. Every effort has been made in the

    preparation of this document to ensure accuracy of the contents, but all statements, information, and

    recommendations in this document do not constitute a warranty of any kind, express or implied.

     

    Huawei Technologies Co., Ltd.

     Address: Huawei Industrial Base

    Bantian, Longgang

    Shenzhen 518129

    People's Republic of China

    Website: http://www.huawei.com

    Email: [email protected]

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    i

    http://www.huawei.com/

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    3/115

    About This Document

    Overview

    This document describes how to install the BSC6900. The components to be installed include

    external power cables, PGND cables, boards, signal cables, cabinet fittings, the computer serving

    as the local maintenance terminal (LMT), and the alarm box. This document also describes how

    to check the installed hardware, constructing connectors for power cables and signal cables, and

    making and attaching engineering labels. Finally, this document provides requirements for the

    operational environment of the equipment.

    Product Version

    The following table lists the product versions related to this document.

    Product Name Product Version Solution Version

    BSC6900 V900R017C10 RAN17.1

     

    Intended Audience

    This document is intended for installation personnel.

    Organization

    1 Change Description

    This section provides information about the changes in different document versions. There are

    two types of changes, including function changes and editorial changes. Function changes refer 

    to changes in functions of a specific product version. Editorial changes refer to changes in

    wording or addition of information that was not described in the earlier version.

    2 Tools Required for Installation

    BSC6900 UMTS

    Installation Guide About This Document

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    ii

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    4/115

    The tools required for installing the BSC are tools for measuring, marking, drilling, and

    fastening, small tools, auxiliary tools, instruments, and special tools.

    3 Installation Process

    The BSC6900 installation process includes the installation of the cabinet and its fittings, power cables and PGND cables, OMUc boards , signal cables, LMT computers, and alarm boxes.

    4 Installing Power Cables and PGND Cables

    This section describes how to install power cables and PGND cables between a cabinet and the

     power distribution frame (PDF) ,and PGND cables between cabinets. For items and

    specifications for checking the installation of the power cables and PGND cables, see 11.1

    Checklist for BSC6900 Cable Installation.

    5 Checking and Setting DIP Switches on Subracks

    This section describes how to check and set the DIP switch on a subrack. In general, subracks

    are installed in the cabinet before delivery.

    6 Checking the Power-On Performance of Cabinet

    This section describes how to check the power supply to cabinets, fan assembly, and boards.

    7 Installing and Setting Boards

    Most boards except the OMUa/OMUc/SAUa/SAUc boards are installed in subracks before the

    delivery. If AEUa/AOUa/PEUa/PEUc/POUa/PAMU/PFCU boards are installed in the cabinet,

    check and set the DIP switches of the boards. Install the OMUa/OMUc/SAUa/SAUc boards

    onsite.

    8 Installing the Signal Cables

    This chapter describes how to install the signal cables according to the layout requirements. The

    signal cables to be installed include clock signal cables, Ethernet cables, E1/T1 cables and optical

    cables. For items and specifications for checking the installation of signal cables, see 11.1

    Checklist for BSC6900 Cable Installation.

    9 Installing the Alarm Box and the Computer Serving as the LMT

    This section describes how to install an alarm box and a computer serving as the LMT. If you

    are installing the computer and the alarm box in the equipment room, you can install them along

    with the BSC6900 equipment. For items and specifications for checking the installation of the

    LMT computer and the alarm box, see 11.3 Checklist for the Installation of the LMT

    Computer and Alarm Box.

    10 Attaching the Engineering Labels to the Cables

    This chapter describes how to attach engineering labels to the power, PGND, and signal cables

    after the cables are installed

    11 Checklist for the Hardware Installation

    This chapter describes how to check the hardware installation. The hardware consists of cables,

    Local Maintenance Terminal (LMT) PC, and alarm box. In addition, you should check the

    installation environment.

    12 Installation Records

    The table is used to record the BSC6900 hardware installation information.

    BSC6900 UMTS

    Installation Guide About This Document

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    iii

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    5/115

    Conventions

    Symbol Conventions

    The symbols that may be found in this document are defined as follows.

    Symbol Description

    Indicates an imminently hazardous situation which, if not

    avoided, will result in death or serious injury.

    Indicates a potentially hazardous situation which, if not

    avoided, could result in death or serious injury.

    Indicates a potentially hazardous situation which, if not

    avoided, may result in minor or moderate injury.

    Indicates a potentially hazardous situation which, if not

    avoided, could result in equipment damage, data loss,

     performance deterioration, or unanticipated results.

     NOTICE is used to address practices not related to personal

    injury.

    Calls attention to important information, best practices and

    tips.

     NOTE is used to address information not related to personal

    injury, equipment damage, and environment deterioration.

     

    General Conventions

    The general conventions that may be found in this document are defined as follows.

    Convention Description

    Times New Roman Normal paragraphs are in Times New Roman.

    Boldface  Names of files, directories, folders, and users are inboldface. For example, log in as user root.

     Italic Book titles are in italics.

    Courier New Examples of information displayed on the screen are in

    Courier New.

     

    Command Conventions

    The command conventions that may be found in this document are defined as follows.

    BSC6900 UMTS

    Installation Guide About This Document

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    iv

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    6/115

    Convention Description

    Boldface The keywords of a command line are in boldface.

     Italic Command arguments are in italics.

    [ ] Items (keywords or arguments) in brackets [ ] are optional.

    { x | y | ... } Optional items are grouped in braces and separated by

    vertical bars. One item is selected.

    [ x | y | ... ] Optional items are grouped in brackets and separated by

    vertical bars. One item is selected or no item is selected.

    { x | y | ... }* Optional items are grouped in braces and separated by

    vertical bars. A minimum of one item or a maximum of all

    items can be selected.

    [ x | y | ... ]* Optional items are grouped in brackets and separated by

    vertical bars. Several items or no item can be selected.

     

    GUI Conventions

    The GUI conventions that may be found in this document are defined as follows.

    Convention Description

    Boldface Buttons, menus, parameters, tabs, window, and dialog titles

    are in boldface. For example, click OK .

    > Multi-level menus are in boldface and separated by the ">"

    signs. For example, choose File > Create > Folder.

     

    Keyboard Operations

    The keyboard operations that may be found in this document are defined as follows.

    Format Description

    Key Press the key. For example, press Enter and press Tab.

    Key 1+Key 2 Press the keys concurrently. For example, pressing Ctrl+Alt

    +A means the three keys should be pressed concurrently.

    Key 1, Key 2 Press the keys in turn. For example, pressing Alt, A means

    the two keys should be pressed in turn.

     

    Mouse Operations

    The mouse operations that may be found in this document are defined as follows.

    BSC6900 UMTS

    Installation Guide About This Document

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    v

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    7/115

    Action Description

    Click Select and release the primary mouse button without moving

    the pointer.

    Double-click Press the primary mouse button twice continuously and

    quickly without moving the pointer.

    Drag Press and hold the primary mouse button and move the

     pointer to a certain position.

    BSC6900 UMTS

    Installation Guide About This Document

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    vi

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    8/115

    Contents

    About This Document.....................................................................................................................ii

    1 Change Description.......................................................................................................................1

    2 Tools Required for Installation..................................................................................................2

    3 Installation Process.......................................................................................................................4

    4 Installing Power Cables and PGND Cables.............................................................................6

    4.1 Power Ca bles and PGND Cables to Be Installed...........................................................................................................7

    4.2 Connections of Power Cables and PGND Cables..........................................................................................................8

    4.3 Principles for Installing Power Cables and PGND Cables.............................................................................................8

    4.4 Installing Power Cables and PGND Cables Between a BSC6900 Cabinet and the PDF...............................................9

    4.4.1 Installing Power Cables and PGND cable Between the BSC6900 and the PDF in Overhead Cabling Mode............9

    4.4.2 Installing Power Cables and PGND Cable Between the BSC6900 and the PDF in Underfloor Cabling Mode.......12

    4.5 Installing the PGND Cables Between Adjacent Cabinets............................................................................................17

    5 Checking and Setting DIP Switches on Subracks................................................................19

    6 Checking the Power-On Performance of Cabinet.................................................................22

    7 Installing and Setting Boards....................................................................................................24

    7.1 Safety Precautions for Board Installation.....................................................................................................................25

    7.2 Installing the OMUa/OMUc/SAUa/SAUc Boards.......................................................................................................25

    7.3 Checking and Setting the DIP Switch on the Board.....................................................................................................27

    7.4 DIP Switches on the BSC6900 Boards.........................................................................................................................29

    8 Installing the Signal Cables......................................................................................................30

    8.1 Signal Ca bles to Be Installed........................................................................................................................................32

    8.2 Principles of Installing Signal Cables...........................................................................................................................34

    8.3 Installing the Clock Signal Cables................................................................................................................................36

    8.3.1 Installing the Y-Shaped Clock Cables.......................................................................................................................36

    8.3.2 Installing Line Clock Signal Cables..........................................................................................................................39

    8.3.3 Installing the BITS Clock Signal Cables...................................................................................................................41

    8.4 Installing the Ethernet Cables.......................................................................................................................................44

    8.4.1 Arranging the Ethernet Cables..................................................................................................................................44

    8.4.2 Installing the Inter-SCUa Cables Between Different Subracks.................................................................................45

    BSC6900 UMTS

    Installation Guide Contents

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    vii

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    9/115

    8.4.3 Installing Ethernet Cables Between the OMUa and the LAN...................................................................................48

    8.4.4 Installing the Ethernet Cables Between the OMUc Board and the LAN..................................................................51

    8.4.5 Installing the Ethernet Cables Between the SAUa Board and the LAN....................................................................53

    8.4.6 Installing the Ethernet Cables Between the SAUc Board and the LAN....................................................................54

    8.4.7 Installing the Ethernet Cables Between the FG2a/FG2c Board and the Other Equipment.......................................56

    8.5 Installing the E1/T1 Cables..........................................................................................................................................58

    8.5.1 Arranging the E1/T1 Cables Between the AEUa/PEUa/PEUc Board and the DDF.................................................59

    8.5.2 Installing the E1/T1 Cables Between the AEUa/PEUa/PEUc Board and the DDF in Overhead Cabling Mode......60

    8.5.3 Installing the E1/T1 Cables Between the AEUa/PEUa/PEUc Board and the DDF in Underfloor Cabling Mode

    ............................................................................................................................................................................................68

    8.6 Installing the Optical Cables.........................................................................................................................................75

    8.6.1 Using the Accessories of the Optical Cable..............................................................................................................75

    8.6.2 Arranging the Optical Cables....................................................................................................................................78

    8.6.3 Installing the Optical Splitter/Combiner....................................................................................................................79

    8.6.4 Installing an Optical Cable Between the SCU Boards in Different Subracks with a Long Distance........................82

    8.6.5 Installing the Optical Cables Between the AOUa/AOUc/GOUa/GOUc/GOUe/POUa/POUc/UOIa/UOIc Boards and

    the Other Equipment...........................................................................................................................................................87

    8.7 Installing the EMU RS485 Communication Cables.....................................................................................................90

    8.8 Connecting the GPS Surge Protector to the GCGa/GCGb Board................................................................................92

    9 Installing the Alarm Box and the Computer Serving as the LMT.....................................97

    9.1 Installing the Computer Serving as the LMT...............................................................................................................98

    9.2 Installing the Alarm Box..............................................................................................................................................98

    10 Attaching the Engineering Labels to the Cables...............................................................100

    10.1 Attaching the Engineering Labels to the Power Cables and PGND Cables.............................................................101

    10.2 Attaching the Engineering Labels to the Signal Cables...........................................................................................101

    11 Checklist for the Hardware Installation.............................................................................104

    11.1 Checklist for BSC6900 Cable Installation................................................................................................................105

    11.2 Checklist for the Installation of the BSC6900 GPS Antenna System......................................................................105

    11.3 Checklist for the Installation of the LMT Computer and Alarm Box......................................................................105

    11.4 Checklist for Field Cleanliness of BSC6900 Installation.........................................................................................105

    12 Installation Records................................................................................................................106

    BSC6900 UMTS

    Installation Guide Contents

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    viii

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    10/115

    1 Change DescriptionThis section provides information about the changes in different document versions. There are

    two types of changes, including function changes and editorial changes. Function changes refer 

    to changes in functions of a specific product version. Editorial changes refer to changes in

    wording or addition of information that was not described in the earlier version.

    01 (2015-03-25)

    This issue does not include any changes.

    Draft A (2015-01-15)

    Compared with Issue 01 (2014-04-29) of V900R016C00, this issue does not include any

    changes.

    BSC6900 UMTS

    Installation Guide 1 Change Description

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    1

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    11/115

    2 Tools Required for InstallationThe tools required for installing the BSC are tools for measuring, marking, drilling, and

    fastening, small tools, auxiliary tools, instruments, and special tools.

    NOTICE

    Electronic devices are prone to electrostatic discharge (ESD). Wear an ESD wrist strap correctly

    and touch only the edges of the boards, especially when dealing with components such as boards.

    Table 2-1 lists the tools required for installation.

    Table 2-1 Tools required for installation

    Common Tools Measuring tools Long measuring tape, ruler (1 m), right angle,

    industrial horizontal ruler, and plumb

    Marking tools Marking pen or ink fountain

    Drilling tools Percussion drill (Ф16 drill bit) and vacuum cleaner 

    Fastening tools M3-M6 straight screwdrivers

    M3-M6 Phillips screwdrivers

    Adjustable wrench

    Socket wrenches M6, M8, M12, M14, M17, and M19

    Double offset ring wrenches M6, M8, M12, M14,

    M17, and M19

    Long-arm wrench

    Small tools Sharp-nose pliers, diagonal pliers, pliers, hand-held

    electric drill, file, handsaw, crowbar, rubber mallet,

    and claw hammer 

    BSC6900 UMTS

    Installation Guide 2 Tools Required for Installation

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    2

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    12/115

    Auxiliary tools Tweezers, brush, bellows, paper knife, bellows,

    soldering iron, solder wires, ladder, pallet truck, panel

    lifter, heat gun, and electric outlet (with three 2-phase

    sockets and three 3-phase sockets, rated current higher 

    than 15 A)

    Meters Earth resistance tester, Ethernet cable tester, multimeter, 500 V

    megohmmeter, optical multimeter, and optical power meter 

    Special tools ESD wrist strap, glove, wire stripper, clamp pincer, feeder cutter, SMB

    crimping tool, RJ-45 crimping tool, and cable cutter 

    BSC6900 UMTS

    Installation Guide 2 Tools Required for Installation

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    3

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    13/115

    3 Installation ProcessThe BSC6900 installation process includes the installation of the cabinet and its fittings, power 

    cables and PGND cables, OMUc boards , signal cables, LMT computers, and alarm boxes.

    Prerequisites

    l The equipment has been unpacked and accepted.

    l The tools required for the installation are available.

    Procedure

    Step 1 Install the cabinet and its fittings. For details, see the N68E-22 Cabinet Installation Guide.

    Step 2 Install the power cables and PGND cables.

    If... Then...

    The type of the cabinet is N68E-22 See 4 Installing Power Cables and PGND

    Cables.

    The type of the cabinet is N68E-21-N See the description of installing power cables and

    PGND cables for the N68E-21-N cabinet in the

     N68E-21-N Cabinet Installation Guide.

    Step 3 Check and Set the Subrack DIP Switch. For details, see 5 Checking and Setting DIP Switcheson Subracks.

    Step 4 Check the Power-On Performance. For details, see 6 Checking the Power-On Performanceof Cabinet.

    Step 5 Install the OMU board. For details, see Installing the OMUc Boards.

    Step 6 Optional: Install the SAU board. For details, see Installing the SAUc Boards.

    Step 7 Install signal cables. For details, see 8 Installing the Signal Cables.

    BSC6900 UMTS

    Installation Guide 3 Installation Process

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    4

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    14/115

    NOTE

    The same method is used to install signal cables in both the N68E-22 and N68E-21-N cabinets. This

    document uses the N68E-22 cabinet as an example.

    Step 8 Optional: Install the GPS antenna system. For details, see the GPS Satellite Antenna SystemQuick Installation Guide.

    Step 9 Install the computer serving as the LMT and the alarm box. For details, see 9 Installing theAlarm Box and the Computer Serving as the LMT.

    Step 10 Attach engineering labels to the cables. For details, see 10 Attaching the Engineering Labelsto the Cables.

    Step 11 Check the installed hardware. For details, see 11 Checklist for the Hardware Installation.

    ----End

    BSC6900 UMTS

    Installation Guide 3 Installation Process

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    5

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    15/115

    4 Installing Power Cables and PGND CablesAbout This Chapter

    This section describes how to install power cables and PGND cables between a cabinet and the

     power distribution frame (PDF) ,and PGND cables between cabinets. For items and

    specifications for checking the installation of the power cables and PGND cables, see 11.1

    Checklist for BSC6900 Cable Installation.

    4.1 Power Ca bles and PGND Cables to Be Installed

    Power cables and PGND cables to be installed include external -48 V power cables for 

    cabinets, external RTN power cables for cabinets, external PGND cables for cabinets, and inter-

    cabinet PGND cables.

    4.2 Connections of Power Cables and PGND Cables

    This section describes the connections of power cables and PGND cables between a BSC6900

    cabinet and the PDF and the connections of inter-cabinet PGND cables.

    4.3 Principles for Installing Power Cables and PGND Cables

    This section describes the principles for installing power cables and PGND cables. When you

    install power cables and PGND cables, follow the routing and binding principles.

    4.4 Installing Power Cables and PGND Cables Between a BSC6900 Cabinet and the PDF

    This section describes how to install power cables and PGND cables for BSC6900 cabinets in

     both overhead cabling and underfloor cabling modes.

    4.5 Installing the PGND Cables Between Adjacent Cabinets

    This section describes how to connect the upper, middle, and lower parts of the PGND busbar 

    of one cabinet to those of its adjacent cabinet through PGND cables. PGND cables need to be

    installed in adjacent cabinets only when they are installed in combined mode.

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    6

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    16/115

    4.1 Power Cables and PGND Cables to Be Installed

    Power cables and PGND cables to be installed include external -48 V power cables for 

    cabinets, external RTN power cables for cabinets, external PGND cables for cabinets, and inter-

    cabinet PGND cables.

    Table 4-1lists the external power cables and PGND cables to be installed for each cabinet.

    Table 4-1 Power cables and PGND cables to be installed

    Item Color Cross-Sectional Area

    (mm2)

    AllowedBending Radius(mm)

    ConnectorType/ Installation Position

    ConnectorType/ Installation Position

    Number

    External

    -48 V

     power 

    cable for 

    the cabinet

    Blue 25/35 30 OT

    terminal/-48

    V input on

    the cabinet

    OT

    terminal/-48

    V output on

    the PDF

    4

    External

    RTN

     power 

    cable for 

    the cabinet

    Black 25/35 30 OT terminal/

    RTN input

    on the

    cabinet

    OT terminal/

    RTN output

    on the PDF

    4

    External

    PGND

    cable

    Green

    and

    yellow

    25/35 30 OT terminal/

    PGND input

    on the

    cabinet

    OT terminal/

    PGND

    output on the

    PDF

    1

    Inter-

    cabinet

    PGND

    cable

    Green

    and

    yellow

    6 15 OT terminal/

    PGND

     busbar in the

    cabinet

    OT terminal/

    PGND

     busbar in the

    cabinet

    3

     

    NOTE

    The required length of power cables and PGND cables is specified in the site survey report. Cut an

    appropriate length of cables and crimp terminals onsite.

    l The colors of power cables and PGND cables must meet the customer requirements. Table 4-1 lists

    only their default colors.

    l Whether to use one-hole OT terminals or two-hole OT terminals for power cables and PGND cables

    is determined based on customer requirements. Table 4-1 lists the one-hole OT terminals.

    l For details about power cables, see Power Cables. For details about PGND cables, see PGND Cables.

    NOTE

    To facilitate the crimping of OT terminals, crimp them on the ground with hydraulic pliers, and then placethem in the installation positions.

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    7

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    17/115

    4.2 Connections of Power Cables and PGND Cables

    This section describes the connections of power cables and PGND cables between a BSC6900cabinet and the PDF and the connections of inter-cabinet PGND cables.

    Figure 4-1 shows the connections of cabinet power cables and PGND cables.

    Figure 4-1 Connections of power cables and PGND cables

     

    NOTE

    In each cabinet, A1 and B1 form a pair of active and standby power supply ports, as do A3 and B3. As

    shown in the preceding figure, to create a hot backup, connect ports A1 and A3 to one power supply group

    in the PDF, and ports B1 and B3 to a different power supply group.

    Connect the PGND cables for a cabinet to the nearest ground bar. If the PDF is located a great distance

    from the cabinet (for example, they are not in the same equipment room), connect the PGND cables to the

    nearest ground bar that is co-grounded with the PDF instead of connecting them directly to the PDF. In

    this case, the methods of installing and routing PGND cables are the same as those of connecting PGND

    cables directly to the PDF. In practice, PGND cables must be connected based on customer requirements.

    4.3 Principles for Installing Power Cables and PGND

    Cables

    This section describes the principles for installing power cables and PGND cables. When you

    install power cables and PGND cables, follow the routing and binding principles.

    Minimum Bending Radius of Power Cables

    Table 4-2 lists the requir ements for bending radius of power cables.

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    8

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    18/115

    Table 4-2 Bending radius of power cables

    Cross-Sectional Area (mm2) Radius

    25 50 mm or larger  

    35 55 mm or larger  

     

    Cable Layout Requirements

    l Lay out power cables and PGND cables with future capacity expansion in mind.

    l When laying out power cables and PGND cables, separate them from signal cables. Lay

    out power cables along outer columns. When you lay out power cables and PGND cables

     parallel to signal cables, the space between them must be at least 30 mm.

    lThe bending radius of a cable must be five times larger than the diameter of the cable.

    l When using the underfloor cabling mode, reserve a surplus length of power cable outside

    the cable inlet of the power distribution box on the top of the cabinet. This facilitates the

    installation of terminals. In addition, lay out cables flat on the top of the cabinet.

    l When connecting power cables to the terminals on the power distribution box, lay out the

    cables straightly and smoothly.

    Cable Binding Requirements

    l When binding power cables and PGND cables, separate them from signal cables.

    l Keep a 200 mm space between cable ties.

    l When using the underfloor cabling mode, route the power cables and PGND cables alongthe middle standing pillar on the front right side of the cabinet.

    l Select the appropriate cable ties, either 150 mm or 300 mm according to the diameter and

    number of cables.

    l Bind the cable ties in the same direction. Cut any excess from the cable ties, cutting surfaces

    smoothly without sharp edges.

    4.4 Installing Power Cables and PGND Cables Between aBSC6900 Cabinet and the PDF

    This section describes how to install power cables and PGND cables for BSC6900 cabinets in

     both overhead cabling and underfloor cabling modes.

    4.4.1 Installing Power Cables and PGND cable Between theBSC6900 and the PDF in Overhead Cabling Mode

    This section describes how to install power cables and PGND cable between a cabinet and the

    PDF in overhead cabling mode.

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    9

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    19/115

    Prerequisites

    l The cabinet to be connected with power cables and PGND cable has been installed.

    l On the PDF, the power distribution switches for the relevant output terminals have been

    set to OFF.l All power distribution switches on the power distribution box have been set to OFF.

    l Power cables and PGND cable are available.

    l The materials required for the installation are available. The materials include cable ties,

    wax strings, and PVC insulation tape.

    l The tools required for the installation are available. These tools include a handsaw, a cable

    cutter, a wrench, a Phillips screwdriver, a flat-head screwdriver, an electric Phillips

    screwdriver (> 5 N•m = 44.25 lbf•in.), diagonal pliers, and hydraulic pliers.

    Context

    If you are using the overhead cabling mode, route the cables from the PDF through the upper 

    cable hole into the cable tray and then to the top of each cabinet along the cable tray. Figure

    4-2 shows how to install power cables and PGND cable between a cabinet and the PDF in

    overhead cabling mode.

    Figure 4-2 Installing power cables and PGND cable in overhead cabling mode

     

    Procedure

    Step 1 Determine the length of each power cable and PGND cable by referring to the related engineeringdesign documents or by measuring the actual cabling route.

    Step 2 Uncoil the power cable roll and the PGND cable roll onsite. Measure an appropriate length of cables with a measuring tape or other measuring tools. Then, cut the cables with a cable cutter 

    (KT35) or a handsaw with 0.8 mm of teeth space. When cutting the cables, leave sufficient slack.

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    10

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    20/115

    NOTICE

    If you find the slack insufficient, replace the cables. Do not make connectors or solder joints.

    Step 3 Attach temporary labels to both ends of the cables. The contents on these temporary labels arenot necessarily the same as those on the formal labels because they are only for easy

    identification.

    Step 4 Lay out power cables and PGND cable between a cabinet and the PDF. Routed the power cablesfrom the PDF through the upper cable hole into the cable tray and then to the top of each

    cabinet along the cable tray.

    NOTE

    l If the space between a cable tray and the top of a cabinet exceeds 800 mm, use a cable ladder to facilitate

    the cable layout.

    l The bending radius of a cable must be five times larger than the diameter of the cable.

    Step 5 Connect the power cables and PGND cable for the cabinet.

    1. According to the installation position of each cable, determine the exact length required,

    and cut off any excess.

    2. Obtain the cable terminals delivered with the cabinet. For details, see Assembling the OT

    Terminal and the Power Cable. Crimp the OT terminals of the power cable and OT terminals

    of PGND cable for the cabinet.

    NOTE

    OT terminals (M6) are used for the -48 V and RTN power cables whereas OT terminals (M8) are

    used for PGND cable on the cabinet side. The type of OT terminals used on the PDF side is determined by the actual situation.

    NOTE

    To facilitate the crimping of OT terminals, crimp them on the ground with hydraulic pliers, and then

     place them in the installation positions.

    3. Remove the left and right plastic cover plates from the top rear of the cabinet and cut holes

    on the cover plates, matching the holes to the power cable inlets on the power distribution

     box.

    4. Place both cover plates back to their original positions.

    5. Through the hole on the cover plate on the top of the cabinet, connect OT terminals of the

    -48 V power cable to wiring terminals labeled "3(-)" and "1(-)" in both part A and part Bof the power distribution box, and connect OT terminals of the RTN power cable to wiring

    terminals labeled "3(+)" and "1(+)" in both part A and part B of the power distribution box.

    6. Connect the OT terminals of the -48 V power cable and RTN power cable to the wiring

    terminals in the power distribution box. .

    7. Secure the OT terminal of PGND cableto the ground bolt at the rear of the cabinet top.

    Step 6 Connect power cables and PGND cable to the PDF output terminals.

    1. According to the installation position of each cable, determine the exact length required,

    and cut off any excess.

    2. Obtain the cable terminals delivered with the cabinet. For details, see Assembling the OT

    Terminal and the Power Cable. Crimp the OT terminals of power cables and PGND cable.

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    11

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    21/115

    3. Connect the -48 V power cables, RTN power cables, and PGND cable to the corresponding

    wiring terminals on the power distribution box.

    NOTE

    When connecting OT terminals to the wiring terminals, add flat washers and spring washers, and

    assemble them in order.

    Figure 4-3 shows how to install an OT terminal.

    Figure 4-3 Installing an OT terminal

    (1) Cable (2) Heat shrink tubing (3) Nut

    (4) Spring washer (5) Flat washer (6) Wiring terminal

     

    4. Record the installation results in 12 Installation Records.

    ----End

    4.4.2 Installing Power Cables and PGND Cable Between theBSC6900 and the PDF in Underfloor Cabling Mode

    This section describes how to install power cables and PGND Cable between a cabinet and the

    PDF for the BSC6900 in underfloor cabling mode.

    Prerequisites

    l The cabinet to be connected with power cables and PGND Cable has been installed.

    l On the PDF, the power distribution switches for the relevant output terminals have been

    set to OFF.

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    12

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    22/115

    l All power distribution switches on the power distribution box have been set to OFF.

    l Power cables and PGND Cable are available.

    l The materials required for the installation are available. The materials include cable ties,

    wax strings, PVC insulation tape, and lifting sling.

    l The tools required for the installation are available. These tools include a handsaw, a cable

    cutter, a wrench, a Phillips screwdriver, a flat-head screwdriver, an electric Phillips

    screwdriver (> 5 N•m = 44.25 lbf•in.), diagonal pliers, and hydraulic pliers.

    Context

    If you are using the underfloor cabling mode, route the cables from the PDF through the cable

    hole under the PDF, to the bottom of the cabinet beneath the ESD floor to the top of the cabinet

    along the middle standing pillar. Figure 4-4Figure 4-5 shows how to install power cables and

    PGND Cable between a cabinet and the PDF in underfloor cabling mode.

    Figure 4-4 Installing power cables and PGND Cable in underfloor cabling mode

     

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    13

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    23/115

    Figure 4-5 Installing power cables and PGND Cable in underfloor cabling mode

     

    Procedure

    Step 1 Determine the length of each power cable and PGND cable by referring to the related engineeringdesign documents or by measuring the actual cabling route.

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    14

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    24/115

    Step 2 Uncoil the power cable roll and the PGND cable roll onsite. Measure an appropriate length of cables with a measuring tape or other measuring tools. Then, cut the cables with a cable cutter 

    (KT35) or a handsaw with 0.8 mm of teeth space. When cutting the cables, leave sufficient slack.

    NOTICE

    If you find the slack insufficient, replace the cables. Do not make connectors or solder joints.

    Step 3 Attach temporary labels to both ends of the cables. The contents on these temporary labels arenot necessarily the same as those on the formal labels because they are only for easy

    identification.

    Step 4 Lay out power cables and PGND Cable according to cable routing and engineering requirements.

    1. Route four pairs of power cables and one PGND cable from the cable outlet at the bottomof the PDF. Then route the cables under the ESD floor for the cabinet.

    2. Divide the four pairs of power cables into two groups . Use a temporary cable tie to bind

    one group with the PGND cable. Repeat this procedure with the other group. Route the two

    groups of cables to the middle standing pillars on the left and right sides of the cabinet,

    respectively.

    3. Place one end of the lifting sling on the top of the middle standing pillar. Route the other 

    end of the lifting sling to the bottom of the cabinet through the middle standing pillar, and

     bind it to the power cables and PGND cable at the bottom of the middle standing pillar.

    4. Pull the upper end of the lifting sling to lift the power cables and PGND cable to the top of 

    the cabinet along the middle standing pillar.

    5. Remove the lifting sling and the temporary cable ties on the power cables and PGND cable.

    Step 5 Connect power cables and the PGND cable to the cabinet.

    1. According to the installation position of each cable, determine the exact length required,

    and cut off any excess.

    2. Obtain the cable terminals delivered with the cabinet. For details, see Assembling the OT

    Terminal and the Power Cable. Crimp the OT terminals of the power cable and OT terminals

    of the PGND cable for the cabinet.

    NOTE

    OT terminals (M6) are used for the -48 V and RTN power cables on the cabinet side. OT terminals

    (M8) are used for PGND Cable. The type of OT terminals used on the PDF side is determined by theactual situation.

    To facilitate the crimping of OT terminals, crimp them on the ground with hydraulic pliers, and then

     place them in the installation positions.

    3. Remove the left and right plastic cover plates from the top rear of the cabinet and cut holes

    on the cover plates, matching the holes to the power cable inlets on the power distribution

     box.

    4. Place both cover plates back to their original positions.

    5. Through the hole on the cover plate on the top of the cabinet, connect OT terminals of the

    -48 V power cable to wiring terminals labeled "3(-)" and "1(-)" in both part A and part B

    of the power distribution box, and connect OT terminals of the RTN power cable to wiring

    terminals labeled "3(+)" and "1(+)" in both part A and part B of the power distribution box.

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    15

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    25/115

    6. Connect the OT terminals of the -48 V power cable and RTN power cable to the wiring

    terminals in the power distribution box. .

    7. Secure the OT terminals of PGND Cable to the ground bolt at the rear of the cabinet top.

    Step 6 Connect power cables and PGND Cable to the PDF output terminals.1. According to the installation position of each cable, determine the exact length required,

    and cut off any excess.

    2. Obtain the cable terminals delivered with the cabinet. For details, see Assembling the OT

    Terminal and the Power Cable. Crimp the OT terminals of power cables and PGND Cable.

    3. Connect the -48 V power cables, RTN power cables, and PGND Cable to the corresponding

    wiring terminals on the power distribution box.

    NOTE

    When connecting OT terminals to the wiring terminals, add flat washers and spring washers, and

    assemble them in order.

    Figure 4-6 shows how to install an OT terminal.

    Figure 4-6 Installing an OT terminal

    (1) Cable (2) Heat shrink tubing (3) Nut

    (4) Spring washer (5) Flat washer (6) Wiring terminal

     

    4. Record the installation results in 12 Installation Records.

    ----End

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    16

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    26/115

    4.5 Installing the PGND Cables Between Adjacent Cabinets

    This section describes how to connect the upper, middle, and lower parts of the PGND busbar 

    of one cabinet to those of its adjacent cabinet through PGND cables. PGND cables need to be

    installed in adjacent cabinets only when they are installed in combined mode.

    Prerequisites

    The power distribution switches for the relevant output terminals have been set to OFF.

    Procedure

    Step 1 As described in 4.2 Connections of Power Cables and PGND Cables, use inter-cabinet PGNDcables to connect the upper, middle, and lower PGND busbars on the mounting bar of adjacent

    cabinets as shown in Figure 4-7.

    Figure 4-7 Installing PGND cables for adjacent cabinets

     

    ----End

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    17

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    27/115

    Follow-up Procedure

    Record the installation results in 12 Installation Records.

    BSC6900 UMTS

    Installation Guide 4 Installing Power Cables and PGND Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    18

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    28/115

    5 Checking and Setting DIP Switches onSubracks

    This section describes how to check and set the DIP switch on a subrack. In general, subracks

    are installed in the cabinet before delivery.

    Prerequisites

    Subracks have been installed in the cabinet.

    Context

    NOTICE

    l Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before performing

    any operations. For details, see Wearing an ESD Wrist Strap.

    l DIP switches cannot be set after the cabinet is powered on. Therefore, check and set the DIP

    switches before powering on the cabinet.

    The DIP switch is used to set the subrack number. Figure 5-1 shows the cover of a DIP

    switch.

    Figure 5-1 DIP switch cover 

     

    BSC6900 UMTS

    Installation Guide 5 Checking and Setting DIP Switches on Subracks

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    19

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    29/115

    The bit 0 indicates the ON state, and the bit 1 indicates the OFF state. The most significant bit

    (MSB) of the DIP switch corresponds to the MSB of a byte. Table 5-1 provides the definition

    of each bit.

    Table 5-1 Definition of each DIP bit

    DIP Bit Definition

    1 (the least significant bit) Subrack number setting bit

    2 Subrack number setting bit

    3 Subrack number setting bit

    4 Subrack number setting bit

    5 Subrack number setting bit

    6 Odd parity check bit

    7 Reserved bit, generally set to ON

    8 (the most significant bit) Startup type of the subrack, generally set to

    OFF

    NOTE

    l For the inventory sites upgrading from

    BSC6000 to BSC6900, keep the former 

    settings.

    l For the new sites in BSC6900, the bit is

    conservative and is fixed to OFF.

     

    The DIP switch uses odd parity check, so the number of bits that are set to OFF must be odd.

    The setting is as follows:

    1. Set bit 1 to bit 5.

    2. Set bit 7 to ON.

    3. Set bit 8 to OFF.

    4. Count the number of bits that are set to OFF.

    l

    If the number of bits is even, set bit 6 to OFF.l If the number of bits is odd, set bit 6 to ON.

    Table 5-2 lists the DIP switch setting.

    BSC6900 UMTS

    Installation Guide 5 Checking and Setting DIP Switches on Subracks

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    20

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    30/115

    Table 5-2 DIP switch setting

    SubrackNo.

    DIP Bit DIP SwitchSetting 

    1 2 3 4 5 6 7 8

    0 0 0 0 0 0 0 0 1

    ON ON ON ON ON ON ON OFF

    1 1 0 0 0 0 1 0 1

    OFF ON ON ON ON OFF ON OFF

    2 0 1 0 0 0 1 0 1

    ON OFF ON ON ON OFF ON OFF

    3 1 1 0 0 0 0 0 1

    OFF OFF ON ON ON ON ON OFF

    4 0 0 1 0 0 1 0 1

    ON ON OF

    F

    ON ON OFF ON OFF

    5 1 0 1 0 0 0 0 1

    OFF ON OF

    F

    ON ON ON ON OFF

     

    Procedure

    Step 1 Loosen the screws on the cover of the DIP switch by turning them counterclockwise for two or three circles, as shown in Figure 5-1.

    Step 2 Turn the cover around the lower right screw and open the cover. Set the DIP switch.

    Step 3 Attach a formal label or temporary label to the subrack. The contents on the temporary label arenot necessarily the same as those on the formal labels because they are used for identifying a

    subrack during BSC6900 software commissioning.

    ----End

    Follow-up Procedure

    Record the checking and setting results of the DIP switch in 12 Installation Records.

    BSC6900 UMTS

    Installation Guide 5 Checking and Setting DIP Switches on Subracks

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    21

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    31/115

    6 Checking the Power-On Performance ofCabinet

    This section describes how to check the power supply to cabinets, fan assembly, and boards.

    Prerequisites

    l Power cables and PGND cables between a cabinet and the PDF are installed.

    l Subracks, fan assemblies, and boards are installed.

    l A multimeter required for the installation is available.

    Context

    The cabinet uses a DC power supply. For details, see Technical Specifications of the Power 

    Distribution Box.

    NOTICE

    Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before performing

    any operations.

    You need not to remove the board for performing the power-on check. During powering on a

    subrack, do not insert a board into or remove a board from the subrack to avoid static damageto boards.

    Procedure

    Step 1 Set the corresponding output switches on the PDF and all the output switches on the power distribution box to OFF.

    Step 2 Use the multimeter to measure the resistance at the power output terminal for the PDF and atthe input and output terminals for the power distribution box. Ensure that short-circuiting does

    not occur either between the -48 V working power and the RTN working ground or between the

    -48 V working power and the PGND protection ground.

    BSC6900 UMTS

    Installation Guide 6 Checking the Power-On Performance of Cabinet

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    22

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    32/115

    Step 3 Set the output switches on the PDF to ON and all the output switches on the power distribution box to OFF.

    Then, the power distribution box starts self-check. (The RUN and ALM indicators on the power 

    distribution box are on and the buzzer sounds.) After the self-check, the power distribution box

    requests registering at the SCUb board (the RUN indicator on the power distribution box blinksat 2 Hz) until the registration is successful (the RUN indicator blinks at 0.5 Hz). For details about

    the indicators on the power distribution box, see Indicators on the Power Distribution Box.

    Step 4 Set the multimeter to the voltage scale. Use the multimeter to measure the output voltage of thePDF or the input voltage of the power distribution box. Ensure that the voltages range from -40

    V to -57 V.

    Step 5 Set the corresponding two switches on the power distribution box to ON.

    Step 6 Set the multimeter to the voltage scale. Use the multimeter to check whether the output power  provided by the power distribution box for each subrack ranges from -40 V to -57 V. Check 

    whether the fan assembly in the subrack can be normally started and whether the power supply

    to the boards in the subrack is normal.

    l If a subrack is powered on and started normally, the green STATUS indicator on the panel

    of the fan assembly blinks. If exceptions occur, turn off the switches on the power distribution

     box and the PDF immediately. Check whether the output voltage of the power distribution

     box is normal and the power cables are installed correctly. For details about the indicators

    on the fan assembly, see Indicators on the Fan Assembly.

    l If a subrack is powered on and started normally, the RUN indicator on the board panel is ON

    or blinks. If all the indicators on a board are OFF, the board or its slot may be faulty. Contact

    Huawei technical support to resolve this problem.

    l If indicators on all the boards in a subrack are OFF, turn off the switches on the power 

    distribution box and the PDF immediately. Check whether the output voltage of the power distribution box is normal and the power cables are installed correctly.

    Step 7 Repeat Step 5 to Step 6 to check the power supply to all the subracks in one cabinet.

    Step 8 Repeat Step 1 to Step 7 to measure the power supply to each cabinet.

    ----End

    Follow-up Procedure

    Record the power-on check results in 12 Installation Records. Set the corresponding output

    switches on the PDF and all the output switches on the power distribution box to OFF.

    BSC6900 UMTS

    Installation Guide 6 Checking the Power-On Performance of Cabinet

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    23

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    33/115

    7 Installing and Setting BoardsAbout This Chapter

    Most boards except the OMUa/OMUc/SAUa/SAUc boards are installed in subracks before the

    delivery. If AEUa/AOUa/PEUa/PEUc/POUa/PAMU/PFCU boards are installed in the cabinet,

    check and set the DIP switches of the boards. Install the OMUa/OMUc/SAUa/SAUc boards

    onsite.

    7.1 Safety Pr ecautions for Board Installation

    This section describes the precautions you must take when you install, remove, or replace the

     boards, or perform any other operation that requires bodily contact with the boards.

    7.2 Installing the OMUa/OMUc/SAUa/SAUc Boards

    This section describes how to install the OMUa/OMUc/SAUa/SAUc board in the MPS.

    7.3 Checking and Setting the DIP Switch on the Board

    The boards are installed in the subrack before delivery. If the AEUa/AOUa/PEUa/PEUc/

    POUa /PAMU/PFCU board is configured in the cabinet, you need to check and set the DIP

    switches of the AEUa/AOUa/PEUa/PEUc/POUa/PAMU/PFCU board.

    7.4 DIP Switches on the BSC6900 Boards

    This section describes the DIP switches on the BSC6900 AEUa/AOUa/PEUa/PEUc/POUa

     boards and the PAMU/PFCU boards.

    BSC6900 UMTS

    Installation Guide 7 Installing and Setting Boards

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    24

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    34/115

    7.1 Safety Precautions for Board Installation

    This section describes the precautions you must take when you install, remove, or replace the boards, or perform any other operation that requires bodily contact with the boards.

    Precautions Before Operation

    l Store materials for board installation (such as ESD boxes and bags) in the equipment room

    for future use.

    l Keep the boards and other electrostatic-sensitive parts in ESD bags. Do not pack or hold

    the boards or parts by using plastic foam, common plastic bags, or paper bags.

    l Ensure that the cabinet is well grounded before inserting the board into the subrack.

    Otherwise, the board mill be severely damaged.

    l Ensure that the wrist strap is functioning. The value of the resistance measured by the

    multimeter must range from 0.8 megohm to 1.2 megohms.

    l see Wearing an ESD Wrist Strap for the method of measuring the resistance.

    Precautions During Operation

    l Wear an ESD wrist strap or gloves and ensure that the ESD wrist strap is well grounded.

    l See Wearing an ESD Wrist Strap for the procedure for wearing an ESD wrist strap or gloves.

    l Place the board on an ESD pad when replacing board hardware or chips. Use ESD tweezers

    or extraction tools to replace chips. Do not touch board chips or pins with your bare hands.

    l Discharge the static electricity of the cables and protective sleeves before connecting them

    to the ports.

    l Do not touch the PCB or any other part except jumpers and DIP switches during board

    replacement.

    l Place the removed boards and components on an ESD pad or other ESD materials. Do not

     pack or hold the boards or parts by using plastic foam, common plastic bags, or paper bags.

    7.2 Installing the OMUa/OMUc/SAUa/SAUc Boards

    This section describes how to install the OMUa/OMUc/SAUa/SAUc board in the MPS.

    Prerequisites

    l The tools required for the installation are available. The tools include ESD wrist strap or 

    gloves and Phillips screwdriver.

    l The boards to be installed are available.

    Context

    For the position of the OMUa/OMUc/SAUa/SAUc board in the subrack, see Configuration of 

    a Subrack and Principles for Installing Boards.

    BSC6900 UMTS

    Installation Guide 7 Installing and Setting Boards

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    25

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    35/115

    Procedure

    Step 1 Remove the board from the ESD box, and then check the pins and sockets of the board.

    In case of any bent, missing or broken pins, or any deformed sockets, contact Huawei engineers

    to replace the board.

    Step 2 As shown in part a of Figure 7-1, press the self-locking latches on the front panel and turn theejector levers outwards until the ejector levers cannot be turned further. Check that the ejector 

    levers are located in the positions shown in part 2 of Figure 7-1.

    Step 3 Hold the panel of the board with one hand and support the board with the other. Then, slide the board into the subrack along the guide rail until the ejector levers are half closed, as shown in

     part 3 of Figure 7-1.

    NOTICEWhen inserting the board into the subrack, push the board slowly and steadily to avoid damaging

    the pins on the backplane and the metal piece on the board.

    Figure 7-1 Installing the board

     

    BSC6900 UMTS

    Installation Guide 7 Installing and Setting Boards

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    26

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    36/115

    Step 4 As shown in part 4 of Figure 7-1, turn the two ejector levers inwards at an angle of about 60°until they hook on to the self-locking latches on the front panel. Ensure that the board is in close

    contact with the backplane and that the front panel is inserted into the subrack.

    Step 5 Press and fasten the screws on the front panel to secure the board, as shown in part b of Figure7-1.

    NOTE

    The screws on the front panel have springs. Therefore, the screws can touch the corresponding holes of the

    subrack only when you press the screws.

    ----End

    Follow-up Procedure

    Record the installation result in the templates provided in 12 Installation Records.

    7.3 Checking and Setting the DIP Switch on the Board

    The boards are installed in the subrack before delivery. If the AEUa/AOUa/PEUa/PEUc/

    POUa /PAMU/PFCU board is configured in the cabinet, you need to check and set the DIP

    switches of the AEUa/AOUa/PEUa/PEUc/POUa/PAMU/PFCU board.

    Prerequisites

    l The tools required for setting the DIP switches are available. The required tools are ESD

    wrist strap, ESD gloves, ESD pad, ESD tweezers, Phillips screwdriver and flat-head

    screwdriver.

    l The DIP switches on the board are found.

    l The actual transmission mode on site is determined.

    Context

    Before delivery, the DIP switches on the AEUa/AOUa/PEUa/PEUc/POUa/PAMU/PFCU board

    are set by default. The settings of the DIP switches on the AEUa/AOUa/PEUa/PEUc/POUa/

    PAMU/PFCU board should be checked according to the transmission mode used onsite and the

    slots housing the boards. If the settings do not match the actual conditions, you need to adjust

    the settings of the DIP switches.

    The PFCU board is installed in the front of the fan box. Operators only need to pull the fan box

    out of the subrack and check the DIP switches on the PFCU board.

    NOTICE

    Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before you perform

    the operation. For details, see Wearing an ESD Wrist Strap.

    BSC6900 UMTS

    Installation Guide 7 Installing and Setting Boards

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    27

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    37/115

    Procedure

    Step 1 Determine the position of the AEUa/AOUa/PEUa/PEUc/POUa/PAMU/PFCU board in thesubrack, and then remove any of the preceding board from the subrack. For details on how to

    remove the AEUa/AOUa/PEUa/PEUc/POUa board, see Removing the Board. For details on

    how to remove the PAMU board, see steps 3 to 6 in Replacing a PAMU Board. For details on

    how to remove the PFCU board, see steps 2 to 4 in Replacing a Fan Assembly.

    Step 2 Determine the proper settings of the DIP switches based on the board type, actual transmissionmode onsite, or the slot that housing the board.

    Step 3 Check whether the settings of the DIP switches on the board match the actual conditions.

    If... Then...

    The settings of the DIP switches on the

    board match the actual conditions

    Do no modify the settings of the DIP switches.

    Go to Step 5.

    The settings of the DIP switches on the

    board do not match the actual conditions

    Modify the settings of the DIP switches by

     performing Step 4.

    Step 4 Wear the ESD gloves and place the board on the ESD pad. Then, use the tweezers to set thetarget DIP bits to the correct positions with moderate force.

    l For details about the settings of the DIP switches on the AEUa board, see DIP Switches on

    the AEUa Board.

    l For details about the settings of the DIP switches on the AOUa board, see DIP Switches on

    the AOUa Board.

    l For details about the settings of the DIP switches on the PEUa board, see DIP Switches on

    the PEUa Board.

    l For details about the settings of the DIP switches on the PEUc board, see DIP Switches on

    the PEUc Board.

    l For details about the settings of the DIP switches on the POUa board, see DIP Switches on

    the POUa Board.

    l For details about the settings of the DIP switches on the PFCU board, see DIP Switch on the

    PFCU Board.

    l For details about the settings of the DIP switches on the PAMU board, see DIP Switch on

    the PAMU Board.

    Step 5 Install the board in its original slot. For details on how to install the AEUa/AOUa/PEUa/PEUc/POUa boards, see Installing the Board. For details on how to install the PAMU board, see steps

    7 to 12 in Replacing a PAMU Board. For details on how to install the PFCU board, see steps 5

    to 7 in Replacing a Fan Assembly.

    Step 6 Check and set all the DIP switches on the board by repeating steps Step 1 to Step 5.

    ----End

    Follow-up Procedure

    Record the checking and setting results of the DIP switches on the AEUa/AOUa/PEUa/PEUc/

    POUa/PAMU/PFCU board in the templates provided in 12 Installation Records.

    BSC6900 UMTS

    Installation Guide 7 Installing and Setting Boards

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    28

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    38/115

    7.4 DIP Switches on the BSC6900 Boards

    This section describes the DIP switches on the BSC6900 AEUa/AOUa/PEUa/PEUc/POUa

     boards and the PAMU/PFCU boards.

    Table 7-1 DIP Switches on BSC Components

    DIP Switches onBSC Components

    Description

    DIP Switch on the

    AEUa Board

    For details, see BSC6900 Hardware DescriptionDIP Switches on

    the AEUa Board

    DIP Switch on the

    AOUa Board

    For details, see BSC6900 Hardware DescriptionDIP Switches on

    the AOUa Board

    DIP Switch on the

    PEUa Board

    For details, see BSC6900 Hardware DescriptionDIP Switches on

    the PEUa Board

    DIP Switch on the

    PEUc Board

    For details, see BSC6900 Hardware DescriptionDIP Switches on

    the PEUc Board

    DIP Switch on the

    POUa Board

    For details, see BSC6900 Hardware DescriptionDIP Switches on

    the POUa Board

    BSC6900 UMTS

    Installation Guide 7 Installing and Setting Boards

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    29

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    39/115

    8 Installing the Signal CablesAbout This Chapter

    This chapter describes how to install the signal cables according to the layout requirements. The

    signal cables to be installed include clock signal cables, Ethernet cables, E1/T1 cables and optical

    cables. For items and specifications for checking the installation of signal cables, see 11.1

    Checklist for BSC6900 Cable Installation.

    8.1 Signal Ca bles to Be Installed

    This section describes the signal cables to be installed on site.

    8.2 Principles of Installing Signal CablesThis section describes principles of installing signal cables. The principles involve minimum

     bending radius, cable layout, cable routing, and cable binding.

    8.3 Installing the Clock Signal Cables

    The clock signal cables refer to the Y-shaped clock signal cable, line clock signal cable and the

    BITS clock signal cable.

    8.4 Installing the Ethernet Cables

    This section describes how to install the Ethernet cables. These cables are the inter-SCUa cable,

    the Ethernet cable between the OMUa/OMUc board and the U2000 or the LAN of the customer,

    and the Ethernet cable between the FG2a/FG2c board and the other device.

    8.5 Installing the E1/T1 CablesThis section describes how to install the E1/T1 cables between the AEUa/PEUa/PEUc board

    and the DDF.

    8.6 Installing the Optical Cables

    This section describes how to install the optical cables between the AOUa/AOUc/GOUa/GOUc/

    GOUe/POUa/POUc/UOIa/UOIc board and the other equipment.

    8.7 Installing the EMU RS485 Communication Cables

    This section describes how to install the EMU RS485 communication cable between the

    BSC6900 and the EMU.

    8.8 Connecting the GPS Surge Protector to the GCGa/GCGb Board

    BSC6900 UMTS

    Installation Guide 8 Installing the Signal Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    30

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    40/115

    For cabinets equipped with the GCGa/GCGb board, install an indoor surge protector on the top

    of the cabinet. Use the cable for the input of the satellite signals to connect the port Protect of 

    the GPS surge protector on the top of the cabinet and the port ANT on the GCGa/GCGb board.

    BSC6900 UMTS

    Installation Guide 8 Installing the Signal Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    31

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    41/115

    8.1 Signal Cables to Be Installed

    This section describes the signal cables to be installed on site.

    Table 8-1 lists the signal cables to be installed.

    Table 8-1 Signal cables

    Name Cable Type Function Remarks

    Clock 

    signal

    cables

    Y-shaped clock 

    cable

    Connects the GCUa/

    GCGa/GCUb/GCGb

     board to the SCUb board.

    BSC6900 uses the BITS clock 

    cables to transmit the reference

    clock signals extracted from the

    BITS clock source, see 8.3

    Installing the Clock Signal

    Cables.

    Line clock 

    signal cable

    Connects the BSC6900

    interface board to theGCUa/GCGa/GCUb/

    GCGb board.

    BITS clock 

    signal cable

    Connects the GCUa/

    GCGa/GCUb/GCGb

     board to the BITS clock.

    Ethernet

    cable

    Unshielded

    straight-

    through cable

    Connects the SCUb boards

    in the main BM and TC

    subracks.

    When the capacity of a site is

    expanded, the inter-SCUb cables

    need to be made and installed on

    site, see Installing the Inter-

    SCUb SFP+ High-Speed CablesBetween Different Subracks.

    NOTE

    GE ports numbered from 0 to 7 are

    recommended for the

    interconnection between SCUb

     boards.

    Shielded

    straight-

    through cable

    Connects the OMUc/

    SAUc board to the U2000

    or the LAN of the

    customer.

    The shielded straight-through

    cables are made before delivery.

    Connects the FG2a/FG2c

     board to other devices.

    E1/T1

    cable

    75-ohm coaxial

    cable

    Connects the AEUa/PEUa/

    PEUc board to the DDF.

    The coaxial cables or twisted

     pair cables are selected

    according to the site survey, see

    8.5 Installing the E1/T1

    Cables.

    Active/standby

    75-ohm coaxial

    cable

    120-ohm

    twisted pair 

    cable

    BSC6900 UMTS

    Installation Guide 8 Installing the Signal Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    32

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    42/115

    Name Cable Type Function Remarks

    Active/standby

    120-ohm

    twisted pair cable

    Optical

    cable

    LC/PC-LC/PC

    single-mode/

    multimode

    optical cable or 

    LC/PC-FC/PC

    single-mode/

    multimode

    optical cable or 

    LC/PC-SC/PC

    single-mode/multimode

    optical cable

    Connects the AOUa/

    AOUc/GOUa/GOUc/

    GOUe/POUa/POUc/

    UOIa/UOIc board to the

    ODF.

    The single-mode optical cables

    are yellow, and the multimode

    optical cables are orange, see 8.6

    Installing the Optical Cables.

    High-

    speed

    cable

    SFP+ high-

    speed cable

    Connects SCUb boards in

    different subracks.

    When a new site is deployed, the

    inter-SCUb cables are already

    installed on the MPR cabinet

    configured with two or three

    subracks or the TCR cabinet.

    When the capacity of a site is

    expanded, the inter-SCUb cables

    need to be made and installed on

    site, see Installing the Inter-

    SCUb SFP+ High-Speed Cables

    Between Different Subracks.

    NOTE

    10GE ports numbered from 8 to 11

    are recommended for the

    interconnection between SCUb

     boards.

    Other 

    signal

    cables

    EMU RS485

    communicatio

    n cable

    Connects the power 

    distribution box to the

    EMU.

    The crossover cables are made

     before delivery.

    Signal cable of 

    the alarm box

    Connects the alarm box to

    the Local Maintenance

    Terminal (LMT) PC.

    The crossover cables are made

     before delivery.

     

    For details about the signal cables, see Cables.

    BSC6900 UMTS

    Installation Guide 8 Installing the Signal Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    33

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    43/115

    8.2 Principles of Installing Signal Cables

    This section describes principles of installing signal cables. The principles involve minimum bending radius, cable layout, cable routing, and cable binding.

    Principles of Installing Signal Cables

    When installing signal cables, take the following precautions:

    l Optical cables should not be stretched roughly or stepped on, and heavy objects should not

     be placed on the cable to avoid damage.

    l Optical connectors not in use must be covered with a dustproof cap.

    l If connectors of signal cables are made before delivery, pack the connectors with soft and

    durable materials such as a packing bag during cabling.

    l Protect jackets of signal cables from being damaged during the routing.

    l When coiling the extra length of optical cables on the fiber management tray, apply proper 

    force to avoid damaging the optical.

    l The actual installation positions must meet the requirements of site survey and data

    configur ation.

    l When installing the signal cables, you should route the extra length of the interconnection

    cables on both sides of the cabinet according to the requirement for the bending radius of 

    the cables.

    lThe related operation guide is intended for only the installation method. The actualinstallation position of cables should meet the requirements of site survey and should be

    consistent with the data configuration scheme.

    Minimum Bending Radius

    The bending radius of the signal cable meets the requirements of all types of cables. Table

    8-2 lists the bending radius of the signal cables.

    Table 8-2 Requirements for the bending radius

     Wire Bending Radius

    BITS clock signal cable Not less than 45 mm

    Y-shaped clock cable Not less than 25 mm

    Ethernet cable Not less than 25 mm

    Optical cable Not less than 40 mm

    SFP+ high-speed cable Not less than 40 mm

    E1/T1 cable Not less than 40 mm

    EMU RS485 Communication Cable Not less than 25 mm

    BSC6900 UMTS

    Installation Guide 8 Installing the Signal Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    34

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    44/115

     Wire Bending Radius

    OMUc serial cable

    NOTE

    The port does not require a signal cableor connection to other devices when the

    system runs properly. Therefore,

    equipment security is not affected.

     Not less than 25 mm

    Signal cable of the alarm box Not less than 25 mm

     

    Principles of Routing the Signal Cables

    To facilitate maintenance and capacity expansion, follow these principles when routing cables.

    The layout sequence in over head and underfloor cabling modes must be the same.

    l The cables can be routed either on the front side first or on the rear side first. The cables

    meant for the front of the cabinet must be laid only in the front side of the cabinet. Follow

    the same principle for the cables meant for the rear of the cabinet.

    l whereas routing the cables at the back of the cabinet, you should route the E1/T1 cables

     before routing the optical cables.

    Requirements of Routing the Signal Cables

    The requirements for routing signal cables are as follows:

    l Protect the jackets of the signal cables from being damaged during the routing.

    l Hold the connector when plugging out the signal cables to protect the signal cable from

    damage.

    l When installing the signal cables, you should route the extra length of the interconnection

    cables on both sides of the cabinet according to the requirement for the bending radius of 

    the cables.

    l For combined cabinets, the extra signal cable in front of the cabinet should be routed along

    the cable ladder or at one side of the cabinet. It should not be placed in the gap between the

    combined cabinets.

    l

    The signal cables must be separated from the power cables.l The bending radius of the signal cable satisfies the requirements of all kinds of cables.

    Table 8-2 lists the bending radius of the signal cables.

    l Extra length of the signal cable should be reserved near the connector.

    l The signal cables must be neatly laid in the rack, according to the engineering design.

    l If the height difference between the cable tray and the top of the cabinet exceeds 800 mm,

    a vertical cable ladder must be used. The signal cables and the lower part of the downward

    cable ladder must be bound together.

    l The routing should be in accordance with the engineering design.

    l The cabling is clear, proper, and smooth at the bends. The cables are laid in parallel.

    l The signal cables layout facilitates maintenance and future expansion.

    BSC6900 UMTS

    Installation Guide 8 Installing the Signal Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    35

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    45/115

    Requirements of Binding the Signal Cables

    The requirements of binding the signal cables are as follows:

    l The signal cables and power cables must be bound separately. The spacing between cable

    ties must be at least 150 mm.

    l The twine for binding the cables must be coated with wax.

    l The signal cables must be bound at the entrance and exit of the cable trough and at the

    turning points, as shown in Figure 8-1.

    Figure 8-1 Bending and binding signal cables

     

    l The optical cables must be neatly bound in pairs.

    l The cables on the cable tray must be bound neatly.

    l The cable ties must face the same direction and be tied with proper tightness.

    l The cable ties must be placed at regular intervals, 200 mm for E1/T1 cables , and 150 mm

    for optical cables.

    l The extra length of the cable ties must be cut and the cut surface must be smooth.

    8.3 Installing the Clock Signal Cables

    The clock signal cables refer to the Y-shaped clock signal cable, line clock signal cable and the

    BITS clock signal cable.

    8.3.1 Installing the Y-Shaped Clock Cables

    This section describes how to install the Y-shaped clock cables between the GCUa/GCUb/

    GCGa/GCGb board in the MPS and the SCUa/SCUb board in the EPS. When a new site is

    deployed, the Y-shaped clock cables are already installed on the MPR cabinet configured with

    two or three subracks. When the capacity of a site is expanded, the Y-shaped clock cables need

    to be installed on site.

    Prerequisites

    l The Y-shaped clock cables required for the installation are available.

    l The required cable ties and wax strings are available.

    BSC6900 UMTS

    Installation Guide 8 Installing the Signal Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    36

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017c10_01)(PDF)-En

    46/115

    l The tools required for the installation are available. The tools are ESD gloves or ESD wrist

    strap, and cable cutter.

    l The wires in the Y-shaped clock cables are intact, the jacket of the cable is undamaged,

    and the pins in the connector are straight.

    Context

    NOTICE

    Wear an ESD wrist strap and connect it to the ESD connector on the cabinet before you perform

    the operation. For details, see Wearing an ESD Wrist Strap.

    For the installation positions of the Y-shaped clock cables in the cabinet, see Connections of Signal Cables for the MPR.

    The Y-shaped clock cable has three specifications in length: 2.0 m, 2.5 m, and 9.7 m. The 2.0

    m cable is used to connect the GCUa/GCUb/GCGa/GCGb board to the SCUa/SCUb board in

    two adjacent subracks in one cabinet. The 2.5 m cable is used to connect the GCUa/GCUb/

    GCGa/GCGb board to the SCUa/SCUb board in different subracks in one cabinet. The 9.7 m

    cable is used to connect the GCUa/GCUb/GCGa/GCGb board to the SCUa/SCUb board in

    different cabinets.

    Procedure

    Step 1 Attach formal labels to identify the signal cables of the same type when the number of signalcables of the same type to be installed is more than one.

    Step 2 Put one end with an RJ45 connector to the SCUa/SCUb board. Take one end of the cable thathas two RJ45 connectors and lead it from the SCUa/SCUb board to the distribution post in the

    cable trough. Estimate the length of the cable between the SCUa/SCUb board and the GCUa/

    GCUb/GCGa/GCGb board. The bending radius must be at least 25 mm. Then, bind the cable

    and the distribution post. Route the cable along the cable trough to the GCUa/GCUb/GCGa/

    GCGb board.

    Step 3 Route the cable to the GCUa/GCUb/GCGa/GCGb according to the requirements specified in

    8.2 Principles of Installing Signal Cables and the engineering requirements. The cabling of the Y-shaped clock cables is described in Table 8-3.

    Table 8-3 Cabling of the Y-shaped clock cables

    Condition Cabling mode Action

    The SCUa/SCUb and the

    GCUa/GCUb/GCGa/GCGb

    are located in the same

    cabinet.

    Cabling within the cabinet Lead the optical cables to the

    GCUa/GCUb/GCGa/GCGb

     board through the cable

    trough beneath the MPS

    along the column of the

    cabinet.

    BSC6900 UMTS

    Installation Guide 8 Installing the Signal Cables

    Issue 01 (2015-03-25) Huawei Proprietary and Confidential

    Copyright © Huawei Technologies Co., Ltd.

    37

  • 8/18/2019 Bsc6900 Umts Installation Guide(v900r017